Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
1 | Achieving 15% physical progress by March 2018 | 0 | 4/2017 | 3/2018 | 0/0 | 0/0 | 0/0 | No | / | 15.2 | Completed | No | IndianOil Corporation Ltd |
2 | Purchase Order for Mainline pipe of Ennore to Manali Refinery section | 0 | 6/2017 | 10/2017 | / | / | 0/0 | No | / | | Completed | No | IndianOil Corporation Ltd. |
3 | Delivery of mainline pipe for Ramanathapura-Tuticorin section | 0 | 4/2018 | 10/2018 | / | / | 0/0 | No | / | 100 | Completed | No | IOCL |
4 | Award of work order for Mainline and combined station works RTPL | 0 | 4/2018 | 11/2018 | / | / | 0/0 | No | / | 100 | Completed | No | IOCL |
5 | Achieving 47.70% physical progress by March 2020 | 0 | 4/2019 | 3/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | IOCL |