Details of ongoing projects costing Rs.150 and above in Jammu & Kashmir
S No.Sector NameAgency NameProject NameDate Of ApprovalCost OriginalCost AnticipatedExpenditure
1.CIVIL AVIATIONAIRPORT AUTHORITY OF INDIA LIMITEDJAMMU - CONSTRUCTION OF NEW CIVIL ENCLAVE 7/2022861.37861.3717.21
2.DEPARTMENT OF HIGHER EDUCATIONCPWD OF HIGHER EDUCATIONCONSTRUCTION OF PERMANENT CAMPUS OF IIM JAMMU (PHASE 1) 3/2019424.93500.91448.15
3.DEPARTMENT OF HIGHER EDUCATIONCPWD OF HIGHER EDUCATIONCONSTRUCTION OF PERMANENT CAMPUS IIT JAMMU (PHASE 1C) 1/20186761085.0454.75
4.HEALTH AND FAMILY WELFARECPWD FOR HEALTHC/O AIIMS AT AWANTIPORA (KASHMIR) JAMMU AND KASHMIR 3/201918281828976.64
5.HEALTH AND FAMILY WELFARECPWD FOR HEALTHCONSTRUCTION OF AIIMS AT JAMMU VIJAYPUR, SAMBA JAMMU AND KASHMIR 3/2019140416201299.97
6.PETROLEUMBHARAT PETROLEUM CORPORATION LIMITEDSETTING UP A COMMON USER PETROLEUM TERMINAL AT JAMMU FOR RE-SITEMENT OF EXISTING DEPOTS OF PSU OMCS 4/2021676.89676.89210.95
7.POWERCHENAB VELLEY POWER PROJECTS [P] LIMITEDKIRU HYDRO ELECTRIC PROJECT 3/20194287.594287.591673.44
8.POWERCHENAB VELLEY POWER PROJECTS [P] LIMITEDKWAR HE PROJECT 5/20224526.124526.12592.41
9.POWERNATIONAL HYDRO-ELECTRIC POWER CORPORATIONRATLE HE PROJECT 2/20215281.945281.94671.59
10.POWERCHENAB VELLEY POWER PROJECTS [P] LIMITEDPAKAL DUL HYDRO ELECTRIC PROJECT (1000 MW) 10/20148112.128112.124077.8
11.RAILWAYSNORTHERN RAILWAYUDHAMPUR-SRINAGAR-BARAMULLA (NL),NR 3/199525004115938931
12.ROAD TRANSPORT AND HIGHWAYSBORDER ROAD ORGANISATIONCONSTRUCTION OF 4 LANE WITH PAVED SHOULDER FROM (DESIGN CH. 14+200 TO 24+400), (DESIGN CH. 35+300 TO6/2022832.46823.46227.5
13.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIADELHI-AMRITSAR-KATRA EXPRESSWAY (PHASE-II PKG-XIV) FROM JUNCTION WITH PATHANKOT-GURDASPUR ROAD (NH-510/20213044.023044.022085.81
14.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIACORRIDOR EFFICIENCY IMPROVEMENT INCLUDING REMOVAL OF BLACK SPOTS IN LAKHANPUR - SAMBA SECTION OF NH-8/2022200.05200.0565.62
15.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIA4/6L ACCESS CONTROL EXPRESSWAY FROM DESIGN CHAINAGE KM 515.000 TO 528.300 (KUNJWANI TO SIDHRA SECTIO8/20222474.472675.93489
16.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.UP-GRADATION TO 4-LANE WITH PAVED SHOULDER OF JAMMU-AKHNOOR ROAD SECTION OF NH-144A FROM GANESH VIHA3/2018253.44253.44176.87
17.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIA2L NH-1 FROM KM 8.660 TO KM 33.775 (SUMBAL TO WAYUL) TO 4L DUAL CARRIAGEWAY NH STANDARD AS PART OF S9/20221183.61183.60
18.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIACONSTRUCTION OF TUNNELS/VIADUCTS AT IDENTIFIED SLIDING/SLIP ZONES AT KM 130.550 TO KM.130.750; KM. 9/2021442.14442.14206.63
19.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIADELHI-AMRITSAR-KATRA EXPRESSWAY (PHASE-II PKG-XVI) EXISTING JAKH (VIJAYPUR)-KUNJWANI SECTION OF NH-49/20211821.721917.322273.06
20.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.UP-GRADATION TO 2-LANE WITH PAVED SHOULDER FROM KM 20.300 TO KM 29.030 OF 8.730 KM LENGTH ON GOHA-K7/2020210.79210.7957.08
21.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.KHELLANI-KHANABAL PKG-1 3/2021486.45486.45115.47
22.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIABALANCE WORKS OF FOUR LANING FROM RAMBAN KM 151.00 TO BANIHAL KM 187.00 OF NH-1A (NOW NH-44) WITH VA9/2021811.19811.19723.48
23.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.KHELLANI-KHANABAL PKG-2 7/2021512.43512.4356.81
24.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIABANIHAL BYPASS (DELINKED FROM SRINAGAR - BANIHAL) FROM KM. 187.00 TO KM. 189.350 1/2020336.01336.01148.02
25.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.CONSTRUCTION OF (I) CONNECTING ROAD FROM Z-MORH TUNNEL TO ZOJILA TUNNEL AND (II) 14.150 KM LONG BI-D8/20206808.696808.692934.54
26.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIADELHI AMRITSAR KATRA EXPRESSWAY (PHASE-II PKG XVIII) DEVELOPMENT AND UPGRADATION OF FOUR LANE ACCESS3/20231107110731.98
27.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIACONSTRUCTION OF FOUR LANE RINGROAD BYPASS SRINAGAR CITY 3/20212919.962919.961993.5
28.ROAD TRANSPORT AND HIGHWAYSBORDER ROAD ORGANISATIONREHABILITATION AND UPGRADATION TO 2 LANE WITH PAVED SHOULDER FROM EXISTING CHAINAGE KM 49.150 TO KM 3/2020796.97796.97323.85
29.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.DONIPAWA TO ASHAJIPORA BYPASS PKG-7 3/2021260.4260.4185.43
30.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIACONSTRUCTION OF TWIN TUBE TUNNELS ON JAMMU KASHMIR RING ROAD (NH-244A) BETWEEN DESIGN CH. 50+600 TO 3/2023939.86939.86125.21
31.ROAD TRANSPORT AND HIGHWAYSBORDER ROAD ORGANISATIONREHABILITATION AND UPGRADATION TO 2 LANE WITH PAVED SHOULDER FROM EXISTING CHAINAGE KM 134.95 TO KM2/2021395.25395.25140.42
32.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.FOUR LANING OF JAMMU-AKHNOOR PKG-1 7/2022245.34245.3428.91
33.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.JAMMU - AKHNOOR SECTION OF NH 144A PKG-3B 7/2022198.28198.2836.98
34.ROAD TRANSPORT AND HIGHWAYSBORDER ROAD ORGANISATIONREHABILITATION AND UPGRADATION TO 2 LANE WITH PAVED SHOULDER FROM EXISTING CHAINAGE KM 30.000 TO K7/2020272.49272.49133.66
35.ROAD TRANSPORT AND HIGHWAYSBORDER ROAD ORGANISATIONREHABILITATION AND UPGRADATION TO 2 LANE WITH PAVED SHOULDER FROM EXISTING CHAINAGE KM 64.535 TO K3/2020152.93152.9390.3
36.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.GOHA-KHELLANI PKG-3 2/2021431.28431.28246.7
37.ROAD TRANSPORT AND HIGHWAYSBORDER ROAD ORGANISATIONREHABILITATION AND UPGRADATION TO 2 LANE WITH PAVED SHOULDER FROM EXISTING CHAINAGE KM 102 TO KM 133/2021642.24642.24345.14
38.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIA4L OF TWIN TUBE TUNNEL CONFIGURATION INCLUDING APPROACHES FROM MAROG TO DIGDOL (FROM KM.154.210 TO K7/20211912.171912.1731.23
39.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.UP-GRADATION TO 2-LANE WITH PAVED SHOULDER FROM KM 12.850 TO KM20.300 OF 7.450KM LENGTH ON GOHA-KHEL7/2020228.39228.3960.25
40.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.CONSTRUCTION, OPERATION AND MAINTENANCE OF Z-MORH TUNNEL INCLUDING APPROACHES ON NH-01 SRINAGAR-SONA12/20192680.422680.420
41.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIACONSTRUCTION OF STAND ALONE RING ROAD/ BYPASS AROUND JAMMU CITY IN THE STATE OF J AND K ON EPC MODE 12/20171471.751471.751728.23
42.ROAD TRANSPORT AND HIGHWAYSBORDER ROAD ORGANISATIONREHABILITATION AND UPGRADATION TO 2 LANE WITH PAVED SHOULDER FROM DESIGN CHAINAGE KM 162.800 TO KM 10/2022562.45562.450
43.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIACONSTRUCTION OF EMERGENCY LANDING FACILITY FROM KM. 246.60 TO KM. 249.70 ON SRINAGAR - BANIHAL SECTI7/2019157.05157.05133.19
44.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIAFOUR LANING OF UDHAMBUR - RAMBAN SECTION OF NH-1A 12/20152136.972136.972362.99
45.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.KHELLANI-KHANABAL PKG-5 7/2021497.09497.09111.87
46.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIADELHI-AMRITSAR-KATRA EXPRESSWAY (PHASE-II PKG-XV) [JUNCTION WITH HIRANAGAR ROAD NEAR VILLAGE GURHA B10/20212714.952714.952259.72
47.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.KHELLANI-KHANABAL PKG-3 3/2021398.51398.5173.81
48.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIA4L TWIN TUBE TUNNEL INCLUDING APPROACHES FROM DIGDOL TO KHUNI NALLAH (NORTH BOUND CONNECTING WITH EX7/20211401.871401.87346.07
49.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd.KHELLANI-KHANABAL PKG-4 7/2021859.67859.67117.72
50.ROAD TRANSPORT AND HIGHWAYSNATIONAL HIGHWAYS AUTHORITY OF INDIA4L OF KM.165.092 TO KM.171.855 (NORTH BOUND) AND FROM KM.166.895 TO KM.173.638 (SOUTH BOUND), EXCL. 7/2021614.48614.48114.44
Total50