S No. | Sector | Agency | Date Of Approval | Cost Original | Cost Overrun |
1. | PETROLEUM | MANGALORE REFINERY AND PETROCHEMICALS LIMITED | 06/2020 | 200 | 104 |
2. | RAILWAYS | SOUTH WESTERN RAILWAY | 04/2010 | 986.3 | 663.01 |
3. | RAILWAYS | SOUTH WESTERN RAILWAY | 02/2011 | 162.13 | 186.72 |
4. | RAILWAYS | RAIL VIKAS NIGAM LTD. | 04/2010 | 2127 | 1565.6 |
5. | RAILWAYS | SOUTH WESTERN RAILWAY | 03/1996 | 644.78 | 180.53 |
6. | RAILWAYS | SOUTH WESTERN RAILWAY | 06/2019 | 663.03 | 85.82 |
7. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 03/2018 | 325.86 | 60.55 |
8. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 12/2017 | 297.3 | 20.98 |
9. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 01/2017 | 166.67 | 97.67 |
10. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 10/2021 | 1331.77 | 751.21 |
11. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 03/2021 | 1065.06 | 379.44 |
12. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 03/2018 | 159.97 | 82.64 |
13. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 08/2016 | 1167.42 | 56.59 |
14. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 02/2017 | 157.32 | 30.29 |
15. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 10/2019 | 1225.24 | 280.61 |
16. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 09/2016 | 950.69 | 157.31 |
17. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 08/2016 | 175.5 | 66.1 |
18. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 05/2014 | 1655.01 | 983.99 |
| Total | 18 | |