S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | CONSTRUCTION OF NEW INTEGRATED TERMINAL BUILDING AT LGBI AIRPORT GUWAHATI | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | 1142 | 12/2016 | 03/2021 | 03/2025 | 48 |
2. | DEVELOPMENT OF SURFACE FACILITIES FOR PRODUCTION AND EVACUATION OF CRUDE OIL AND NATURAL GAS FROM NA | OIL INDIA LIMITED | PETROLEUM | 543.91 | 01/2018 | 02/2020 | 04/2024 | 50 |
3. | NUMALIGARH REFINERY EXPANSION PROJECT 6 MMTPA REFINARY | NUMALIGARH REFINERY LIMITED | PETROLEUM | 12366 | 01/2019 | 10/2024 | 07/2025 | 9 |
4. | NUMALIGARH REFINERY EXPANSION PROJECT COIT AND PIPELINES | NUMALIGARH REFINERY LIMITED | PETROLEUM | 10228 | 01/2019 | 10/2024 | 03/2025 | 5 |
5. | EXPANSION OF GUWAHATI REFINERY FROM 1 TO 1.2 MMTPA ALONG WITH INSTALLATION OF CATALYTIC REFORMING UN | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 412 | 05/2021 | 10/2023 | 02/2025 | 16 |
6. | GAS ASSISTED GRAVITY DRAINAGE SCHEME, KASOMARIGAON | OIL & NATURAL GAS CORPORATION LIMITED | PETROLEUM | 218.38 | 08/2021 | 02/2023 | 07/2024 | 17 |
7. | REVAMPING OF FACILITIES AT EXISTING GUWAHATI TERMINAL, ASSAM | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 277 | 03/2022 | 07/2026 | 09/2026 | 2 |
8. | BONGAIGAON-GOALPARA-GUWAHATI (176 KM) | NORTH EAST FRONTIER RAILWAY | RAILWAYS | 2232.32 | 04/2015 | 03/2022 | 03/2026 | 48 |
9. | FOUR LANING OF NUMALIGARH TO JORHAT SECTION FROM KM. 402.500 TO KM. 453.000 (DESIGN KM 403.200 TO KM | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 454.89 | 05/2015 | 05/2018 | 02/2024 | 69 |
10. | 4 LANING OF JORHAT TO JHANJI SECTION FROM KM. 453.00 TO KM. 491.08 (DESIGN KM 403.200 TO KM 454.240) | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 437.39 | 06/2015 | 08/2023 | 08/2024 | 12 |
11. | FOUR LANING OF JHANJHI JN TO DEMOW SECTION FROM KM. 491.050 TO KM. 535.250(DESIGN KM 490.800 TO KM 5 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 463.49 | 06/2015 | 03/2024 | 07/2024 | 4 |
12. | 4 LANING FROM JAMUGURI TO BISWANATH CHARIALI FROM KM 182 TO KM 208 OF NH-52 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 520.01 | 01/1991 | 06/2019 | 03/2024 | 57 |
13. | 4 LANING FROM RANGAGARA TO KALIABHOR TINALI FROM KM 297.00 TO KM 315.315 OF NH-37 ON EPC BASIS. | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 289.99 | 12/2015 | 12/2018 | 03/2024 | 63 |
14. | 4 LANING OF NH-37 SECTION BETWEEN DEMOW TO END OF MORAN BYPASS (FROM KM. 534.800 TO KM. 561.700) O | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 294.17 | 01/2016 | 01/2016 | 10/2024 | 105 |
15. | FOUR LANING OF BALACHERA-HARANGAJAO SECTION OF NH-54 (EXT) FROM KM 275.00 TO KM 244.000 IN THE STATE | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 818 | 10/2017 | 06/2020 | 03/2024 | 45 |
16. | 4-LANING OF HAPACHARA - TULUNGIA SECTION | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 220.2 | 03/2020 | 12/2022 | 03/2024 | 15 |
17. | WIDENING/IMPROVEMENT TO 4-LANE WITH PAVED SHOULDER FROM CH.75.330KM TO CH.88.00KM (DESIGN CH.71.800 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 208.84 | 08/2020 | 04/2022 | 07/2024 | 27 |
18. | 2-LANING OF CHURACHANDPUR TUIVAI SECTION OF NH-102B (PKG- IB) | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 216.49 | 03/2020 | 03/2022 | 03/2024 | 24 |
19. | 2-LANING FROM YAINGANGPOKPI TO FINCH CORNER (PKG-I) | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 261.13 | 03/2020 | 06/2022 | 08/2024 | 26 |
20. | 2-LANING FROM YAINGANGPOKPI TO FINCH CORNER (PKG-II) | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 217.5 | 03/2020 | 06/2022 | 05/2024 | 23 |
21. | DABOKA KATHKATI PACKAGE-5 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 288.85 | 03/2021 | 01/2023 | 03/2024 | 14 |
22. | TULUNGIA-JOGIGHOPA-PAIKAN PKG-5 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 636.42 | 03/2021 | 12/2022 | 02/2024 | 14 |
23. | TULUNGIA-JOGIGHOPA-PAIKAN ROAD PKG-7 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 286.72 | 03/2021 | 01/2024 | 10/2025 | 21 |
24. | 4-LANING OF DERGAON TOWN | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 287.63 | 03/2020 | 06/2022 | 02/2024 | 20 |
25. | 6L STANDALONE FLYOVERS AT RAHA, DEMOW, BORGHAT, KATHIATALI JUNCTIONS AND ROB AT JAGIROAD ON STRETCHE | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 175 | 08/2022 | 12/2022 | 06/2024 | 18 |
26. | SHRIRAMPUR (KM. 0.000) TO KOCHUGAON (KM. 30.000) OF BIJNI TO ASSAM./WEST BENGAL BORDER SECTION OF NH | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 442.23 | 07/2017 | 04/2020 | 03/2024 | 47 |
27. | DEVELOPMENT OF EXTERNAL TRUNK CONNECTIVITY AND INTERNAL INFRASTRUCTURE WORKS AT MULTI MODEL LOGISTIC | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 592.06 | 02/2020 | 03/2022 | 05/2024 | 26 |
| Total | 27 | |