Details of Projects Showing Time Overrun in Chhatisgarh
S No.Project TitleAgency NameSector NameCost OriginalDate Of ApprovalDOC OriginalDOC AnticipatedTime Overrun(in months)
1.GEVRA EXPANSION OCP (SECL) (35-70) MTY SOUTH-EASTERN COAL FIELDS LIMITEDCOAL11816.406/201003/202303/202524
2.KUSMUNDA EXPN.OCP(SECL)(15-50)MTY SOUTH-EASTERN COAL FIELDS LIMITEDCOAL7612.3308/201303/202303/202524
3.PELMA OCP(15.00MTY) SOUTH-EASTERN COAL FIELDS LIMITEDCOAL1624.5911/201403/202303/203196
4.KARTALI (EAST) OCP (2.50 MTY) SOUTH-EASTERN COAL FIELDS LIMITEDCOAL178.4407/200803/201403/2026144
5.CHHAL OC SEAM -III (6.00 MTY) SOUTH-EASTERN COAL FIELDS LIMITEDCOAL610.6312/201303/202203/202536
6.AMERA OC RCE SOUTH-EASTERN COAL FIELDS LIMITEDCOAL335.9702/201503/201803/202696
7.AMGAON OPENCAST PROJECT RCE SOUTH-EASTERN COAL FIELDS LIMITEDCOAL316.107/201503/202003/202560
8.DURGAPUR OPENCAST PROJECT SOUTH-EASTERN COAL FIELDS LIMITEDCOAL916.2402/201503/202303/203084
9.MADANNAGAR OPENCAST PROJECT SOUTH-EASTERN COAL FIELDS LIMITEDCOAL1875.3210/201503/202403/202736
10.JHIRIA WEST OPENCAST PROJECT SOUTH-EASTERN COAL FIELDS LIMITEDCOAL389.9711/201803/202603/202936
11.JAGANNATHPUR OC RCE (3.0 MTY) SOUTH-EASTERN COAL FIELDS LIMITEDCOAL459.4907/201603/202003/202448
12.AUGMENTATION OF FACILITIES AT THE EXISTING RAIPUR DEPOT HINDUSTAN PETROLEUM CORPORATION LIMITEDPETROLEUM45603/202103/202403/202512
13.WESTERN REGION EXPANSION SCHEME XXV POWER GRID CORPORATION OF INDIA LIMITEDPOWER385.8402/202311/202306/20247
14.KIRANDUL - JAGDALPUR DOUBLING EAST COAST RAILWAYRAILWAYS116012/201203/202003/202448
15.JHARSUGUDA-BILASPUR 4TH LINE SOUTH EAST CENTRAL RAILWAYRAILWAYS197304/201503/202110/202443
16.KHARSIA DHARAMJAIGARH WITH SPUR LINE EAST CORRIDOR-PHASE I Indian Railway Construction Company LimitedRAILWAYS305504/201309/201806/202469
17.REHABILITATION AND UPGRADATION OF NH 43 KANKER TO BEDMA SECTION KM. 130 TO 180 MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs)ROAD TRANSPORT AND HIGHWAYS497.1401/201608/201612/2024100
18.REHABILITATION AND UPGRADATION OF NH 111 FROM KM 163.400 TO 215.800 SHIVNAGAR TO AMBIKAPUR SECTION MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs)ROAD TRANSPORT AND HIGHWAYS335.3211/201506/201704/202482
19.REHABILITATION AND UPGRADATION OF NH 78 FROM KM 469.000 TO 531.000 PATTHALGAON TO KUNKURI MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs)ROAD TRANSPORT AND HIGHWAYS452.9403/201607/201607/202496
20.CONSTRUCTION OF 4 NOS GRADE SEPARATOR BETWEEN KM. 281.000 TO KM 307.600 KM. 286.400 KUMHARI KM. 299.MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs)ROAD TRANSPORT AND HIGHWAYS349.0303/201801/201905/202464
21.UPGRADATION AND WIDENING OF BILASPUR TO MUNGELI SECTION NH-130A MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs)ROAD TRANSPORT AND HIGHWAYS188.811/201705/201904/202459
22.4 LANING OF CHAMPA-KORBA-CHHURI-KATGHORA SECTION OF NH 149B FROM KM.0.000 TO KM.38.200 NATIONAL HIGHWAYS AUTHORITY OF INDIAROAD TRANSPORT AND HIGHWAYS999.9702/202101/202409/20248
23.4 LANE OF BILASPUR TO URGA PROJECT (KM 0.00 TO KM 70.2) OF NH-130A NATIONAL HIGHWAYS AUTHORITY OF INDIAROAD TRANSPORT AND HIGHWAYS1855.5904/202003/202406/202515
24.UPGRADATION OF NH 930 JHALMALA TO SHERPER FROM NH KM 30.600 TO KM 67.800 TO TWOFOUR LANE WITH PAVED MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs)ROAD TRANSPORT AND HIGHWAYS222.8612/202008/202305/20249
25.UP GRADATION OF NH 130C ABHANPUR TO PAUND FROM NK KM 0.000 TO KM. 40.380 TO TWO LANE WITH PAVED SHOUMINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs)ROAD TRANSPORT AND HIGHWAYS193.1612/202009/202306/20249
26.NMDC SLURRY PIPE LINE PROJECT - PHASE-1 NATIONAL MINERAL DEVELOPMENT CORPORATION (NMDC)STEEL290711/201506/202305/202523
27.SCREENING PLANT-III AT KIRANDUL NATIONAL MINERAL DEVELOPMENT CORPORATION (NMDC)STEEL2092.9703/202108/202410/202514
28.CONSTRUCTION OF RESIDENTIAL TOWERS AT BIOM KIRANDUL COMPLEX NATIONAL MINERAL DEVELOPMENT CORPORATION (NMDC)STEEL282.4407/202111/202411/202512
Total28