S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | KAKRAPAR ATOMIC POWER PROJECT - 3 AND 4 | NUCLEAR POWER CORPORATION OF INDIA LIMITED | ATOMIC ENERGY | 11459 | 10/2009 | 12/2015 | 03/2024 | 99 |
2. | C/O NEW GREENFIELD AIRPORT AT HISSAR, RAJKOT, GUJARAT | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | 1405 | 01/2018 | 08/2022 | 03/2024 | 19 |
3. | EXTENSION OF TERMINAL BUILDING, PTT, APRON AND CAR PARK AT SURAT AIRPORT. | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | 353.25 | 08/2018 | 02/2021 | 03/2024 | 37 |
4. | SUSTAINED EVACUATION OF GAS FROM GANDHAR FIELDS BY INSTALLING A GAS COMPRESSOR AND PIPELINE CONNECTI | GAS AUTHORITY OF INDIA LIMITED | PETROLEUM | 225.54 | 09/2018 | 02/2021 | 03/2024 | 37 |
5. | ACRYLICS OR OXO-ALCOHOL PROJECT AT GUJARAT REFINERY | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 5251 | 11/2019 | 05/2023 | 03/2024 | 10 |
6. | AUGUMENTATION OF SALAYA MATHURA CRUDE OIL PIPELINE SYSTEM | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 1614 | 10/2020 | 08/2023 | 05/2024 | 9 |
7. | REDEVELOPMENT OF LINCH FIELD | OIL & NATURAL GAS CORPORATION LIMITED | PETROLEUM | 631.03 | 04/2021 | 03/2025 | 07/2025 | 4 |
8. | GUJARAT 200 MW (GUVNL TENDER) | NATIONAL THERMAL POWER CORPORATION | POWER | 842.27 | 01/2021 | 07/2022 | 03/2024 | 20 |
9. | 150 MW SOLAR PV PROJECT IN GUJARAT (LIMBDI, MESANKA AND RADHANPUR) | NATIONAL THERMAL POWER CORPORATION | POWER | 674.92 | 05/2021 | 09/2022 | 03/2024 | 18 |
10. | Bagodara Solar Power Project | SATLUJ JAL VIDYUT NIGAM LIMITED | POWER | 339.35 | 05/2021 | 10/2022 | 03/2024 | 17 |
11. | DAYAPAR WIND ENERGY PROJECT 150MW | NATIONAL THERMAL POWER CORPORATION | POWER | 937.8 | 11/2021 | 05/2023 | 06/2024 | 13 |
12. | RAGHANESDA SOLAR POWER PROJECT | SATLUJ JAL VIDYUT NIGAM LIMITED | POWER | 642.15 | 06/2022 | 12/2023 | 02/2024 | 2 |
13. | BHUJ SOLAR 300MW (TRANCHE-IV WIND SOLAR HYBRID) | NATIONAL THERMAL POWER CORPORATION | POWER | 1442.6 | 11/2022 | 03/2024 | 06/2024 | 3 |
14. | DAYAPAR WIND- III (HYBRID TRANCHE-V) | NATIONAL THERMAL POWER CORPORATION | POWER | 1095.01 | 05/2023 | 01/2025 | 05/2025 | 4 |
15. | BHUJ-NALIYA(GC) WITH EXTENSION FROM NALIYA TO VAYOR (WR) | WESTERN RAILWAY | RAILWAYS | 318.24 | 04/2008 | 03/2012 | 05/2024 | 146 |
16. | ANAND GODHRA DOUBLING PROJECT 79 KMS | WESTERN RAILWAY | RAILWAYS | 692.25 | 04/2017 | 03/2020 | 12/2024 | 57 |
17. | MEHSANA PALANPUR DOUBLING PROJECT 65.10 KMS | WESTERN RAILWAY | RAILWAYS | 537.31 | 04/2018 | 03/2024 | 12/2024 | 9 |
18. | FOUR LANING OF BHAVNAGAR-TALAJA SECTION OF NH-8E FROM KM. 7.090 TO KM. 53.585 (DESIGN CH FROM KM. 6. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 998.18 | 05/2016 | 08/2019 | 02/2024 | 54 |
19. | FOUR LANING OF KAGAVADAR - UNA SECTION OF NH-8E FROM KM 139.915 TO KM 180.478 (PACKAGE-IV) IN THE ST | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 723.64 | 05/2016 | 09/2019 | 03/2024 | 54 |
20. | FOUR LANING OF UNA TO KODINAR OF NH-8E FROM KM. 180.478 TO KM 221.610 (PACKAGE-V) IN THE STATE OF GU | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 763.08 | 05/2016 | 08/2019 | 03/2024 | 55 |
21. | 4-LANNING OF KODINAR TO VERAVAL SECTION OF NH-8E FROM KM 221.610 TO KM 263.000 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 829.97 | 07/2016 | 07/2020 | 03/2024 | 44 |
22. | SIX LANNING FROM KM. 401.200 TO 494.410 OF NH-8 ON HYBRID ANNUITY MODE UNDER NHDP-V(PKG VI)REG. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1251.11 | 01/2017 | 12/2020 | 03/2024 | 39 |
23. | JUNAGADH BYPASS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 232.49 | 10/2017 | 04/2021 | 03/2024 | 35 |
24. | CONSTRUCTION OF EIGHT LANE VADODARA KIM EXPRESSWAY FROM KM 254.430 TO KM 279.000 (KIM TO ANKLESHWAR | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1161.39 | 03/2018 | 10/2021 | 09/2024 | 35 |
25. | DEVELOPMENT OF CHILODA GANDHINAGAR SARKHEJ OF NH 147 OLD NH 8C FROM KM 0/0 TO KM 44/042 IN THE STATE | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 867.97 | 12/2017 | 11/2020 | 03/2024 | 40 |
26. | CONSTRUCTION OF MISSING LINKS (SINGLE LANE) IN LAKHPAT GADULI HAJIPIR ODMA KHAVDA DHOLAVIRA MAUVANA | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 400.76 | 10/2018 | 11/2020 | 05/2024 | 42 |
27. | CONSTRUCTION OF SIGNATURE BRIDGE BETWEEN DWARKA AND BEY DWARKA AND ITS APPROACHES IN THE STATE OF GU | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 962.43 | 08/2017 | 09/2020 | 02/2024 | 41 |
28. | CONSTRUCTION OF ROB WITH APPROACHES IN LIEU OF L C NO 165 OF AHMEDABAD PALANPUR BETWEEN RAILWAY STAT | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 166.21 | 06/2020 | 04/2023 | 05/2024 | 13 |
29. | CONSTRUCTION OF FOUR LANE EXPRESSWAY FROM START OF SARDAR PATEL RING ROAD TO SINDHREJ VILLAGE (CH. 0 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 690.3 | 05/2020 | 03/2024 | 08/2024 | 5 |
30. | CONSTRUCTION OF FOUR LANE EXPRESSWAY FROM START OF SINDHREJ VILLAGE (CH. 22.00 TO CH. 48.52) SECTION | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 882 | 05/2020 | 01/2024 | 08/2024 | 7 |
31. | CONSTRUCTION OF FOUR LANE EXPRESSWAY FROM START OF VEJALLKA VILLAGE TO START OF DSIR ZONE OF AHMEDAB | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 691.52 | 05/2020 | 07/2023 | 08/2024 | 13 |
32. | CONSTRUCTION OF FOUR LANE EXPRESSWAY FROM START OF DSIR ZONE OF AHMEDABAD DISTRICT TO ADHELAI VILLAG | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 894 | 05/2020 | 12/2023 | 08/2024 | 8 |
33. | DELHI VADODARA GREENFIELD ALIGNMENT SECTION OF NH 148N PACKAGE 26 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1542.02 | 09/2020 | 02/2024 | 08/2024 | 6 |
34. | DELHI VADODARA GREENFIELD ALIGNMENT SECTION OF NH 148N PACKAGE 27 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1185.69 | 09/2020 | 02/2024 | 03/2024 | 1 |
35. | DELHI VADODARA GREENFIELD ALIGNMENT SECTION OF NH 148N PACKAGE 30 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1669.56 | 11/2019 | 09/2023 | 03/2024 | 6 |
36. | DELHI VADODARA GREENFIELD ALIGNMENT SECTION OF NH 148N PACKAGE 28 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1198.55 | 09/2020 | 11/2023 | 03/2024 | 4 |
37. | CONSTRUCTION OF EIGHT LANE ACCESS CONTROLLED EXPRESSWAY FROM KM 103.400 TO KM 128.000 OF VADODARA MU | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1259 | 03/2021 | 03/2024 | 12/2024 | 9 |
38. | 4L OF DHROL-BHADRA-PATIYA SECTION FROM 0.000 TO KM 13.600 AND BHADRA PATIYA - PIPALIYA SECTION FROM | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 971.03 | 05/2020 | 10/2023 | 04/2024 | 6 |
39. | CONSTRUCTION OF EIGHT LANE ACCESS CONTROLLED EXPRESSWAY FROM KM 217.500 TO KM 254.430 OF VADODARA MU | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2271.86 | 07/2020 | 12/2023 | 06/2024 | 6 |
40. | CONSTRUCTION OF EIGHT LANE EXPRESSWAY FROM KM 190.000 TO KM 217.500 GANDEVA TO ENA SECTION OF VADODA | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1710.3 | 07/2020 | 08/2023 | 06/2024 | 10 |
41. | SANCHORE - SANTALPUR FROM KM 67.000- KM 99.000 OF NH-754K (AJ-RGBS-PACKAGE-3) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 752.3 | 02/2020 | 08/2023 | 03/2024 | 7 |
42. | SANCHORE - SANTALPUR FROM KM 4.888 - KM 35.000 OF NH-754K (AJ-RGBS-PACKAGE-1) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 606.51 | 02/2020 | 06/2023 | 03/2024 | 9 |
43. | 4L OF BAL WORKS OF TALAJA - MAHUVA FROM 54.990 KM. TO 100.450 KM. OF OLD NH-8E (PACKAGE-II) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 536.03 | 03/2021 | 09/2022 | 03/2024 | 18 |
44. | 4L OF BAL WORKS OF MAHUVA TO KAGVADAR FROM 100.450 KM. TO 140.470 KM. OF NH-8E (PKG- III) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 485.75 | 03/2021 | 09/2022 | 03/2024 | 18 |
45. | SANCHORE - SANTALPUR FROM KM 99.000- KM 130.073 OF NH-754K (AJ-RGBS-PACKAGE-4) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 778.15 | 02/2020 | 03/2023 | 03/2024 | 12 |
46. | 4L KODINAR - VERAVAL (PACKAGE VI) FROM KM. 222.400 TO KM. 230.00 (KODINAR BYPASS) OF NH-8E (NH 51 NE | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 162.73 | 03/2022 | 03/2023 | 03/2024 | 12 |
47. | UPGRADATION AND STRENGTHENING TO 2 LANE PS FROM KM 95/500 TO KM 129/775 OF NH 168 G IDAR BHILODA SA | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 237.28 | 09/2022 | 12/2023 | 12/2025 | 24 |
48. | AHMEDABAD METRO RAIL PROJECT PHASE 1 | AHMEDABAD METRO RAIL | URBAN DEVELOPMENT | 10773 | 11/2014 | 12/2018 | 03/2024 | 63 |
49. | AHMEDABAD METRO RAIL PROJECT PHASE II | AHMEDABAD METRO RAIL | URBAN DEVELOPMENT | 5384.17 | 03/2019 | 03/2024 | 12/2024 | 9 |
50. | SURAT METRO RAIL PROJECT | AHMEDABAD METRO RAIL | URBAN DEVELOPMENT | 12020.32 | 03/2019 | 03/2024 | 06/2025 | 15 |
| Total | 50 | |