Milestone Summary For Project | |||||||||||||
Sector Name : | RAILWAYS. | ||||||||||||
Agency Name : | WEST CENTRAL RAILWAY. | ||||||||||||
Project Name : | SATNA - REWA (50 KM). |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
HRT | Hinauta Ramban -Turky | 0 | 11/2016 | 6/2024 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | WCR Jabalpur |