S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | CONSTRUCTION OF PERMANENT CAMPUS OF IIM JAMMU (PHASE 1) | CPWD OF HIGHER EDUCATION | DEPARTMENT OF HIGHER EDUCATION | 424.93 | 03/2019 | 07/2022 | 05/2024 | 22 |
2. | CONSTRUCTION OF AIIMS AT JAMMU VIJAYPUR, SAMBA JAMMU AND KASHMIR | CPWD FOR HEALTH | HEALTH AND FAMILY WELFARE | 1404 | 03/2019 | 09/2023 | 05/2024 | 8 |
3. | PAKAL DUL HYDRO ELECTRIC PROJECT (1000 MW) | CHENAB VELLEY POWER PROJECTS [P] LIMITED | POWER | 8112.12 | 10/2014 | 04/2020 | 09/2026 | 77 |
4. | KIRU HYDRO ELECTRIC PROJECT | CHENAB VELLEY POWER PROJECTS [P] LIMITED | POWER | 4287.59 | 03/2019 | 08/2024 | 09/2026 | 25 |
5. | RATLE HE PROJECT | NATIONAL HYDRO-ELECTRIC POWER CORPORATION | POWER | 5281.94 | 02/2021 | 02/2026 | 12/2026 | 10 |
6. | KWAR HE PROJECT | CHENAB VELLEY POWER PROJECTS [P] LIMITED | POWER | 4526.12 | 05/2022 | 11/2026 | 12/2027 | 13 |
7. | UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR | NORTHERN RAILWAY | RAILWAYS | 2500 | 03/1995 | 11/2002 | 08/2024 | 261 |
8. | FOUR LANING OF UDHAMBUR - RAMBAN SECTION OF NH-1A | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2136.97 | 12/2015 | 12/2018 | 04/2024 | 64 |
9. | CONSTRUCTION OF STAND ALONE RING ROAD/ BYPASS AROUND JAMMU CITY IN THE STATE OF J AND K ON EPC MODE | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1471.75 | 12/2017 | 07/2021 | 06/2024 | 35 |
10. | UP-GRADATION TO 4-LANE WITH PAVED SHOULDER OF JAMMU-AKHNOOR ROAD SECTION OF NH-144A FROM GANESH VIHA | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 253.44 | 03/2018 | 07/2021 | 03/2024 | 32 |
11. | UP-GRADATION TO 2-LANE WITH PAVED SHOULDER FROM KM 12.850 TO KM20.300 OF 7.450KM LENGTH ON GOHA-KHEL | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 228.39 | 07/2020 | 04/2022 | 07/2024 | 27 |
12. | UP-GRADATION TO 2-LANE WITH PAVED SHOULDER FROM KM 20.300 TO KM 29.030 OF 8.730 KM LENGTH ON GOHA-K | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 210.79 | 07/2020 | 04/2022 | 07/2024 | 27 |
13. | KHELLANI-KHANABAL PKG-1 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 486.45 | 03/2021 | 09/2022 | 06/2024 | 21 |
14. | KHELLANI-KHANABAL PKG-3 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 398.51 | 03/2021 | 12/2022 | 07/2024 | 19 |
15. | KHELLANI-KHANABAL PKG-2 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 512.43 | 07/2021 | 02/2023 | 08/2025 | 30 |
16. | KHELLANI-KHANABAL PKG-4 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 859.67 | 07/2021 | 08/2023 | 01/2025 | 17 |
17. | KHELLANI-KHANABAL PKG-5 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 497.09 | 07/2021 | 02/2023 | 07/2024 | 17 |
18. | GOHA-KHELLANI PKG-3 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 431.28 | 02/2021 | 03/2023 | 07/2024 | 16 |
19. | BALANCE WORKS OF FOUR LANING FROM RAMBAN KM 151.00 TO BANIHAL KM 187.00 OF NH-1A (NOW NH-44) WITH VA | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 811.19 | 09/2021 | 12/2023 | 05/2024 | 5 |
20. | CONSTRUCTION OF FOUR LANE RINGROAD BYPASS SRINAGAR CITY | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2919.96 | 03/2021 | 02/2024 | 02/2025 | 12 |
21. | CONSTRUCTION OF TUNNELS/VIADUCTS AT IDENTIFIED SLIDING/SLIP ZONES AT KM 130.550 TO KM.130.750; KM. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 442.14 | 09/2021 | 10/2023 | 07/2024 | 9 |
22. | BANIHAL BYPASS (DELINKED FROM SRINAGAR - BANIHAL) FROM KM. 187.00 TO KM. 189.350 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 336.01 | 01/2020 | 01/2024 | 07/2024 | 6 |
23. | CONSTRUCTION OF EMERGENCY LANDING FACILITY FROM KM. 246.60 TO KM. 249.70 ON SRINAGAR - BANIHAL SECTI | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 157.05 | 07/2019 | 10/2020 | 04/2024 | 42 |
24. | REHABILITATION AND UPGRADATION TO 2 LANE WITH PAVED SHOULDER FROM EXISTING CHAINAGE KM 64.535 TO K | BORDER ROAD ORGANISATION | ROAD TRANSPORT AND HIGHWAYS | 152.93 | 03/2020 | 09/2023 | 06/2024 | 9 |
| Total | 24 | |