S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | C/O OF NITB AND ASSOCIATED WORK AT VIJAYAWADA AIRPORT | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | 611.8 | 04/2020 | 03/2023 | 12/2024 | 21 |
2. | CONSTRUCTION OF PERMANENT CAMPUS FOR IISER AT JANGALAPALLI VILLAGE, YERPEDU MANDAL, CHITTOOR DISTRIC | CPWD OF HIGHER EDUCATION | DEPARTMENT OF HIGHER EDUCATION | 588.72 | 09/2019 | 09/2022 | 04/2024 | 19 |
3. | VISAKH REFINERY MODERNISATION PROJECT | HINDUSTAN PETROLEUM CORPORATION LIMITED | PETROLEUM | 20928 | 07/2016 | 07/2020 | 06/2024 | 47 |
4. | KG-DWN-98-2 CLUSTER II DEVELOPMENT PROJECT | OIL & NATURAL GAS CORPORATION LIMITED | PETROLEUM | 34012 | 03/2016 | 06/2020 | 05/2024 | 47 |
5. | REVAMPING OF FACILITIES AT VIZAG TERMINAL | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 355 | 04/2018 | 04/2022 | 03/2025 | 35 |
6. | SWRO II WITH LLPH FACILITIES | HINDUSTAN PETROLEUM CORPORATION LIMITED | PETROLEUM | 196.26 | 09/2019 | 07/2020 | 06/2024 | 47 |
7. | RUF PITCH LOADING GANTRY | HINDUSTAN PETROLEUM CORPORATION LIMITED | PETROLEUM | 332.61 | 10/2020 | 11/2022 | 04/2024 | 17 |
8. | CGD PROJECT AT SRIKAKULAM, VISAKHAPATNAM AND VIZIANAGARAM DISTRICTS | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 2880 | 06/2019 | 08/2027 | 03/2030 | 31 |
9. | MULTI-PRODUCT PIPELINE FROM KRISHNAPATNAM COASTAL INSTALLATION TO THE PROPOSED INSTALLATION AT HYDER | BHARAT PETROLEUM CORPORATION LIMITED | PETROLEUM | 1932 | 09/2019 | 03/2025 | 10/2025 | 7 |
10. | TRANSMISSION SCHEME FOR SOLAR ENERGY ZONE IN ANANTHPURAM (2500MW) AND KURNOOL (1000MW) | POWER GRID CORPORATION OF INDIA LIMITED | POWER | 1249 | 09/2023 | 03/2025 | 09/2025 | 6 |
11. | KOTLPALLI-NARASAPUR (NL) (SCR) | SOUTH CENTRAL RAILWAY | RAILWAYS | 1045.2 | 12/2001 | 03/2009 | 03/2027 | 216 |
12. | NADIKUDE-SRI KALAHASTI | SOUTH CENTRAL RAILWAY | RAILWAYS | 2288.7 | 04/2011 | 03/2021 | 05/2027 | 74 |
13. | GUNTUR-GUNTAKAL | SOUTH CENTRAL RAILWAY | RAILWAYS | 3631 | 04/2016 | 03/2022 | 12/2025 | 45 |
14. | VIJAYAWADA-GUDUR | RAIL VIKAS NIGAM LTD. | RAILWAYS | 3246.26 | 04/2015 | 12/2023 | 12/2024 | 12 |
15. | MALUGUR-PALASAMUDRAM (17.98 KM) (PB#29/NR/2022-23) | SOUTH WESTERN RAILWAY | RAILWAYS | 323.14 | 09/2022 | 12/2025 | 03/2026 | 3 |
16. | REHABILITATION AND UPGRADATION OF EXISTING NH-565 FROM KM.86.057 TO 133.922 OF NAGARJUNASAGAR DAM T | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 195.45 | 01/2014 | 11/2014 | 05/2024 | 114 |
17. | CONSTRUCTION OF SIX LANING OF DEDICATED PORT ROAD TO KRISHNAPATNAM PORT (PACKAGE-I) KM 0+000 TO KM 1 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 314.43 | 03/2018 | 12/2020 | 12/2024 | 48 |
18. | 6-LANING OF VIJAYAWADA BYPASS FROM CHINNA AVUTUPALLI (DESIGN CH.0+000) TO GOLLAPUDI (DESIGN CH. 30+0 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1226.88 | 11/2019 | 02/2021 | 09/2024 | 43 |
19. | 6-LANING OF VIJAYAWADA BYPASS FROM GOLLAPUDI (DESIGN CH. 30+000) TO CHINNAKAKANI (DESIGN CH. 47+881) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1601.1 | 11/2019 | 01/2024 | 07/2024 | 6 |
20. | REHABILITATION AND UPGRADATION TO 2-LANE WITH PAVED SHOULDERS CONFIGURATION OF PADERU-GONDIGUDA SECT | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 222.61 | 08/2020 | 03/2021 | 03/2024 | 36 |
21. | CONSTRUCTION OF 4 LANE ACCESS CONTROLLED NEW GREENFIELD HIGHWAY SECTION OF NH 365BG FROM RECHARLA VI | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 517.05 | 09/2021 | 09/2022 | 09/2024 | 24 |
22. | CONSTRUCTION OF 4 LANE ACCESS CONTROLLED NEW GREENFIELD HIGHWAY SECTION OF NH-365BG (KHAMMAM-DEVARAP | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 622 | 09/2021 | 09/2022 | 09/2024 | 24 |
23. | 6L OF CHILKARARUPET BYPASS FROM KM. 357.400 TO KM. 371.920 OF NH-16 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 757.45 | 02/2019 | 03/2023 | 03/2024 | 12 |
24. | 6L JAKKUVA – KORLAM SECTION OF NH-130CD ROAD FROM KM 396.800 TO KM 421.100 (PKG 2) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 663.6 | 02/2021 | 03/2024 | 06/2024 | 3 |
25. | 6L ALURU - JAKKUVA SECTION OF NH-130CD ROAD FROM KM 365.033 TO KM 396.800 (PKG. 1) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 922.5 | 02/2021 | 03/2024 | 12/2024 | 9 |
26. | 6L ACCESS CONTROLLED GREENFIELD HIGHWAY FROM KODUR 0.000 KMS TO VANAVOLU 24.300 KMS OF NH 544G PACKA | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 912.94 | 12/2022 | 09/2025 | 02/2026 | 5 |
27. | NH165 FROM KM 0.000 TO KM 64.020 PAMARRU TO AKIVEEDU SECTION TO TWO LANE WITH PAVED SHOULDERS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 529.24 | 03/2020 | 09/2023 | 12/2024 | 15 |
28. | 2LPS FROM GONDIGUDA TO ARAKU BHALLAGUDA KM 27.480 TO KM 51.772 SECTION OF NH 516E | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 296.66 | 08/2020 | 09/2023 | 03/2024 | 6 |
29. | POLAVARAM IRRIGATION PROJECT | Polavaram Project Authority | WATER RESOURCES | 10151.04 | 02/2009 | 03/2020 | 03/2024 | 48 |
| Total | 29 | |