S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | C/O PERMANENT CAMPUS OF IIT PALAKKAD PHASE IA AT PUDESSERY VILLAGE,KANJIKODE WEST, DISTRICT PALAKKA | CPWD OF HIGHER EDUCATION | DEPARTMENT OF HIGHER EDUCATION | 753.63 | 07/2019 | 03/2021 | 12/2024 | 45 |
2. | C/O NEW HOSPITAL BLOCK FOR SREE CHITRA TIRUNAL INSTITIUTE OF MEDICAL SCIENCE AND TECHNOLOGY (SCTIMST | CPWD FOR HEALTH | HEALTH AND FAMILY WELFARE | 150.29 | 09/2017 | 03/2020 | 05/2024 | 50 |
3. | KOCHI SALEM LPG PIPELINE PROJECT | Kochi Salem Pipeline Private Limited(JV) | PETROLEUM | 1112 | 12/2015 | 06/2019 | 02/2025 | 68 |
4. | KUMBALAM-THURAVUR - PATCH DOUBLING (15.59 KM) | SOUTHERN RAILWAY | RAILWAYS | 812.85 | 12/2011 | 08/2023 | 09/2026 | 37 |
5. | 4 LANNING OF MUKKOLA JUNCTION TO KERALA/ TAMIL NADU BORDER FROM KM 26.500 TO KM 43.000 OF NH-47 IN T | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 804.97 | 04/2016 | 06/2018 | 04/2024 | 70 |
6. | 6-LANING OF KOZHIKODE BYPASS (CALICUT BYPASS) (I.E. VENGALAM JN. TO RAMANATTUKARA JN.) SECTION OF NH | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1424.77 | 02/2018 | 02/2023 | 12/2024 | 22 |
7. | SIX LANING OF KADAMBATTUKONAM TO KAZHAKKOOTTAM SECTION OF NH-66(OLD NH-47) FROM KM. 517+250 TO KM.54 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 3635.64 | 12/2021 | 01/2025 | 08/2025 | 7 |
8. | 6L MINOR BRIDGE (PALOLI PALAM) AT KM. 203.160 and MAJOR BRIDGE (MORAD) AT KM. 204.895 AND ALLIED WOR | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 210.37 | 03/2020 | 06/2022 | 03/2024 | 21 |
9. | SIX LANING OF KOTTUKULANGARA (DESIGN KM. 454+500) TO START OF KOLLAM BYPASS (DESIGN KM. 486+000) SEC | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2842.14 | 06/2021 | 10/2024 | 12/2025 | 14 |
10. | SIX LANING OF THALIPARAMBHA- MUZHAPILANGAD SECTION FROM KM 137.900 TO KM. 170.600 OF NH-17 (NEW NH | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2714.6 | 08/2020 | 02/2024 | 12/2024 | 10 |
11. | 6L OF AZHIYUR-VENGALAM FROM KM. 189.200 TO KM. 230.400 OF NH-66 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 3219.47 | 10/2020 | 04/2024 | 05/2025 | 13 |
12. | SIX LANING OF KT/KL BORDER (THALAPPDY) TO CHENGALA SECTION OF NH17 (NEW NH-66) FROM CH. 17.200 TO CH | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1981.07 | 05/2020 | 05/2024 | 12/2024 | 7 |
13. | SIX LANING OF NEELESHWARAM TO THALIPARAMBHA SECTION FROM CH. 94+540 (EXISTING KM 96+450) TO CH. 134+ | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 3041.65 | 06/2020 | 04/2024 | 12/2024 | 8 |
14. | SIX LANING OF CHENGALA TO NEELESHWARAM SECTION OF NH-17 (NEW NH-66) FROM CH. 56+200 (EXISTING KM 57+ | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1746.45 | 06/2020 | 04/2024 | 12/2024 | 8 |
| Total | 14 | |