S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | EXTENSION OF RUNWAY WITH BLAST PAD, RESA, TAXIWAY, APRON, GSE AREA, ISOLATION BAY, NEW DOMESTIC TERM | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | 255.68 | 06/2017 | 12/2020 | 03/2024 | 39 |
2. | UKNI DEEP OC | WESTERN COAL FIELDS LIMITED | COAL | 318.14 | 11/2018 | 03/2021 | 03/2025 | 48 |
3. | BELLORA-NAIGAON DEEP OC | WESTERN COAL FIELDS LIMITED | COAL | 252.71 | 11/2018 | 03/2021 | 03/2024 | 36 |
4. | CONSTRUCTION OF IITB RESEARCH PARK AT IIT BOMBAY, POWAI, MUMBAI | CPWD OF HIGHER EDUCATION | DEPARTMENT OF HIGHER EDUCATION | 223.37 | 01/2018 | 07/2020 | 02/2024 | 43 |
5. | LIFE EXTENSION OF WALL PLATFORMS OF MUMBAI HIGH AND HEERA FIELDS | OIL & NATURAL GAS CORPORATION LIMITED | PETROLEUM | 3190.69 | 12/2015 | 04/2018 | 05/2026 | 97 |
6. | KOYALI AHMEDNAGAR SOLAPUR PIPELINE | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 1945 | 05/2016 | 02/2022 | 02/2024 | 24 |
7. | MUMBAI HIGH NORTH REDEVELOPMENT PHASE-IV | OIL & NATURAL GAS CORPORATION LIMITED | PETROLEUM | 3228.8 | 04/2019 | 03/2022 | 06/2024 | 27 |
8. | SETTING UP 500KTPA PROPANE DEHYDROGENATION INTEGRATED WITH POLYPROPYLENE UNIT ALONG WITH OFFSITE AND | GAS AUTHORITY OF INDIA LIMITED | PETROLEUM | 8797 | 05/2019 | 04/2025 | 10/2025 | 6 |
9. | DEBOTTLENECKING AND AUGMENTATION OF CRYOGENIC FACILITIES AT URAN LPG IMPORT TERMINAL | BHARAT PETROLEUM CORPORATION LIMITED | PETROLEUM | 1164.69 | 04/2021 | 06/2024 | 04/2025 | 10 |
10. | EXPANSION OF CRYOGENICS GROUP BY SETTING UP NEW MANUFACTURING FACILITY | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 378 | 09/2021 | 10/2023 | 05/2024 | 7 |
11. | CONSTRUCTION OF LUBE OIL BLENDING AND FILLING PLANT AT RASAYANI | BHARAT PETROLEUM CORPORATION LIMITED | PETROLEUM | 423.39 | 05/2022 | 03/2024 | 09/2024 | 6 |
12. | DAMAN UPSIDE DEVELOPMENT PROJECT (DUDP) IN TAPTI DAMAN BLOCK | OIL & NATURAL GAS CORPORATION LIMITED | PETROLEUM | 4144.41 | 06/2022 | 10/2025 | 02/2026 | 4 |
13. | CONSTRUCTION OF ADDITIONAL TANKAGES AND ALLIED FACILITIES AT JNPT TERMINAL | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 341.43 | 04/2022 | 10/2024 | 05/2026 | 19 |
14. | BIKANER SOLAR POWER PROJECT | SATLUJ JAL VIDYUT NIGAM LIMITED | POWER | 5491.89 | 04/2022 | 05/2024 | 09/2024 | 4 |
15. | AHMEDNAGAR-PARLI VAIJNATH(NL) CR | CENTRAL RAILWAYS | RAILWAYS | 2271.5 | 02/1997 | 03/2021 | 12/2025 | 57 |
16. | WARDHA-NANDED MAHARASHTRA | CENTRAL RAILWAYS | RAILWAYS | 3168.29 | 04/2008 | 03/2023 | 12/2026 | 45 |
17. | KALYAN-KASARA 3RD LINE | CENTRAL RAILWAYS | RAILWAYS | 792.89 | 04/2011 | 03/2021 | 12/2025 | 57 |
18. | WARDHA-SEWAGRAM NGP 3RD LINE | CENTRAL RAILWAYS | RAILWAYS | 540.02 | 04/2012 | 03/2022 | 03/2025 | 36 |
19. | WARDHA-BALHARSHAH - 3RD LINE (132 KM) | CENTRAL RAILWAYS | RAILWAYS | 1272.19 | 02/2015 | 03/2022 | 03/2025 | 36 |
20. | ITARSI-NAGPUR (BAL.) - 3RD LINE (267 KM) | CENTRAL RAILWAYS | RAILWAYS | 2449.91 | 02/2015 | 03/2023 | 03/2027 | 48 |
21. | PUNE-MIRAJ-LONDA (467 KM) | CENTRAL RAILWAYS | RAILWAYS | 3627.47 | 02/2015 | 03/2024 | 06/2024 | 3 |
22. | DAUND - MANMAD (236 KM) | CENTRAL RAILWAYS | RAILWAYS | 1876 | 02/2016 | 03/2023 | 12/2024 | 21 |
23. | MANMAD - JALGAON - 3RD LINE (160 KM) | CENTRAL RAILWAYS | RAILWAYS | 1035.16 | 02/2016 | 03/2022 | 12/2024 | 33 |
24. | WARDHA - NAGPUR - 4TH LINE (76 KM) | CENTRAL RAILWAYS | RAILWAYS | 637.95 | 02/2016 | 03/2023 | 03/2025 | 24 |
25. | RAJNANDGAON - NAGPUR - 3RD LINE (SECR) | SOUTH EAST CENTRAL RAILWAY | RAILWAYS | 1908.51 | 09/2016 | 03/2023 | 12/2024 | 21 |
26. | WADSA-GADHCHIROLI NEW LINE (52.36 KM) | SOUTH EAST CENTRAL RAILWAY | RAILWAYS | 229 | 06/2018 | 12/2021 | 12/2025 | 48 |
27. | DHULE (BORVIHIR)-NARDANA (UMBRELLA WORK) | CENTRAL RAILWAYS | RAILWAYS | 492.76 | 01/2019 | 03/2026 | 12/2026 | 9 |
28. | MUMBAI URBAN TRANSPORT PROJECT IIIA | Mumbai Railway Vikas Corporation | RAILWAYS | 33690 | 04/2019 | 03/2025 | 12/2027 | 33 |
29. | CONSTRUCTION OF FLYOVER AT KM.544.650 INCLUDING ROB ,SERVICE ROADS ,FOOTPATH FOR RCC DRAINS ON URBAN | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 649.5 | 12/2015 | 03/2019 | 05/2024 | 62 |
30. | NAGPUR RING ROAD PACKAGE-2 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 591.66 | 03/2016 | 07/2019 | 03/2024 | 56 |
31. | 4-LANNING OF TARSOD-FAGNE(FROM KM 422.700-510.00) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1064.88 | 11/2016 | 07/2021 | 03/2024 | 32 |
32. | 4-LANNING OF KODEBAD-DHAMTARI SECTION OF NH-43 (FROM KM. 43.400 TO KM. 82.209) IN THE STATE OF CHHAT | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 446.17 | 11/2016 | 03/2019 | 03/2024 | 60 |
33. | 4-LANNING OF BODHRE-DHULE SECTION(KM 390.000 TO 452.800) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 744.64 | 03/2017 | 03/2020 | 07/2024 | 52 |
34. | 4-LANNING OF WARANGA-MAHAGAON SECTION(KM 253.7000 TO 320.580) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1059.73 | 03/2017 | 03/2017 | 10/2024 | 91 |
35. | CONSTRUCTION OF 8 LANING OF EXISTING 4 LANE VADAPE TO THANE FROM KM 539.202 TO KM 563.000 SECTION OF | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1162.92 | 03/2018 | 07/2021 | 09/2024 | 38 |
36. | SHAHPUR PATGAON SECTION I | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 150.79 | 01/2018 | 12/2019 | 03/2024 | 51 |
37. | KARWANDI TO RAJURI | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 276.95 | 03/2018 | 12/2019 | 03/2024 | 51 |
38. | CHIKALI TO DHAD | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 189.46 | 03/2018 | 12/2019 | 03/2024 | 51 |
39. | DHAD BHOKARDAN TO BHOKARDHAN SILLOD | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 336.21 | 03/2018 | 12/2019 | 03/2024 | 51 |
40. | SELDOH TO PANVAR | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 404.33 | 07/2018 | 05/2020 | 03/2024 | 46 |
41. | KOLHA TO NASRATPUR | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 281.78 | 04/2016 | 04/2019 | 08/2024 | 64 |
42. | NASRATPUR TO BARASGAON | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 406.54 | 07/2016 | 09/2019 | 03/2024 | 54 |
43. | INDAPUR TO VADPALE | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 1202.52 | 01/2017 | 12/2019 | 03/2024 | 51 |
44. | PAITHAN TO SHIRUR | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 341.8 | 03/2017 | 06/2019 | 03/2024 | 57 |
45. | FARDAPUR TO JALGAON | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 456.45 | 02/2017 | 06/2019 | 03/2024 | 57 |
46. | KUMBHARI PHTA TO DEULGAON RAJA | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 406.51 | 02/2017 | 06/2019 | 02/2024 | 56 |
47. | KANTE TO WAKED | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 1230.02 | 03/2016 | 11/2019 | 12/2024 | 61 |
48. | REPANPALLI TO SIRONCHA | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 282.07 | 03/2022 | 06/2022 | 06/2024 | 24 |
49. | INTEGRATED STRUCTURE WITH DEVELOPMENT OF OTHER ALLIED STRUCTURES ON BOTH SIDES OF CHANDNI CHOWK JUNC | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 397.6 | 02/2019 | 02/2022 | 03/2024 | 25 |
50. | TUNNEL AT KHAMBATAKI GHAT SECTION AND ITS APPROACHES FROM EXISTING KM. 771.730 TO EXISTING KM. 782.0 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 493 | 02/2019 | 02/2022 | 06/2024 | 28 |
51. | DHARAMPURI-LONAND FROM KM. 117.00 TO 166.40 (PKG-IV) ON MOHOL-ALANDI SECTION | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 618.45 | 09/2021 | 09/2023 | 03/2024 | 6 |
52. | 4L OF BARAMATI TO INDAPUR (PKG-II) FROM KM. 41.400 TO KM. 84.550 OF NH-965G (SAINT TUKARAM MARG) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 624.45 | 09/2021 | 09/2023 | 03/2024 | 6 |
53. | 4L OF INDAPUR TO TONDLE (PKG-III) FROM KM.84.550 TO KM. 131.00 OF NH-965G (SAINT TUKARAM MARG) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 667.66 | 09/2021 | 09/2023 | 03/2024 | 6 |
54. | 6L OF WAINGANGA BRIDGE - BHANDARA (INCLUDING BHANDARA BYPASS) SECTION FROM KM 485.000 TO KM 499.800 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 815.77 | 10/2021 | 01/2024 | 07/2024 | 6 |
55. | 4L MITIGATION MEASURE STRUCTURES ON CH/MH BORDER TO WAINGANGA BRIDGE SECTION OF NH-53 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 540.21 | 02/2021 | 11/2023 | 06/2024 | 7 |
56. | 4L OF NAGPUR-KATOL SECTION FROM KM. 13.00 TO KM. 62.900 OF NH-353J | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1166.96 | 02/2021 | 10/2023 | 04/2024 | 6 |
57. | BAL. WORKS OF FAGNE (KM. 510.000) TO MAHARASHTRA/GUJARAT BORDER (KM. 650.794) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1654.07 | 12/2019 | 09/2022 | 06/2024 | 21 |
58. | CONSTRUCTION OF 4 LANE FLYOVER AT NAGPUR RTO CHOWK TO NAGPUR UNIVERSITY CAMPUS FROM CH 2/250 TO 5/10 | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 478.83 | 03/2021 | 03/2024 | 04/2024 | 1 |
59. | UP-GRADATION OF TIRORA-GONDIA, STATE HIGHWAY FROM EXISTING KM 163+213 (ON SH-335, TIRORA) TO KM 191+ | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 288.14 | 08/2021 | 04/2023 | 05/2024 | 13 |
60. | BALANCE WORK OF REHABILITATION AND UP-GRADATION TO NH-166F FROM MAHAD JUNCTION (AT KM 123/400 ON NH- | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 256.54 | 07/2021 | 11/2023 | 03/2024 | 4 |
61. | SHEWALI (SAKRI) - NANDURBAR | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 232.59 | 09/2022 | 04/2024 | 07/2024 | 3 |
62. | UPGRADATIOBN AND REHABILITATION OF SECTION OF NH 361 F FROM PARLI (00/000) TO GANGAKHED (30/400) TO | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 224.44 | 11/2021 | 09/2023 | 04/2024 | 7 |
63. | CONSTRUCTION OF SIX LANE FLYOVER AT KATRAJ JUNCTION AT KM, 3/880 OF NH 548-DD (VADGAON - KATRAJ - KO | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 169.15 | 06/2021 | 02/2024 | 03/2024 | 1 |
64. | PUNE METRO RAIL PROJECT (PHASE 1) | MAHARASTRA METRO RAIL CORPORATION LTD. | URBAN DEVELOPMENT | 11420 | 12/2016 | 11/2021 | 03/2024 | 28 |
| Total | 64 | |