S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | CONSTRUCTION OF NEW DORNESTIC TERMINAL BUILDING AND OTHER STRUCTURES, PHASE I AND II | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | 1216.9 | 05/2018 | 10/2022 | 12/2024 | 26 |
2. | PERMANENT CAMPUS FOR IIM BODH GAYA | CPWD OF HIGHER EDUCATION | DEPARTMENT OF HIGHER EDUCATION | 375 | 09/2018 | 09/2020 | 04/2024 | 43 |
3. | CITY GAS DISTRIBUTION (CGD) NETWORK PATNA | GAS AUTHORITY OF INDIA LIMITED | PETROLEUM | 359.25 | 10/2017 | 10/2022 | 03/2024 | 17 |
4. | BARAUNI REFINERY CAPACITY EXPANSION FROM 6.0 TO 9.0 MMTPA | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 14810 | 01/2020 | 04/2023 | 12/2024 | 20 |
5. | CGD PROJECT AT AURANGABAD, KAIMUR AND ROHTAS DISTRICTS | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 176 | 10/2018 | 08/2027 | 02/2029 | 18 |
6. | CGD PROJECT AT ARARIA, PURNIA, KATIHAR AND KISHANGANJ DISTRICTS | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 988 | 06/2019 | 12/2029 | 03/2030 | 3 |
7. | CGD PROJECT AT ARWAL, JEHANABAD, BHOJPUR AND BUXAR DISTRICTS | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 439 | 06/2019 | 02/2028 | 08/2029 | 18 |
8. | CGD PROJECT AT KHAGARIA, SAHARSA AND MADHEPURA | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 163 | 06/2019 | 12/2029 | 03/2030 | 3 |
9. | CGD PROJECT AT LAKHISARAI, MUNGER AND BHAGALPUR DISTRICTS | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 347 | 06/2019 | 02/2028 | 08/2029 | 18 |
10. | CGD PROJECT AT MUZAFFARPUR, VAISHALI, SARAN AND SAMASTIPUR DISTRICTS | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 2996 | 06/2019 | 02/2028 | 08/2029 | 18 |
11. | BARH STPP(3X660MW) NTPC | NATIONAL THERMAL POWER CORPORATION | POWER | 8692.97 | 02/2005 | 10/2011 | 11/2024 | 157 |
12. | BUXAR THERMAL POWER PLANT (1320 MW) | SATLUJ JAL VIDYUT NIGAM LIMITED | POWER | 10439.09 | 03/2019 | 01/2024 | 12/2024 | 11 |
13. | NEW B.G. LINE FROM ARARIA TO GALGALIA (THAKURGUNG), NEFR | NORTH EAST FRONTIER RAILWAY | RAILWAYS | 532.87 | 09/2006 | 03/2019 | 12/2024 | 69 |
14. | JAYNAGAR-BIJALPURA INCLUDING EXTENSION BIJALPURA-BARDIBAS(NEPAL) GC | EAST CENTRAL RAILWAYS | RAILWAYS | 548 | 04/2009 | 03/2020 | 03/2026 | 72 |
15. | KIUL - GAYA DOUBLING PROJECT | EAST CENTRAL RAILWAYS | RAILWAYS | 1200.2 | 12/2015 | 03/2020 | 05/2024 | 50 |
16. | RAMPUR DUMRA - TAL - RAJENDRAPUL DOUBLING INCLUDING GANGA BRIDGE | EAST CENTRAL RAILWAYS | RAILWAYS | 1491.47 | 12/2015 | 03/2020 | 03/2025 | 60 |
17. | SAGAULI VALMIKINAGAR DOUBLING 109.7 KM | EAST CENTRAL RAILWAYS | RAILWAYS | 744.04 | 04/2016 | 03/2021 | 06/2024 | 39 |
18. | MUZAFFARPUR SAGAULI DOUBLING 100.60 KM | EAST CENTRAL RAILWAYS | RAILWAYS | 731.64 | 04/2016 | 03/2021 | 06/2024 | 39 |
19. | PATNA-MUZZAFFARPUR | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 671.3 | 08/2010 | 02/2013 | 06/2024 | 136 |
20. | 4-LANNING OF CHAPRA-HAJIPUR | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 575 | 01/2011 | 07/2013 | 06/2024 | 131 |
21. | FOUR OF SIMARIA - KHAGARIA SECTION OF NH-31 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1041.1 | 12/2015 | 04/2019 | 12/2024 | 68 |
22. | FOUR LANING OF BAKHTIYARPUR - MOKAMA SECTION OF NH-31 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1167.45 | 12/2015 | 12/2019 | 05/2024 | 53 |
23. | CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2 LANES/2 LANE(FOR LOT-I-KM 40.00 TO KM 65.400 AND K | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 178.85 | 02/2016 | 05/2016 | 04/2024 | 95 |
24. | PROCUREMENT, AND CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2 LANES/2 LANE(FOR LOT-III-KM 156.5 | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 553.3 | 02/2016 | 05/2016 | 04/2024 | 95 |
25. | FOUR LANING OF GAYA-HISUA-RAJGIRI-NALANDA-BIHARSHARIF SECTION (KM0.00 TO 92.935) ON NH-82 IN BIHAR | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 1408.85 | 01/2014 | 10/2016 | 08/2024 | 94 |
26. | TWO-LANNING WITH PAVED SHOULDER OF MAHSHKUNT-SAHARSA-PURNEA SECTION FROM EXISTING KM.89.020 (DESIGN | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 672.89 | 03/2017 | 03/2020 | 12/2024 | 57 |
27. | SIX LANNING OF AUNTA-SIMARIA(GANGA BRIDGE WITH APPROACH ROADS) SECTION OF NH-31 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 950.64 | 08/2017 | 02/2022 | 10/2024 | 32 |
28. | CONSTRUCTION OF NEW LINK (NH-133B) FROM KM 0/00 (KM 200/87 OF SAHIBANJ BYPASS) IN JHARKHAND TO KM 15 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2598 | 12/2017 | 10/2024 | 04/2025 | 6 |
29. | REHABILITATION AND UPGRADATION OF TWO LANING OF MAHESHKHUNT - SAHARSA - PURNEA SECTION PKG - I | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 573.7 | 01/2018 | 12/2021 | 06/2024 | 30 |
30. | BALANCE WORK OF 4- LANING OF PATNA-GAYA-DOBHI SECTION (KM. 0.00 TO KM. 127.217) OF NH-83 IN THE STAT | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 649.9 | 10/2013 | 12/2020 | 03/2024 | 39 |
31. | BALANCE WORK OF 4- LANING OF PATNA-GAYA-DOBHI SECTION (KM. 39.00 TO KM. 83.00) OF NH-83 IN THE STATE | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 446.97 | 10/2013 | 11/2020 | 04/2024 | 41 |
32. | BALANCE WORK OF 4- L ANING OF PATNA-GAYA-DOBHI SECTION (KM.83.00 TO KM. 127.217) OF NH-83 IN THE STA | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 464.09 | 10/2013 | 11/2020 | 04/2024 | 41 |
33. | CONSTRUCTION OF 2 LANE BRIDGE ACROSS RIVER KOSI WITH APPROACH ROAD FROM BHEJA TO BAKAUR SECTION OF N | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1101.99 | 10/2019 | 08/2023 | 12/2024 | 16 |
34. | 4 LANING OF GALGALIA - BAHADURGANJ SECTION FROM KM 0.000 TO KM 49.000 (PACKAGE-I) OF NH-327E. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1097.18 | 03/2021 | 01/2024 | 05/2024 | 4 |
35. | 4 LANING OF BAHADURGANJ ARARIA SECTION FROM KM 49.000 TO KM 94.000 (PACKAGE-II) OF NH-327E | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1143.46 | 03/2021 | 01/2024 | 05/2024 | 4 |
36. | 4 LANING FROM KM. 34.600 TO KM. 79.970 and 2LPS FROM KM. 79.970 TO KM. 82.000 OF NARENPUR - PURNEA S | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2334.68 | 09/2020 | 03/2023 | 05/2024 | 14 |
37. | WIDENING and STRENTHENING FROM KM132.895 TO KM 190.15 NH-80 | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 566.15 | 03/2021 | 03/2024 | 11/2024 | 8 |
38. | BALANCE WORK - WB-10 (GANDAK BRIDGE) KM 402.00 TO KM 440.00 (DEVANPUR - KOTWA) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 210.05 | 12/2021 | 01/2024 | 06/2025 | 17 |
39. | PATNA METRO RAIL CORPORATION LIMITED | PATNA METRO RAIL CORPORATION | URBAN DEVELOPMENT | 13365.77 | 02/2019 | 06/2024 | 09/2024 | 3 |
40. | I AND D AND STP WORKS FOR BHAGALPUR | Bihar Urban Infrastructure Development Corporation Ltd | WATER RESOURCES | 254.13 | 10/2017 | 09/2020 | 03/2024 | 42 |
41. | SEWERAGE SYSTEM AND STP FOR KANKARBAG ZONE PATNA | Bihar Urban Infrastructure Development Corporation Ltd | WATER RESOURCES | 578.89 | 08/2017 | 06/2022 | 03/2024 | 21 |
42. | SEWERAGE SYSTEM AND STP FOR DIGHA ZONE, PATNA | Bihar Urban Infrastructure Development Corporation Ltd | WATER RESOURCES | 824 | 08/2017 | 06/2022 | 03/2024 | 21 |
| Total | 42 | |