Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
2 | Permanent Power supply arrangement | 0 | 6/2020 | 6/2021 | 0/0 | 0/0 | 0/0 | No | / | 80 | On going | No | |
3 | Acquisition & Physical possession of Land for inclines and infrastructure | 0 | 10/2019 | 12/2020 | 0/0 | 0/0 | 0/0 | No | / | 82 | On going | No | |
5 | Environmental Clearance | 0 | 1/2020 | 12/2020 | 0/0 | 0/0 | 0/0 | No | / | 52 | On going | No | |
6 | Incline Drivage | 0 | 1/2021 | 12/2022 | 0/0 | 0/0 | 0/0 | No | / | 10 | On going | No | |
7 | Award of work for Hiring of CM Package | 0 | 10/2021 | 6/2022 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |