Milestone Summary For Project | |||||||||||||
Sector Name : | PETROLEUM. | ||||||||||||
Agency Name : | GAS AUTHORITY OF INDIA LIMITED. | ||||||||||||
Project Name : | LAYING OF VIJAIPUR-AURAIYA PIPELINE SECTION OF VIJAIPUR-AURAIYA-PHULPUR PIPELINE PROJECT. |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
22 | Pipeline Laying Progress -100% | 0 | 8/2019 | 8/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
23 | Mechanical Completion ( Laying & Terminal ) | 0 | 8/2019 | 8/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
24 | Pre-commissioning & commissioning of Pipeline | 0 | 9/2019 | 9/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No |