S No. | Sector | Agency | Date Of Approval | Cost Original | Cost Overrun |
1. | POWER | NATIONAL THERMAL POWER CORPORATION | 02/2005 | 8692.97 | 12619.14 |
2. | RAILWAYS | EAST CENTRAL RAILWAYS | 04/1997 | 162.87 | 451.58 |
3. | RAILWAYS | EAST CENTRAL RAILWAYS | 04/2003 | 528.65 | 1538.13 |
4. | RAILWAYS | NORTH EAST FRONTIER RAILWAY | 09/2006 | 532.87 | 2117.13 |
5. | RAILWAYS | EAST CENTRAL RAILWAYS | 04/2004 | 372.14 | 1327.86 |
6. | RAILWAYS | EAST CENTRAL RAILWAYS | 04/1997 | 324.73 | 785.27 |
7. | RAILWAYS | EAST CENTRAL RAILWAYS | 04/2009 | 548 | 235.83 |
8. | RAILWAYS | EAST CENTRAL RAILWAYS | 04/1999 | 325 | 410.2 |
9. | RAILWAYS | EAST CENTRAL RAILWAYS | 04/1991 | 329.39 | 1180.61 |
10. | RAILWAYS | EAST CENTRAL RAILWAYS | 04/2016 | 744.04 | 471.5 |
11. | RAILWAYS | EAST CENTRAL RAILWAYS | 05/2015 | 380 | 139.33 |
12. | RAILWAYS | EAST CENTRAL RAILWAYS | 04/2016 | 731.64 | 454.09 |
13. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 01/2018 | 573.7 | 153.29 |
14. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 01/2014 | 1408.85 | 729.31 |
15. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 09/2020 | 2334.68 | .32 |
16. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 02/2016 | 553.3 | 153.09 |
17. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 02/2016 | 178.85 | 99.69 |
18. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 03/2017 | 672.89 | 157.42 |
19. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 12/2018 | 333.6 | 127.81 |
20. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 12/2015 | 1167.45 | 15.49 |
21. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 12/2021 | 184.9 | .1 |
22. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 12/2021 | 552.55 | .45 |
23. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 08/2017 | 950.64 | 217.69 |
24. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 03/2018 | 496.2 | 40.97 |
25. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 01/1991 | 675 | 105.77 |
26. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 02/2022 | 786.81 | .19 |
27. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 01/1991 | 319.68 | 183.6 |
28. | URBAN DEVELOPMENT | PATNA METRO RAIL CORPORATION | 02/2019 | 13365.77 | 559.73 |
29. | WATER RESOURCES | Bihar Urban Infrastructure Development Corporation Ltd | 10/2017 | 254.13 | 159.16 |
30. | WATER RESOURCES | Bihar Urban Infrastructure Development Corporation Ltd | 04/2015 | 268.63 | 162.58 |
31. | WATER RESOURCES | Bihar Urban Infrastructure Development Corporation Ltd | 12/2014 | 225.77 | 173.13 |
| Total | 31 | |