Milestone Summary For Project | |||||||||||||
Sector Name : | COAL. | ||||||||||||
Agency Name : | WESTERN COAL FIELDS LIMITED. | ||||||||||||
Project Name : | NILJAI EXPANSION (DEEP) OC (3.5 MTY). |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
1 | Land Acquisition and physical possession of land | 0 | 8/2016 | 10/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | WCL |
2 | Rehabilitation and Resettlement | 0 | 8/2017 | 3/2020 | 0/0 | 0/0 | 0/0 | No | / | 40 | On going | No | WCL, MH State |
3 | Procurement & Installation of Slope Monitoring Radar | 0 | 6/2020 | 3/2021 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | WCL |