S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | CONSTRUCTION OF NEW INTEGRATED TERMINAL BUILDING, CONTROL TOWER CUM TECHNICAL BLOCK, APRON, LINK TAX | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | 499 | 11/2021 | 07/2024 | 03/2025 | 8 |
2. | JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR) | NORTH EAST FRONTIER RAILWAY | RAILWAYS | 4454.17 | 04/2003 | 03/2011 | 12/2026 | 189 |
3. | 2-LANING OF CHURACHANDPUR TUIVAI SECTION OF NH-102B (PKG- 2A) | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 292.24 | 03/2020 | 06/2022 | 05/2024 | 23 |
4. | 2-LANING OF CHURACHANDPUR TUIVAI SECTION OF NH-102B (PKG- 2B) | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 365.53 | 06/2020 | 08/2022 | 06/2024 | 22 |
5. | 2-LANING OF CHURACHANDPUR TUIVAI SECTION OF NH-102B (PKG- 4A) | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 167.95 | 03/2020 | 06/2022 | 05/2024 | 23 |
6. | 2-LANING OF CHURACHANDPUR TUIVAI SECTION OF NH-102B (PKG- 4B) | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 177.76 | 07/2020 | 08/2022 | 06/2024 | 22 |
7. | IMPROVEMENT/UPGRADATION OF EXISTING 2-LANE TO 4-LANE DIVIDED HIGHWAY FROM TAPHOU KUKI TO DAILI SECTI | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 379.39 | 08/2020 | 04/2022 | 10/2024 | 30 |
8. | MARIAM - PEREN PKG-1A | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 226.32 | 02/2021 | 12/2022 | 12/2024 | 24 |
9. | MARIAM - PEREN (PKG 1B) | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 188.36 | 02/2021 | 12/2022 | 09/2024 | 21 |
10. | MARIAM - PEREN PKG-2B | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 232.26 | 02/2021 | 12/2022 | 03/2024 | 15 |
11. | IMPHAL – MOREH PACKAGE- 3 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 259.31 | 03/2021 | 12/2022 | 04/2024 | 16 |
12. | IMPHAL - KHONGSANG PKG-2 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 195.14 | 03/2021 | 12/2022 | 05/2024 | 17 |
13. | TAMENGLONG - MAHUR PKG-3 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 234.08 | 03/2021 | 12/2022 | 04/2024 | 16 |
14. | IMPHAL – MOREH (PACKAGE 4) | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 277.99 | 03/2021 | 01/2023 | 04/2024 | 15 |
15. | SENAPATI- IMPHAL PKG-5B | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 211.7 | 03/2021 | 01/2023 | 03/2025 | 26 |
16. | IMPHAL - KHONGSANG PKG-3 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 467 | 07/2021 | 03/2023 | 08/2024 | 17 |
17. | TAMENGLONG - MAHUR PKG-1 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 185.8 | 07/2021 | 03/2023 | 04/2024 | 13 |
18. | TAMENGLONG - MAHUR PKG-2 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 483.87 | 07/2021 | 03/2023 | 05/2024 | 14 |
19. | TAMENGLONG - MAHUR PKG-4 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 198.77 | 07/2021 | 03/2023 | 04/2024 | 13 |
20. | CHURACHANPUR TUIVAI PKG-3 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 673.27 | 07/2021 | 10/2023 | 06/2024 | 8 |
21. | TAMENGLONG - MAHUR PKG-5 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 477.86 | 08/2021 | 05/2023 | 07/2024 | 14 |
22. | TAMENGLONG - MAHUR PKG-6 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 311.18 | 09/2021 | 05/2023 | 05/2024 | 12 |
23. | MARAM - PEREN PKG-3 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 467.41 | 08/2021 | 05/2023 | 05/2024 | 12 |
24. | IMPHAL - KHONGSANG PKG-4 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 579.63 | 08/2021 | 12/2023 | 09/2024 | 9 |
25. | CONSTRUCTION OF 2-LANING WITH HARD SHOULDER ROAD OF UKHRUL - TOLOI - TADUBI SECTION OF NH-102A FROM | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 310.76 | 09/2021 | 02/2024 | 12/2024 | 10 |
26. | IMPHAL - KHONGSANG PKG-5 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 410.68 | 12/2021 | 05/2024 | 02/2025 | 9 |
| Total | 26 | |