S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | ADDITIONAL INFRASTRUCTURE AT IISC BANGALORE SH RCC MONOLITHIC FOR MEN WOMEN HOSTEL | CENTRAL PUBLIC WORKS DEPARTMENT | DEPARTMENT OF HIGHER EDUCATION | 316.25 | 08/2021 | 02/2024 | 06/2024 | 4 |
2. | CONSTRUCTION OF 80000MT LPG CAVERN AT MANGALORE | HINDUSTAN PETROLEUM CORPORATION LIMITED | PETROLEUM | 854 | 12/2018 | 12/2022 | 09/2024 | 21 |
3. | DEVANGONTHI MARKETING TERMINAL | MANGALORE REFINERY AND PETROCHEMICALS LIMITED | PETROLEUM | 200 | 06/2020 | 06/2023 | 06/2024 | 12 |
4. | REVAMPING, AUGMENTATION OF FACILITIES AT EXISTING PORT TERMINAL AT MANGALORE | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 463 | 01/2022 | 07/2025 | 12/2025 | 5 |
5. | BAGALKOT-KUDACHI NL | SOUTH WESTERN RAILWAY | RAILWAYS | 986.3 | 04/2010 | 03/2016 | 03/2027 | 132 |
6. | SHIMOGA-HARIHAR NL | SOUTH WESTERN RAILWAY | RAILWAYS | 832.47 | 04/2011 | 03/2016 | 12/2028 | 153 |
7. | HOSPET-HUBLI-LONDA-VASCODAGAMA DL | RAIL VIKAS NIGAM LTD. | RAILWAYS | 2127 | 04/2010 | 03/2023 | 12/2026 | 45 |
8. | GADAG-WADI NL | SOUTH WESTERN RAILWAY | RAILWAYS | 2841.84 | 04/2013 | 12/2018 | 03/2027 | 99 |
9. | MARIKUPPAM - KUPPAM | SOUTH WESTERN RAILWAY | RAILWAYS | 279.54 | 04/2012 | 03/2016 | 06/2026 | 123 |
10. | KADUR CHIKMAGALUR SAKLESHPUR NEW LINE (93 KM) | SOUTH WESTERN RAILWAY | RAILWAYS | 644.78 | 03/1996 | 03/2017 | 06/2025 | 99 |
11. | BELGAUM-DHARWAD VIA KITTUR (73.10 KM) (UMBRELLA WORK PB#22/2019-20/NR) | SOUTH WESTERN RAILWAY | RAILWAYS | 1590.8 | 09/2020 | 03/2026 | 03/2028 | 24 |
12. | SHIMOGA-SHIKARIPURA-RANEBENNUR (UMBRELLA WORK PB#23/2018-19/NR) | SOUTH WESTERN RAILWAY | RAILWAYS | 1453.73 | 09/2019 | 12/2027 | 03/2028 | 3 |
13. | WHITEFIELD-KOLAR (52.9 KM) | SOUTH WESTERN RAILWAY | RAILWAYS | 162.13 | 02/2011 | 04/2028 | 12/2030 | 32 |
14. | STRENGTHENING AND WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM.106.00 TO 153.00 OF NH-218 BIJAP | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 165.67 | 03/2015 | 11/2015 | 04/2024 | 101 |
15. | 4-LANING OF GOA/KARNATAKA BORDER-KUNDAPUR SECTION | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1655.01 | 05/2014 | 08/2016 | 12/2024 | 100 |
16. | 4-LANNING EXISTING KM 189.700 TO 237.00] HASSAN TO MARANAHALLY | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 701.4 | 03/2016 | 03/2019 | 03/2025 | 72 |
17. | HOSPET-BELLARY-KARNATAKA AP BORDER | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1167.42 | 08/2016 | 03/2019 | 05/2025 | 74 |
18. | TWO/FOUR LANNING OF BRT TIGER RESERVE BOUNDARY TO BANGALORE SECTION OF NH-209(EXISTING CHAINAGE FROM | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 950.69 | 09/2016 | 08/2019 | 05/2024 | 57 |
19. | IMPROVEMENTS AND RECONSTRUCTION TO TWO LANE WITH PAVED SHOULDERS FROM KM 243.20 TO KM 290.20 OF NH | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 175.5 | 08/2016 | 02/2017 | 07/2024 | 89 |
20. | WIDENING TWO LANE WITH PAVED SHOULDERS FROM FROM KM.56.00 TO 106.00 OF NH-218 (218-KNT-2014-15-775) | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 159.12 | 03/2015 | 01/2016 | 03/2024 | 98 |
21. | CONSTRUCTION OF MAJOR BRIDGE AT KM 180.865 ACROSS RIVER KRISHNA ON NH-167 HAGARI – JADERCELA SECTION | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 157.32 | 02/2017 | 05/2019 | 11/2024 | 66 |
22. | CONSTRUCTION OF MAJOR BRIDGE ACROSS SHARAVATHI BACKWATERS AND APPROCHES BETWEEN AMBARGODU AND KALASA | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 423.15 | 03/2019 | 12/2019 | 11/2024 | 59 |
23. | 4L OF ADDAHOLE TO BANTWAL CROSS SECTION INCLUDING FLYOVER AT KALLADKA TOWN | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1100.88 | 03/2021 | 11/2021 | 11/2024 | 36 |
24. | 4L OF ADDAHOLE TO BANTWAL CROSS SECTION | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 317.9 | 03/2021 | 10/2021 | 05/2024 | 31 |
25. | BELAKERI PORT TO KUMTA - SIRSI ROAD FROM KM 0.00 - KM 4.265 OF BELEKERI PORT ROAD LINK RD. AND KM 4. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 440.16 | 03/2018 | 12/2022 | 06/2024 | 18 |
26. | UPGRADATION 2/4 LANE NH CONNECTIVITY UNDER SAGARMALA SCHEME SH 2 HAVERI YEKAMBI SH 69 YEKAMBI KUMTA | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 294.62 | 03/2022 | 03/2024 | 01/2025 | 10 |
27. | 4L OF CHANNARAYAPATNA BYPASS AND HASSAN BYPASS WITH STRUCTURES IN DEVIHALLI -HASSAN SECTION | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 688 | 09/2020 | 01/2023 | 03/2025 | 26 |
28. | CONSTRUCTION OF 4 LANE BANGALORE -CHENNAI EXPRESSWAY FROM KM 53.500 TO KM 71.000 SECTION OF NE-7 (BA | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1069 | 01/2021 | 01/2024 | 04/2024 | 3 |
29. | FOUR LANING OF BANAVARA TO BETTADAHALLI SECTION FROM KM. 119+790 (DESIGN KM. 121+900) TO KM. 166+100 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1065.06 | 03/2021 | 03/2023 | 07/2024 | 16 |
30. | FOUR LANING OF BETTADAHALLI TO SRIRAMPURA SECTION FROM KM. 166+100 (DESIGN KM. 170+415) TO KM. 217+0 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1331.77 | 10/2021 | 10/2023 | 10/2024 | 12 |
31. | CONSTRUCTION OF 4 LANE BANGALORE-CHENNAI EXPRESSWAY FROM KM 0.000 TO KM 26.400 NE-7(ALONG WITH 0.700 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 3184 | 10/2020 | 09/2023 | 06/2024 | 9 |
32. | CONSTRUCTION OF 4 LANE BANGALORE - CHENNAI EXPRESSWAY FROM KM 26.400 TO KM 53.500 SECTION OF NE-7 (M | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1745 | 12/2020 | 09/2023 | 06/2024 | 9 |
33. | CHALLAKERE TO HARIYUR SECTION FROM KM 358.500 TO KM 414.205 OF NH150 A | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1167.52 | 01/2021 | 01/2023 | 04/2024 | 15 |
34. | FOUR LANING OF KARADI TO BANAVARA SECTION FROM KM. 66+540 (DESIGN KM. 65+195) TO KM. 119+790 (DESIGN | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1225.24 | 10/2019 | 10/2021 | 07/2024 | 33 |
35. | BALANCE WORK OF CONTSRUCTION OF TWO/FOUR LANE WITH PAVED SHOULDER FROM KM. 54.370 TO KM. 101.400 (BI | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 344.79 | 03/2021 | 03/2023 | 05/2024 | 14 |
36. | BALANCE WORK OF REHABILITATION AND UPGRADING TO 2LANE/2LANE WITH PAVED SHOULDER CONFIGURATION AND ST | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 398.48 | 02/2023 | 02/2024 | 02/2025 | 12 |
37. | WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM. 33.13 TO KM. 40.23 AND KM. 52.00 TO KM. 71.00 (EX | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 172.98 | 09/2022 | 03/2024 | 11/2024 | 8 |
38. | WIDENING TO INTERMEDIATE/TWO LANE TO 2 LANE WITH PAVED SHOULDER FROM EXISTING CHANAGES KM 112.750 TO | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 255.88 | 01/2023 | 06/2024 | 07/2024 | 1 |
39. | WIDENING TO 2 LANE WITH PAVED SHOULDERS FROM KM 116.800 TO 149.070(DESIGN CHANGES) ON HOSADURGA HOL | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 170.34 | 08/2022 | 02/2024 | 04/2024 | 2 |
40. | 4/6L OF BANGALORE - PUNE SECTION OF BYPASS CONNECTING DHARWAD - HUBLI FROM KM. 403.80 TO KM. 433.20 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1135.39 | 05/2022 | 03/2023 | 09/2025 | 30 |
41. | CONSTRUCTION OF TWO LANE WITH PAVED SHOULDER FROM KM.0 TO KM. 80 ON NH 548B (VIJAYAPURA-SANKESWAR SE | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 766.64 | 03/2021 | 02/2022 | 10/2024 | 32 |
42. | BANGALORE METRO RAIL PROJECT PHASE-2 | BANGALORE METRO RAIL CORPORATION LIMITED | URBAN DEVELOPMENT | 26405.14 | 02/2014 | 02/2021 | 03/2025 | 49 |
| Total | 42 | |