S No. | Project Title | Agency Name | Sector Name | Date Of Approval | Cost Original | Cost Anticipated | Month |
1. | AUGMENTATION OF LPG IMPORT TERMINAL FROM 0.6 MMTPA TO 2.5 MMTPA AT KANDLA, GUJARAT | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 03/2018 | 588.2 | 588.2 | APR |
2. | REPLACEMENT OF EXISTING TWIN 42” OFFSHORE PIPELINES AT VADINAR ALONG WITH TWO EXISTING PIPELINE END | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 06/2020 | 1378 | 1378 | MAR |
3. | DELHI VADODARA GREENFIELD ALIGNMENT SECTION OF NH 148N PACKAGE 29 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 09/2020 | 1523.77 | 1523.77 | SEP |
4. | TRANSMISSION SYSTEM FOR PROVIDING CONNECTIVITY TO RE PROJECTS AT BHUJ-II (2000 MW) IN GUJARAT | POWER GRID CORPORATION OF INDIA LIMITED | POWER | 10/2019 | 1031 | 1031 | APR |
5. | PALANPUR-SAMAKHAYALI (DL) | RAIL VIKAS NIGAM LTD. | RAILWAYS | 04/2013 | 1548.66 | 1548.66 | JUN |
6. | RAGHANESDA SOLAR POWER PROJECT | SATLUJ JAL VIDYUT NIGAM LIMITED | POWER | 06/2022 | 642.15 | 642.15 | MAR |
7. | AHMEDABAD-HIMMATNAGAR-UDAIPUR (WR) | WESTERN RAILWAY | RAILWAYS | 04/2008 | 829.74 | 394.14 | JUN |
8. | VIRAMGAM-SAMAKHIALI (DL) | WESTERN RAILWAY | RAILWAYS | 04/2011 | 1037.15 | 446 | JUN |
9. | SURENDRA NAGAR RAJKOT | WESTERN RAILWAY | RAILWAYS | 04/2015 | 1002.39 | 1002.39 | JUN |
| Total | 9 | |