S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | ESTABLISHMENT OF PERMANENT CAMPUS PHASE 1 OF IIM SIRMAUR | CPWD OF HIGHER EDUCATION | DEPARTMENT OF HIGHER EDUCATION | 392.51 | 09/2018 | 06/2022 | 04/2024 | 22 |
2. | CONSTRUCTION OF PERMANENT CAMPUSES OF CENTRAL UNIVERSITY OF HIMACHAL PRADESH AT DEHRA AND DHARAMSHAL | CENTRAL PUBLIC WORKS DEPARTMENT | DEPARTMENT OF HIGHER EDUCATION | 512.37 | 03/2021 | 08/2022 | 11/2024 | 27 |
3. | CONSTRUCTION OF 300 BEDDED HOSPITAL AND TEACHING BLOCK IN DR YS PARMAR GMC AT NAHAN HIMACHAL PRADESH | CPWD FOR HEALTH | HEALTH AND FAMILY WELFARE | 260 | 12/2018 | 06/2021 | 06/2026 | 60 |
4. | PARBATI HEP (4X200 MW) (NHPC) II | NATIONAL HYDRO-ELECTRIC POWER CORPORATION | POWER | 3919.59 | 09/2002 | 09/2009 | 12/2024 | 183 |
5. | FOUR LANNING OF NERCHOWK-PANDOH BYPASS SECTION OF NH-21(PACKAGE-I KM 190.000 TO KM 221.305) UNDER NH | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1273.71 | 09/2016 | 07/2020 | 06/2024 | 47 |
6. | 4-LANNING OF END OF PANDOH BYPASS TAKOLI IN H.P | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2485.93 | 06/2017 | 06/2020 | 03/2024 | 45 |
| Total | 6 | |