S No. | Agency Name | Sector Name | Project Name | Date Of Approval | Cost Original | Cost Anticipated | Expenditure |
1. | BHARAT PETROLEUM CORPORATION LIMITED | PETROLEUM | REPLACEMENT AND EXTENSION OF JETTY PIPELINES AT KOCHI REFINERY | 3/2023 | 621.87 | 621.87 | 31.15 |
2. | CPWD FOR HEALTH | HEALTH AND FAMILY WELFARE | C/O NEW HOSPITAL BLOCK FOR SREE CHITRA TIRUNAL INSTITIUTE OF MEDICAL SCIENCE AND TECHNOLOGY (SCTIMST | 9/2017 | 150.29 | 162 | 146.95 |
3. | CPWD OF HIGHER EDUCATION | DEPARTMENT OF HIGHER EDUCATION | C/O PERMANENT CAMPUS OF IIT PALAKKAD PHASE IA AT PUDESSERY VILLAGE,KANJIKODE WEST, DISTRICT PALAKKA | 7/2019 | 753.63 | 753.63 | 411.86 |
4. | CPWD OF HIGHER EDUCATION | DEPARTMENT OF HIGHER EDUCATION | CONSTRUCTION OF MEGA HOSTEL II FOR NIT CALICUT KERALA | 1/2010 | 165.23 | 165.23 | 135.78 |
5. | KOCHI METRO RAIL CORPORATION LTD | URBAN DEVELOPMENT | KOCHI METRO RAIL PROJECT | 7/2012 | 5181.79 | 6218.14 | 6059.17 |
6. | Kochi Salem Pipeline Private Limited(JV) | PETROLEUM | KOCHI SALEM LPG PIPELINE PROJECT | 12/2015 | 1112 | 1507.24 | 1108.43 |
7. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO 2 LANES WITH PAVED SHOULDERS FROM KM.87/000 TO 133/720 (NATTUKAL TO THANAU JN. IN PALAKK | 2/2017 | 294.28 | 296.53 | 285.3 |
8. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO 2-LANE WITH PAVED SHOULDERS FROM KM 119/017 TO KM 161/300 ON NH 85 (OLD NH 49) | 2/2017 | 380.76 | 372.87 | 331.51 |
9. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING OF KADAMBATTUKONAM TO KAZHAKKOOTTAM SECTION OF NH-66(OLD NH-47) FROM KM. 517+250 TO KM.54 | 12/2021 | 3635.64 | 3635.64 | 252.86 |
10. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING OF PARAVOOR(DESIGN KM. 417+000) TO KOTTUKULANGARA(DESIGN KM. 454+500) SECTION OF NEW NH-6 | 12/2021 | 3273.61 | 3273.61 | 327.98 |
11. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING FROM THALIKULAM TO KODUNGALLUR SECTION OF NH – 66 (OLD NH-17) FROM DESIGN CH.369+015 (EX. | 6/2021 | 2595 | 3994.6 | 2883.02 |
12. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L OF AZHIYUR-VENGALAM FROM KM. 189.200 TO KM. 230.400 OF NH-66 | 10/2020 | 3219.47 | 3713.14 | 2015.46 |
13. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING FROM KAPPIRIKKAD TO THALIKULAM SECTION OF NH – 66 (OLD NH-17) FROM DESIGN CH. 335+850 (EX | 6/2021 | 3606 | 3923.82 | 2945.82 |
14. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4-LANNING OF THALSERRY -MAHE BYPASS | 9/2017 | 1124.11 | 1567.73 | 1499.29 |
15. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING OF KT/KL BORDER (THALAPPDY) TO CHENGALA SECTION OF NH17 (NEW NH-66) FROM CH. 17.200 TO CH | 5/2020 | 1981.07 | 1981.07 | 1321.04 |
16. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING OF THURAVOOR (DESIGN KM. 378+612) TO PARAVOOR (DESIGN KM.417+000) SECTION OF NEW NH-66 (O | 9/2021 | 2878.97 | 2878.97 | 271.56 |
17. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING FROM START OF VALANCHERY BYPASS TO KAPPIRIKKAD-SECTION OF NH-66(OLD NH-17) FROM DESIGN CH | 2/2021 | 3375.31 | 3790.17 | 2082.35 |
18. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING FROM KODUNGALLUR TO EDAPALLY SECTION OF NH –66 (OLD NH-17) FROM DESIGN CHAINAGE 397+750 ( | 11/2021 | 3565.82 | 3064.11 | 1763 |
19. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING OF RAMANATTUKARA JUNCTION TO START OF VALANCHERY BYPASS SECTION OF NH-66 (OLD NH-17) FROM | 1/2021 | 4265.42 | 4708.42 | 3121.76 |
20. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4 LANNING OF MUKKOLA JUNCTION TO KERALA/ TAMIL NADU BORDER FROM KM 26.500 TO KM 43.000 OF NH-47 IN T | 4/2016 | 804.97 | 571.45 | 655.6 |
21. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING OF KOTTUKULANGARA (DESIGN KM. 454+500) TO START OF KOLLAM BYPASS (DESIGN KM. 486+000) SEC | 6/2021 | 2842.14 | 2842.14 | 378.44 |
22. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L MINOR BRIDGE (PALOLI PALAM) AT KM. 203.160 and MAJOR BRIDGE (MORAD) AT KM. 204.895 AND ALLIED WOR | 3/2020 | 210.37 | 214.36 | 198.01 |
23. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING OF CHENGALA TO NEELESHWARAM SECTION OF NH-17 (NEW NH-66) FROM CH. 56+200 (EXISTING KM 57+ | 6/2020 | 1746.45 | 1746.45 | 1018.98 |
24. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6-LANING OF KOZHIKODE BYPASS (CALICUT BYPASS) (I.E. VENGALAM JN. TO RAMANATTUKARA JN.) SECTION OF NH | 2/2018 | 1424.77 | 1862.77 | 664.68 |
25. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING OF NEELESHWARAM TO THALIPARAMBHA SECTION FROM CH. 94+540 (EXISTING KM 96+450) TO CH. 134+ | 6/2020 | 3041.65 | 3041.65 | 2007.08 |
26. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | WIDENING/DEVELOPMENT OF EXISTING NH-85 FROM KM 0.000 TO KM 124.636 SECTION TO 2L/@L+PS SECTION IN TH | 8/2022 | 1231.74 | 1231.74 | 20.09 |
27. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING OF THALIPARAMBHA- MUZHAPILANGAD SECTION FROM KM 137.900 TO KM. 170.600 OF NH-17 (NEW NH | 8/2020 | 2714.6 | 2714.6 | 1614.54 |
28. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING OF START OF KOLLAM BYPASS (KM.486+000) KADAMBATTUKONAM (KM.517+250) SECTION OF NEW NH-66 | 6/2021 | 2641.37 | 2641.37 | 337.39 |
29. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF 6 LANE ELEVATED CORRIDOR ALONG WITH DEVELOPMENT OF EXISTING 4 LANE ROAD AT GROUND LE | 8/2022 | 2429.52 | 2429.52 | 318 |
30. | SOUTHERN RAILWAY | RAILWAYS | TRIVANDRUM-KANYAKUMARI DOUBLING | 2/2015 | 1431.9 | 3785.45 | 3019.36 |
31. | SOUTHERN RAILWAY | RAILWAYS | ERNAKULAM-KUMBALAM - PATCH DOUBLING (7.71 KM) | 12/2010 | 600.82 | 595.39 | 269.98 |
32. | SOUTHERN RAILWAY | RAILWAYS | TURAVUR-AMBALAPUZHA DOUBLING | 2/2015 | 1000 | 1416.49 | 1.63 |
33. | SOUTHERN RAILWAY | RAILWAYS | KUMBALAM-THURAVUR - PATCH DOUBLING (15.59 KM) | 12/2011 | 812.85 | 802.8 | 258.01 |
| Total | 33 | |