S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | CHURI BENTI UG (0.81 MTY) | CENTRAL COAL FIELDS LIMITED | COAL | 163.51 | 08/2007 | 03/2011 | 06/2024 | 159 |
2. | RAJRAPPA RCE OCP ( 3.0 MTY) | CENTRAL COAL FIELDS LIMITED | COAL | 510.85 | 12/2009 | 03/2016 | 03/2025 | 108 |
3. | KARMA OCP (1.0MTY) | CENTRAL COAL FIELDS LIMITED | COAL | 162.46 | 06/2009 | 03/2014 | 06/2024 | 123 |
4. | MURAIDIH UG TURN-KEY PROJECT | BHARAT COKING COAL LIMITED | COAL | 339.88 | 02/2011 | 04/2014 | 01/2026 | 141 |
5. | MOONIDIH XV SEAM UG | BHARAT COKING COAL LIMITED | COAL | 1230.27 | 08/2011 | 03/2019 | 04/2025 | 73 |
6. | HURA - C OC (3 MTY) | EASTERN COAL FIELDS LIMITED | COAL | 359.69 | 10/2015 | 03/2022 | 03/2029 | 84 |
7. | TETARIAKHAR EXPANSION OCP | CENTRAL COAL FIELDS LIMITED | COAL | 243.52 | 11/2019 | 03/2023 | 03/2025 | 24 |
8. | PATHERDIH 2.5 NLW COAL WASHERY | BHARAT COKING COAL LIMITED | COAL | 243 | 10/2015 | 04/2018 | 09/2024 | 77 |
9. | DEVELOPMENT PLAN OF CBM - BOKARO BLOCK | OIL & NATURAL GAS CORPORATION LIMITED | PETROLEUM | 823.27 | 12/2015 | 03/2023 | 03/2025 | 24 |
10. | CITY GAS DISTRIBUTION (CGD) NETWORK, RANCHI | GAS AUTHORITY OF INDIA LIMITED | PETROLEUM | 226.45 | 10/2017 | 10/2022 | 03/2024 | 17 |
11. | CITY GAS DISTRIBUTION, JAMSHEDPUR | GAS AUTHORITY OF INDIA LIMITED | PETROLEUM | 221.45 | 10/2017 | 10/2022 | 03/2025 | 29 |
12. | CGD PROJECT AT BOKARO, HAZARIBAGH AND RAMGARH DISTRICTS | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 613 | 10/2018 | 12/2029 | 03/2030 | 3 |
13. | DEVELOPMENT OF JHARIA CBM BLOCK (PHASE-1) | OIL & NATURAL GAS CORPORATION LIMITED | PETROLEUM | 431 | 11/2019 | 01/2024 | 12/2024 | 11 |
14. | NORTH KARANPURA STPP (3X660 MW) | NATIONAL THERMAL POWER CORPORATION | POWER | 16242.9 | 02/2014 | 06/2019 | 12/2024 | 66 |
15. | PATRATU STPP-I (3X800MW) | NATIONAL THERMAL POWER CORPORATION | POWER | 17112 | 11/2017 | 03/2023 | 11/2025 | 32 |
16. | BONDAMUNDA RANCHI DOUBLING | SOUTH EASTERN RAILWAY | RAILWAYS | 1724.2 | 03/2016 | 03/2021 | 06/2025 | 51 |
17. | LODHMA TO PISKA LINK LINE BY PASSING HATIA/RANCHI WITH Y CONNECTION (17.2 KM) | SOUTH EASTERN RAILWAY | RAILWAYS | 428.65 | 04/2018 | 06/2022 | 06/2026 | 48 |
18. | CHITRA - BASUKINATH (38.30 KM) | EASTERN RAILWAYS | RAILWAYS | 827.89 | 01/2019 | 03/2026 | 03/2027 | 12 |
19. | GARHWA ROAD - RAIL OVER RAIL | EAST CENTRAL RAILWAYS | RAILWAYS | 262.71 | 03/2017 | 03/2024 | 07/2024 | 4 |
20. | FOUR LANING OF BARHI - KODERMA SECTION OF NH - 31 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 273.46 | 01/2018 | 11/2021 | 03/2024 | 28 |
21. | SIX LANING OF BIHAR - JHARKHAND BORDER (CHORDAHA) TO GORHAR SECTION | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1155.16 | 01/2018 | 11/2021 | 03/2024 | 28 |
22. | 4-LANING OF LOHA - WARANGA SECTION OF NH-361 FROM KM. 187.800 TO KM. 244.369 (DESIGN LENGTH 56.569 K | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1005.08 | 03/2018 | 03/2021 | 03/2024 | 36 |
23. | WIDENING TO 2 LANE WITH PAVED SHOULDERS AND GEOMETRIC IMPROVEMENT OF NH-114A FROM KM 141 TO KM 184 I | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 196 | 12/2016 | 09/2021 | 06/2024 | 33 |
24. | 4L OF PALMA TO GUMLA SECTION OF NH23 FROM KM. 26.00 TO KM. 89.170 ON HAM MODE IN THE STATE OF JHARKH | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1034 | 08/2020 | 03/2024 | 10/2024 | 7 |
25. | 4L OF MIRZA CHAUKI TO FARKKA SECTION OF NH80 FROM KM 215.00 TO KM 260.00 ON HAM MODE IN THE STATE OF | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1302.72 | 11/2021 | 07/2023 | 06/2024 | 11 |
26. | WIDENING TO 2-LANE WITH PAVED SHOULDER FROM KM 0.00 TO 44.00 (KURU-GHAGHRA SECTION) OF NH-143A INCLU | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 153.01 | 02/2020 | 08/2023 | 06/2024 | 10 |
27. | NEW SINTER PLANT AT BOKARO STEEL PLANT | STEEL AUTHORITY OF INDIA LIMITED (SAIL) | STEEL | 1034.01 | 03/2015 | 10/2017 | 03/2026 | 101 |
| Total | 27 | |