Milestone Summary For Project | |||||||||||||
Sector Name : | COAL. | ||||||||||||
Agency Name : | SOUTH-EASTERN COAL FIELDS LIMITED. | ||||||||||||
Project Name : | AMGAON OPENCAST PROJECT RCE. |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
A2 | Stage-I forestry clearance of 93.58 Ha forest land | 0 | 8/2015 | 10/2018 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
A4 | Final forestry clearance | 0 | 4/2017 | 2/2021 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
A6 | Disbursement of compensation for 50% of land of Patna village | 0 | 4/2018 | 3/2020 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes |