Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
1 | Engagement of PMC | 0 | 12/2016 | 12/2016 | / | / | 0/0 | No | / | | Completed | No | |
10 | Tendering - Terminal Work | 0 | 1/2018 | 1/2018 | / | / | 0/0 | No | / | | Completed | No | |
11 | Ordering - Pipeline Laying Works | 0 | 3/2018 | 3/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
12 | Start issue of section-8 notices | 0 | 3/2018 | 3/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
13 | Submission of all crossings and statutory permission application | 0 | 3/2018 | 3/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
14 | Ordering - Terminal Work | 0 | 4/2018 | 4/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
15 | Start of Delivery of Line pipe | 0 | 5/2018 | 5/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
16 | Pipeline Laying Progress-25% | 0 | 10/2018 | 10/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
17 | Delivery complete - Mainline Line Pipe | 0 | 2/2019 | 2/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
18 | Pipeline Laying Progress-50% | 0 | 2/2020 | 2/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
19 | Receipt of all Crossings and statutory permissions | 0 | 3/2019 | 3/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
2 | Completion of detailed Route Survey | 0 | 12/2016 | 12/2016 | / | / | 0/0 | No | / | | Completed | No | |
20 | Complete RoU opening | 0 | 4/2019 | 4/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
21 | Pipeline Laying Progress-75% | 0 | 5/2019 | 5/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
22 | Pipeline Laying Progress -100% | 0 | 8/2019 | 8/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
23 | Mechanical Completion ( Laying & Terminal ) | 0 | 8/2019 | 8/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
24 | Pre-commissioning & commissioning of Pipeline | 0 | 9/2019 | 9/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
3 | Submission of design basis | 0 | 6/2017 | 6/2017 | / | / | 0/0 | No | / | | Completed | No | |
4 | Tendering - Mainline Line Pipe | 0 | 6/2017 | 6/2017 | / | / | 0/0 | No | / | | Completed | No | |
5 | Tendering - Mainline Ball Valve | 0 | 6/2017 | 6/2017 | / | / | 0/0 | No | / | | Completed | No | |
6 | Tendering - Pipeline Laying Works | 0 | 10/2017 | 10/2017 | / | / | 0/0 | No | / | | Completed | No | |
8 | Ordering - Mainline Line Pipe | 0 | 1/2018 | 1/2018 | / | / | 0/0 | No | / | | Completed | No | |
9 | Ordering - Mainline Ball Valve | 0 | 1/2018 | 1/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |