S No. | Project Title | Agency Name | Sector Name | Date Of Approval | Cost Original | Cost Anticipated | Month |
1. | CITY GAS DISTRIBUTION NETWORK PROJECT AT SANGLI AND SATARA | BHARAT PETROLEUM CORPORATION LIMITED | PETROLEUM | 04/2019 | 2337.98 | 2337.98 | MAR |
2. | CITY GAS DISTRIBUTION NETWORK PROJECT AT AHMEDNAGAR AND AURANGABAD | BHARAT PETROLEUM CORPORATION LIMITED | PETROLEUM | 04/2019 | 3972.18 | 3972.18 | MAR |
3. | RESIDENTIAL COMPLEX AND OPD BLOCK, AIIMS, NAGPUR MAHARASTRA | HOSPITAL SERVICES CONSULTANCY CORPORATION LTD | HEALTH AND FAMILY WELFARE | 08/2017 | 274.19 | 274.19 | JUN |
4. | HOSPITAL AND TEACHING- AIIMS NAGPUR | HOSPITAL SERVICES CONSULTANCY CORPORATION LTD | HEALTH AND FAMILY WELFARE | 03/2018 | 582.99 | 582.99 | JUN |
5. | KOYALI AHMEDNAGAR SOLAPUR PIPELINE | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 05/2016 | 1945 | 1945 | MAR |
6. | BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP) | METROPOLITAN RAPID TRANSPORT PROJECTS | RAILWAYS | 03/1996 | 495.44 | 495.44 | JUN |
7. | SAKOLI TO BHANDARA | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 362.96 | 362.96 | SEP |
8. | MALEWADA TO CHIMUR | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 10/2016 | 322.55 | 322.55 | DEC |
9. | MUL TO CHANDRAPUR | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 12/2016 | 162.34 | 162.34 | SEP |
10. | ARNI TO NAIGAINBANDI | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 12/2017 | 309.94 | 309.94 | SEP |
11. | KATOL TO WARUD | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 463.62 | 463.62 | SEP |
12. | INDAPAUR TO AGARDANDA | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 355.17 | 355.17 | SEP |
13. | SANGOLA TO JATH | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2018 | 257.38 | 257.38 | SEP |
14. | AKOT TO ANJANGAON | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 245.77 | 245.77 | SEP |
15. | PATGAON KHOPOLI SECTION I | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2018 | 170 | 170 | SEP |
16. | PARTUR TO MAJALGAON | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 420.57 | 420.57 | DEC |
17. | HELWAK TO KARAD | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 02/2017 | 416.99 | 416.99 | DEC |
18. | MALEGAON TO RISOD | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 02/2018 | 303.24 | 303.24 | SEP |
19. | LATUR TO PANGAON | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 03/2018 | 336.47 | 336.47 | SEP |
20. | TALEGAON TO GONAPUR | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2018 | 264.41 | 264.41 | SEP |
21. | NAGAJ TO VAIJAPUR | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 376.72 | 376.72 | DEC |
22. | WAKED TO TALEGAON | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 02/2016 | 1244.75 | 1244.75 | SEP |
23. | BODHWAD TO STATE BORDER | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 178.26 | 178.26 | SEP |
24. | DEORI TO AMGAON | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 409.62 | 409.62 | SEP |
25. | KARAD TO VITA | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2018 | 344.85 | 344.85 | SEP |
26. | JALKOT TO TOGRI | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 07/2018 | 299.92 | 299.92 | DEC |
27. | KHAMGAON TO SHEGAON | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 02/2017 | 203.21 | 203.21 | SEP |
28. | TEMBHURNI PANDHARPUR MANGALWEDHA MARWADE UMDI | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 02/2017 | 422.02 | 422.02 | SEP |
29. | CONSTRUCTION OF MAJOR BRIDGE WITH APPROACHES ACROSS PRANHITA RIVER AT KM 57.300 ON NH-63(16) | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 03/2015 | 168.3 | 168.3 | SEP |
30. | JALGAON TO NANDURA | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 03/2018 | 177.84 | 177.84 | DEC |
31. | MANGAON TO DIGHI PORT | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 457.52 | 457.52 | SEP |
32. | NAIGAONBANDI TO MANGRULPIR | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 12/2017 | 244.04 | 244.04 | SEP |
33. | SARAD VANI PIMPALGAON | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 250.46 | 250.46 | SEP |
34. | WADIGODRI TO DHANGRIPIMPRI | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 03/2018 | 194.23 | 194.23 | DEC |
35. | BHOKAR TO SARSAM | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 02/2017 | 295.09 | 295.99 | SEP |
36. | RISOD TO HINGOLI | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 02/2018 | 355.99 | 355.99 | SEP |
37. | GADCHIROLI TO MUL | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 12/2016 | 484.15 | 484.15 | SEP |
38. | CHIKLI TO TAKARKHED | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 03/2018 | 393.1 | 393.1 | SEP |
39. | MORSHI TO ACHALPUR | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 341.16 | 341.16 | SEP |
40. | SHEGAON TO DEORI PHATA | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 02/2017 | 373.1 | 373.1 | SEP |
41. | KARAD TO TAGAON | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 537.81 | 537.81 | SEP |
42. | KALMATH TO ZARAP | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 09/2016 | 1338.13 | 1338.13 | SEP |
43. | WARDHA TO HINGAGHAT | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2018 | 216.9 | 216.9 | SEP |
44. | PARSHURAM GHAT TO ARAWALI | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 04/2016 | 983.14 | 983.14 | SEP |
45. | DHANGIPIMPRI TO JALNA AND AMBAD CHOWK TO MANTH CHOWK | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 03/2018 | 217.14 | 217.14 | DEC |
46. | MANTHA TALUKAS BORDER TO PARTUR | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 486.19 | 486.19 | DEC |
47. | SHIVUR TO YEOLA | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 03/2018 | 181.08 | 181.08 | SEP |
48. | MORSHI TO MAH/MP BORDER | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 471.61 | 471.61 | SEP |
49. | NANDGAON TO MORSHI | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 385.87 | 385.87 | SEP |
50. | VADPALE TO BHOGAN KHURD | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 01/2017 | 1598.47 | 1598.47 | SEP |
51. | KHAMGAON TO DEULGAON SAKARSHA | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 03/2018 | 249.29 | 249.29 | DEC |
52. | NAGPUR METRO RAIL | NAGPUR METRO RAIL CORPORATION LTD | URBAN DEVELOPMENT | 08/2014 | 8680 | 8680 | APR |
53. | BALANCE WORKS OF 4L AMRAVATI - CHIKHLI (PKG II) [KURANKHED TO SHELAD FROM KM. 220.00 TO KM. 270.00] | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 11/2019 | 633.7 | 633.7 | DEC |
54. | SINNAR-SHIRDI (INCLUDING SINNAR BYPASS) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 08/2020 | 1026 | 1026 | APR |
55. | 4L OF AHMEDNAGAR - MIRAJGAON - KARMALA - TEMBHURNI (PKG-I) [AHMEDNAGAR TO GHOGARGAON] FROM KM. 0.00 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 12/2021 | 605 | 605 | FEB |
56. | 4-LANNING OF RAIPUR-KODEBAD SECTION OF NH-43 (FROM KM. 10.200 TO KM. 43.400) IN THE STATE OF CHHATTI | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 11/2016 | 400.25 | 400.25 | FEB |
57. | 4L OF AHMEDNAGAR - MIRAJGAON - KARMALA - TEMBHURNI (PKG-II) [GHOGARGAON TO AHMEDNAGAR- SOLPAUR DISTR | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 01/2022 | 629 | 629 | FEB |
58. | BALANCE WORK UNDER PHASE-I FOR 4L OF KHED SINNER SECTION COMPRISING OF THE STRETCHES (I) KHED BYPASS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 10/2020 | 169.83 | 169.83 | FEB |
59. | BALANCE WORKS OF 4L AMRAVATI CHIKHLI (PKG IV) [NANDURA TO CHIKHLI FROM KM. 315.00 TO KM. 360.00] | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 11/2019 | 583.61 | 583.61 | OCT |
60. | BALANCE WORKS OF 4L AMRAVATI - CHIKHLI (PKG I) [AMRAVATI TO KURANKHED FROM KM. 166.00 TO KM. 220.00] | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 11/2019 | 713.07 | 713.07 | DEC |
61. | AHMEDNAGAR BYPASS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 07/2021 | 715 | 715 | MAR |
62. | HEERA REDEVELOPMENT - PHASE III | OIL & NATURAL GAS CORPORATION LIMITED | PETROLEUM | 06/2019 | 2494.68 | 2494.68 | DEC |
63. | PIPELINE REPLACEMENT PROJECT (PRP-VI) | OIL & NATURAL GAS CORPORATION LIMITED | PETROLEUM | 05/2019 | 763.92 | 763.92 | JUN |
64. | DAUND-GULBARGA - DOUBLING (224.9 KM) AND PUNE-GUNTAKAL -ELECTRIFICATION (641.37 KM) | RAIL VIKAS NIGAM LTD. | RAILWAYS | 03/2009 | 713.48 | 1750 | JUN |
| Total | 64 | |