S No. | Agency Name | Sector Name | Project Name | Date Of Approval | Cost Original | Cost Anticipated | Expenditure |
1. | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | CONSTRUCTION OF COMBINED OPERATIONAL OFFICES FOR DGCA, BCAS, AAIB, AERA AND AAI AT SAFDARJUNG AIRPOR | 11/2016 | 303.8 | 374.98 | 319.66 |
2. | CENTRAL PUBLIC WORKS DEPARTMENT | URBAN DEVELOPMENT | REDEVELOPMENT OF GENERAL POOL RESIDENTIAL COLONY AT SRINIWASPURI NEW DELHI PHASE-I | 10/2016 | 1180 | 1100.8 | 36.69 |
3. | CENTRAL PUBLIC WORKS DEPARTMENT | URBAN DEVELOPMENT | CONSTRUCTION OF 184 MULTI STORIED FLATS FOR HON'BLE MPS AT BKS MARG, NEW DELHI | 1/2022 | 646.52 | 646.52 | 92.06 |
4. | CENTRAL PUBLIC WORKS DEPARTMENT | URBAN DEVELOPMENT | REDEVELOPMENT OF GPRA AT KASTURBA NAGAR PHASE I | 10/2016 | 1128 | 1128 | 307.76 |
5. | CPWD FOR MHA | HOME AFFAIRS | ESTABLISHMENT OF CENTRAL ARMED POLICE FORCE INSTITUTE OF MEDICAL SCIENCES(CAPFIMS) AT NEW DELHI | 10/2013 | 1219.21 | 2091.53 | 1773.27 |
6. | CPWD FOR MHA | HOME AFFAIRS | CONSTRUCTION OF HEADQUARTER BUILDING OF CRPF AT LODHI ROAD NEW DELHI | 6/2019 | 277.35 | 290.33 | 99.28 |
7. | CPWD FOR RENEWABLE ENERGY | RENEWABLE ENERGY | CONSTRUCTION OF ATAL AKSHAY URJA BHAWAN CGO COMPLEX LODHI ROAD NEW DELHI | 10/2017 | 271.9 | 366.12 | 329.49 |
8. | CPWD FOR TELECOM | TELECOMMUNICATIONS | SETTING UP PHYSICAL INFRASTRUCTURE FOR THE NATIONAL INSTITUTE OF COMMUNICATION FINANCE(NICF) AT GHIT | 10/2014 | 248.2 | 248.2 | 198.43 |
9. | DELHI METRO RAIL CORPORATION | URBAN DEVELOPMENT | DELHI METRO RAIL EXTENSION FROM NAJAFGARH TO DHANSA BUS STAND | 5/2017 | 565 | 565 | 520.85 |
10. | DELHI METRO RAIL CORPORATION | URBAN DEVELOPMENT | DELHI METRO PHASE IV THREE PRIORITY CORRIDORS | 7/2019 | 24948.65 | 24948.65 | 10342.37 |
11. | DELHI METRO RAIL CORPORATION | URBAN DEVELOPMENT | DELHI MRTS PHASE-III | 9/2011 | 38585 | 40180.91 | 40420.8 |
12. | Delhi Jal Board | WATER RESOURCES | REHABILITATION AND UP-GRADATION OF PHASE I STP 182 MLD R2 | 5/2016 | 211.79 | 211.79 | 203.03 |
13. | Delhi Jal Board | WATER RESOURCES | CONSTRUCTION OF 564 MLD 124 MGD WASTE WATER TREATMENT PLANT WITH EFFLUENT STANDARDS OF BOD – 10MG/L | 3/2017 | 665.78 | 665.78 | 747.84 |
14. | Delhi Jal Board | WATER RESOURCES | CONSTRUCTION OF 318 MLD WWTP WITH 10 YEARS O AND M AT CORONATION PILLAR DELHI | 12/2018 | 515.07 | 515.07 | 388.08 |
15. | Delhi Jal Board | WATER RESOURCES | REHABILITATION AND UPGRADATION OF KONDLI PHASE I STP 45 MLD PHASE II STP 114 MLD AND PHASE III S | 5/2016 | 239.11 | 239.11 | 268.13 |
16. | Delhi Jal Board | WATER RESOURCES | 7 NOS PRIORITIZED STPS 1 NO. SPS AND PERIPHERAL SEWERS IN COMMAND AREA OF NAJAFHARH DRAIN DHANSA TO | 5/2017 | 344.81 | 344.81 | 0 |
17. | IICC FOR DPIIT | DPIIT | INDIA INTERNATIONAL CONVENTION AND EXPO CENTRE | 11/2017 | 4773 | 5401 | 4625.54 |
18. | NATIONAL BUILDING CONSTRUCION CORPORATION LTD | URBAN DEVELOPMENT | REDEVELOPMENT OF GPRA COLONY AT NAUROJI NAGAR | 7/2016 | 2694 | 2694 | 2101.61 |
19. | NATIONAL BUILDING CONSTRUCION CORPORATION LTD | URBAN DEVELOPMENT | REDEVELOPMENT OF GPRA AT NETAJI NAGAR NEW DELHI PACKAGE 2 | 10/2016 | 1536.72 | 1536.72 | 74 |
20. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 8L OF DWARKA EXPRESSWAY PKG-II (RUB NEAR DWARKA SECTOR 21-DL/HR BORDER) FROM 5.300 KM.TO 9.500 KM. O | 1/2018 | 2067.67 | 2160 | 1496.49 |
21. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | DEVELOPMENT OF 4L UER II [PACKAGE - V] (SPUR TO BAHADURGARH BYPASS) (NH-10) FROM KM. 0.00 TO KM.7.30 | 7/2020 | 801.46 | 801.46 | 382.03 |
22. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | DEVELOPMENT OF 6L UER II [PACKAGE - II] (KARALA KANJHAWALA ROAD TILL NANGLOI - NAJAFGARH ROAD) FROM | 7/2020 | 1894.96 | 1894.96 | 741.88 |
23. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | DEVELOPMENT OF 6L UER-II (PACKAGE-I) (NH-1 NEAR BAKOLI TILL KARALA KANJHAWALA ROAD) FROM KM. (-)0.70 | 7/2020 | 2171.8 | 2171.8 | 958.13 |
24. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L ACCESS CONTROLLED HIGHWAY FROM DND MAHARANI BAGH JN. WITH JAITPUR PUSHTA ROAD OF NH 148NA FROM | 5/2020 | 1467.44 | 1942.89 | 836.96 |
25. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANE ACCESS CONTROLLED OF DELHI SAHARANPUR HIGHWAY FROM AKSHARDHAM NH 9 JUNCTION TO DELHI UP BOR | 6/2020 | 1479.22 | 1479.22 | 918.95 |
26. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | DWARKA EXPRESSWAY FROM KM -0.600 TO KM 5.300 - PKG-I (SHIVMURTI CHOWK-RUB NEAR DWARKA SECTOR 21) | 3/2018 | 2507 | 3030.73 | 1155.7 |
27. | NATIONAL PROJECTS CONSTRUCTION CORPORATION LIMITED | FINANCE | C/O RESIDENTIAL COMPLEX BUILDING FOR CENTRAL BOARD OF INDIRECT TAXES AND CUSTOMS AT SECTOR-9, DWARKA | 7/2018 | 228.5 | 220.27 | 176.28 |
28. | NORTHERN RAILWAY | RAILWAYS | ANAND VIHAR-TILAK BRIDGE 3RD AND 4TH LINE | 4/2012 | 295.68 | 419 | 133.78 |
| Total | 28 | |