S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | C/O AIIMS AT AWANTIPORA (KASHMIR) JAMMU AND KASHMIR | CPWD FOR HEALTH | HEALTH AND FAMILY WELFARE | 1828 | 03/2019 | 09/2025 | 11/2025 | 2 |
2. | CGD PROJECT AT JAMMU DISTRICTS | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 538 | 03/2022 | 03/2032 | 09/2034 | 30 |
3. | PAKAL DUL HYDRO ELECTRIC PROJECT (1000 MW) | CHENAB VELLEY POWER PROJECTS [P] LIMITED | POWER | 8112.12 | 10/2014 | 04/2020 | 12/2026 | 80 |
4. | KIRU HYDRO ELECTRIC PROJECT | CHENAB VELLEY POWER PROJECTS [P] LIMITED | POWER | 4287.59 | 03/2019 | 08/2024 | 12/2026 | 28 |
5. | RATLE HE PROJECT | NATIONAL HYDRO-ELECTRIC POWER CORPORATION | POWER | 5281.94 | 02/2021 | 02/2026 | 08/2028 | 30 |
6. | KWAR HE PROJECT | CHENAB VELLEY POWER PROJECTS [P] LIMITED | POWER | 4526.12 | 05/2022 | 11/2026 | 03/2028 | 16 |
7. | CONSTRUCTION OF STAND ALONE RING ROAD/ BYPASS AROUND JAMMU CITY IN THE STATE OF J AND K ON EPC MODE | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1471.75 | 12/2017 | 07/2021 | 07/2025 | 48 |
8. | UP-GRADATION TO 4-LANE WITH PAVED SHOULDER OF JAMMU-AKHNOOR ROAD SECTION OF NH-144A FROM GANESH VIHA | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 253.44 | 03/2018 | 07/2021 | 10/2025 | 51 |
9. | UP-GRADATION TO 2-LANE WITH PAVED SHOULDER FROM KM 12.850 TO KM20.300 OF 7.450KM LENGTH ON GOHA-KHEL | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 228.39 | 07/2020 | 04/2022 | 10/2026 | 54 |
10. | UP-GRADATION TO 2-LANE WITH PAVED SHOULDER FROM KM 20.300 TO KM 29.030 OF 8.730 KM LENGTH ON GOHA-K | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 210.79 | 07/2020 | 04/2022 | 08/2025 | 40 |
11. | KHELLANI-KHANABAL PKG-2 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 512.43 | 07/2021 | 02/2023 | 06/2026 | 40 |
12. | KHELLANI-KHANABAL PKG-4 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 859.67 | 07/2021 | 08/2023 | 06/2026 | 34 |
13. | KHELLANI-KHANABAL PKG-5 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 497.09 | 07/2021 | 02/2023 | 08/2025 | 30 |
14. | CONSTRUCTION OF FOUR LANE RINGROAD BYPASS SRINAGAR CITY | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2919.96 | 03/2021 | 02/2024 | 10/2025 | 20 |
15. | FOUR LANING OF JAMMU-AKHNOOR PKG-1 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 245.34 | 07/2022 | 01/2025 | 10/2025 | 9 |
16. | DELHI-AMRITSAR-KATRA EXPRESSWAY (PHASE-II PKG-XVI) EXISTING JAKH (VIJAYPUR)-KUNJWANI SECTION OF NH-4 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1821.72 | 09/2021 | 09/2024 | 12/2025 | 15 |
17. | DELHI-AMRITSAR-KATRA EXPRESSWAY (PHASE-II PKG-XIV) FROM JUNCTION WITH PATHANKOT-GURDASPUR ROAD (NH-5 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 3044.02 | 10/2021 | 09/2024 | 12/2025 | 15 |
18. | DELHI-AMRITSAR-KATRA EXPRESSWAY (PHASE-II PKG-XV) [JUNCTION WITH HIRANAGAR ROAD NEAR VILLAGE GURHA B | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2714.95 | 10/2021 | 09/2024 | 02/2026 | 17 |
19. | CORRIDOR EFFICIENCY IMPROVEMENT INCLUDING REMOVAL OF BLACK SPOTS IN LAKHANPUR - SAMBA SECTION OF NH- | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 200.05 | 08/2022 | 06/2024 | 06/2025 | 12 |
20. | CONSTRUCTION OF TUNNELS/VIADUCTS AT IDENTIFIED SLIDING/SLIP ZONES AT KM 130.550 TO KM.130.750; KM. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 442.14 | 09/2021 | 10/2023 | 12/2025 | 26 |
21. | 4L OF KM.165.092 TO KM.171.855 (NORTH BOUND) AND FROM KM.166.895 TO KM.173.638 (SOUTH BOUND), EXCL. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 614.48 | 07/2021 | 08/2024 | 07/2025 | 11 |
22. | 4L TWIN TUBE TUNNEL INCLUDING APPROACHES FROM DIGDOL TO KHUNI NALLAH (NORTH BOUND CONNECTING WITH EX | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1401.87 | 07/2021 | 06/2024 | 07/2025 | 13 |
23. | 4L OF TWIN TUBE TUNNEL CONFIGURATION INCLUDING APPROACHES FROM MAROG TO DIGDOL (FROM KM.154.210 TO K | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1912.17 | 07/2021 | 02/2025 | 05/2026 | 15 |
24. | JAMMU - AKHNOOR SECTION OF NH 144A PKG-3B | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 198.28 | 07/2022 | 03/2025 | 08/2025 | 5 |
25. | CONSTRUCTION OF TWIN TUBE TUNNELS ON JAMMU KASHMIR RING ROAD (NH-244A) BETWEEN DESIGN CH. 50+600 TO | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 939.86 | 03/2023 | 06/2025 | 03/2026 | 9 |
26. | 2L NH-1 FROM KM 8.660 TO KM 33.775 (SUMBAL TO WAYUL) TO 4L DUAL CARRIAGEWAY NH STANDARD AS PART OF S | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1183.6 | 09/2022 | 06/2026 | 12/2026 | 6 |
27. | DELHI AMRITSAR KATRA EXPRESSWAY (PHASE-II PKG XVIII) DEVELOPMENT AND UPGRADATION OF FOUR LANE ACCESS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1107 | 03/2023 | 11/2025 | 03/2026 | 4 |
28. | 4/6L ACCESS CONTROL EXPRESSWAY FROM DESIGN CHAINAGE KM 515.000 TO 528.300 (KUNJWANI TO SIDHRA SECTIO | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2474.47 | 08/2022 | 06/2025 | 02/2026 | 8 |
| Total | 28 | |