Milestone Summary For Project | |||||||||||||
Sector Name : | COAL. | ||||||||||||
Agency Name : | WESTERN COAL FIELDS LIMITED. | ||||||||||||
Project Name : | AMALGAMATED YEKONA-I YEKONA-II. |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
17 | Total Additional Capital - Rs.727.28 Crores | 0 | 4/2016 | 3/2022 | 0/0 | 0/0 | 0/0 | No | / | 70 | On going | No | WCL |
3 | Land Acquisition & Payment of Compensation | 0 | 4/2016 | 3/2020 | 0/0 | 0/0 | 0/0 | No | / | 96 | On going | No | WCL |
9 | CHP | 0 | 4/2016 | 9/2018 | 0/0 | 0/0 | 0/0 | No | / | 12 | On going | No | WCL |