Milestone Summary For Project | |||||||||||||
Sector Name : | RAILWAYS. | ||||||||||||
Agency Name : | WEST CENTRAL RAILWAY. | ||||||||||||
Project Name : | SATNA - REWA (50 KM). |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
STHR | Satna - Hinauta Ramban | 0 | 1/2017 | 8/2022 | 0/0 | 0/0 | 8/2022 | No | / | 100 | Completed | No | WCR Jabalpur |
TR | Turky-Rewa | 0 | 5/2017 | 3/2019 | 0/0 | 0/0 | 3/2019 | No | / | 100 | Completed | No | WCR Jabalpur |