S No. | Sector | Agency | Date Of Approval | Cost Original | Cost Overrun |
1. | ATOMIC ENERGY | NUCLEAR POWER CORPORATION OF INDIA LIMITED | 10/2009 | 11459 | 11058 |
2. | PETROLEUM | OIL & NATURAL GAS CORPORATION LIMITED | 04/2021 | 631.03 | 229.01 |
3. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | 11/2019 | 5251 | 643 |
4. | PETROLEUM | OIL & NATURAL GAS CORPORATION LIMITED | 08/2021 | 885.63 | 401.04 |
5. | PETROLEUM | GAS AUTHORITY OF INDIA LIMITED | 09/2018 | 225.54 | 22.36 |
6. | RAILWAYS | WESTERN RAILWAY | 03/2012 | 248.26 | 280.23 |
7. | RAILWAYS | WESTERN RAILWAY | 05/2022 | 202.5 | 104.62 |
8. | RAILWAYS | WESTERN RAILWAY | 02/2023 | 401.48 | 268.69 |
9. | RAILWAYS | WESTERN RAILWAY | 09/2020 | 529.3 | 8.01 |
10. | RAILWAYS | WESTERN RAILWAY | 05/2022 | 335.34 | 126.57 |
11. | RAILWAYS | WESTERN RAILWAY | 10/2021 | 1011.72 | 68.85 |
12. | RAILWAYS | WESTERN RAILWAY | 04/2008 | 318.24 | 1213.31 |
13. | RAILWAYS | WESTERN RAILWAY | 05/2022 | 216.72 | 133.21 |
14. | RAILWAYS | WESTERN RAILWAY | 06/2022 | 279.23 | 67.71 |
15. | RAILWAYS | WESTERN RAILWAY | 04/2017 | 692.25 | .01 |
16. | RAILWAYS | WESTERN RAILWAY | 05/2022 | 309.81 | 105.57 |
17. | RAILWAYS | WESTERN RAILWAY | 06/2022 | 354.99 | 127.44 |
18. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 02/2020 | 778.15 | 7.52 |
19. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 02/2020 | 752.3 | 13.9 |
20. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 07/2020 | 1710.3 | 216.7 |
21. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 12/2022 | 173.06 | 45.94 |
22. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 03/2021 | 1259 | 651 |
23. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 01/2017 | 1251.11 | 109.89 |
24. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 03/2018 | 1161.39 | 242.61 |
25. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 02/2020 | 606.51 | 50.49 |
26. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 07/2020 | 2271.86 | 1644.14 |
27. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 10/2022 | 246.6 | 44.4 |
28. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 08/2017 | 962.43 | 16.5 |
29. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 12/2017 | 867.97 | 45.52 |
30. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 10/2017 | 232.49 | 143.09 |
31. | URBAN DEVELOPMENT | AHMEDABAD METRO RAIL | 11/2014 | 10773 | 2151.55 |
| Total | 31 | |