S No. | Agency Name | Sector Name | Project Name | Date Of Approval | Cost Original | Cost Anticipated | Expenditure |
1. | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | HUBBALI AIRPORT - CONSTRUCTION OF NEW DOMESTIC TERMINAL BUILDING AND MISCELLANEOUS WORKS | 6/2023 | 320.47 | 320.47 | 1.73 |
2. | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | BELAGAVI AIRPORT- EXPANSION OF TERMINAL BUILDING AND ASSOCIATED WORKS | 6/2023 | 322.45 | 322.45 | 12.03 |
3. | BANGALORE METRO RAIL CORPORATION LIMITED | URBAN DEVELOPMENT | BANGALORE METRO RAIL PROJECT LIMITED. PHASE. 2A AND 2B | 6/2021 | 14788.1 | 14788.1 | 2424.04 |
4. | BANGALORE METRO RAIL CORPORATION LIMITED | URBAN DEVELOPMENT | BANGALORE METRO RAIL PROJECT PHASE-2 | 2/2014 | 26405.14 | 26405.14 | 26717.53 |
5. | CENTRAL PUBLIC WORKS DEPARTMENT | DEPARTMENT OF HIGHER EDUCATION | ADDITIONAL INFRASTRUCTURE AT IISC BANGALORE SH RCC MONOLITHIC FOR MEN WOMEN HOSTEL | 8/2021 | 316.25 | 316.25 | 281.32 |
6. | CPWD FOR DEFENCE | DEFENCE PRODUCTION | RESIDENTIAL QUATERS FOR HAL,BANGLORE | 12/2016 | 246.31 | 195 | 187.12 |
7. | CPWD OF HIGHER EDUCATION | DEPARTMENT OF HIGHER EDUCATION | CONSTRUCTION OF PERMANENT CAMPUS FOR INDIAN INSTITUTE OF TECHNOLOGY, DHARWAD (PHASE 1A) | 7/2019 | 851 | 851 | 882.53 |
8. | HINDUSTAN PETROLEUM CORPORATION LIMITED | PETROLEUM | CONSTRUCTION OF 80000MT LPG CAVERN AT MANGALORE | 12/2018 | 854 | 854 | 524.99 |
9. | INDIAN OIL CORPORATION LIMITED | PETROLEUM | REVAMPING, AUGMENTATION OF FACILITIES AT EXISTING PORT TERMINAL AT MANGALORE | 1/2022 | 463 | 463 | 141.37 |
10. | MANGALORE REFINERY AND PETROCHEMICALS LIMITED | PETROLEUM | POWER SYSTEM UPGRADATION PROJECT | 10/2023 | 385 | 385 | 34.65 |
11. | MANGALORE REFINERY AND PETROCHEMICALS LIMITED | PETROLEUM | DEVANGONTHI MARKETING TERMINAL | 6/2020 | 200 | 304 | 242.95 |
12. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM 24.600 TO 70.063 OF MUDIGERE TO KADUR SECTION OF NH- | 12/2017 | 297.3 | 318.28 | 298.72 |
13. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO INTERMEDIATE/TWO LANE TO 2 LANE WITH PAVED SHOULDER FROM EXISTING CHANAGES KM 112.750 TO | 1/2023 | 255.88 | 255.88 | 60.99 |
14. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO 2 LANE WITH PAVED SHOULDERS FROM KM 0 TO 54 OF NH-50 UNDER EPC MODE IN THE STATE OF KARN | 10/2016 | 396.96 | 396.96 | 332.58 |
15. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TWO LANE WITH PAVED SHOULDERS FROM FROM KM.56.00 TO 106.00 OF NH-218 (218-KNT-2014-15-775) | 3/2015 | 159.12 | 159.12 | 131.48 |
16. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO 4 LANE FROM KM. 133.00 TO 158.04 (DESIGN CHAINAGE KM. 130.88 TO 155.145) (SHIRUR CROSS T | 1/2023 | 350.69 | 350.69 | 39.89 |
17. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT AND RECONSTRUCTION TO TWO LANE WITH PAVED SHOULDERS FROM KM 489.845 (NEW KM.58.125) AN | 3/2018 | 325.86 | 386.41 | 368.41 |
18. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO TWO LANE WITH PAVED SHOULDER FROM KM 544.200 TO KM 594.000 OF NH-150A HOSMANE CROSS – PA | 1/2017 | 166.67 | 264.34 | 221.31 |
19. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM 20.150 TO KM 40.00 OF BC ROAD KOTTIGEHARA SECTION | 1/2018 | 159.7 | 159.7 | 156.62 |
20. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENTS AND RECONSTRUCTION TO TWO LANE WITH PAVED SHOULDERS FROM KM 243.20 TO KM 290.20 OF NH | 8/2016 | 175.5 | 241.6 | 185.78 |
21. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF ELEVATED CORRIDOR FROM KM. 135.650 TO 136.300 ON 63, FROM KM. 249 TO KM. 250.050 ON | 6/2021 | 298 | 298 | 7.32 |
22. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF MAJOR BRIDGE ACROSS SHARAVATHI BACKWATERS AND APPROCHES BETWEEN AMBARGODU AND KALASA | 3/2019 | 423.15 | 423.15 | 356.51 |
23. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO 4 LANE FROM KM 51.60 TO 76.20 (HEBRI TO PARKALA) AND FROM KM 85.20 TO 88.90 (KARAVALI JU | 10/2022 | 355.72 | 355.72 | 23.29 |
24. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO 2 LANE WITH PAVED SHOULDERS FROM KM 116.800 TO 149.070(DESIGN CHANGES) ON HOSADURGA HOL | 8/2022 | 170.34 | 170.34 | 29.26 |
25. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | BALANCE WORK OF REHABILITATION AND UPGRADING TO 2LANE/2LANE WITH PAVED SHOULDER CONFIGURATION AND ST | 2/2023 | 398.48 | 398.48 | 7.8 |
26. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM 40.00 TO KM 75.00 (EXISTING CHAINAGES) OF MANGALOR | 3/2023 | 718.52 | 718.52 | 75.88 |
27. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | RECONSTRUCTION TO TWO LANE WITH PAVED SHOULDERS FROM DS. CH. 442+180 (EX. KM 448.00) TO DS. CH.485+2 | 3/2018 | 159.97 | 242.61 | 173.43 |
28. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO 2 LANE WITH PAVED SHOULDERS FROM KM 34.00 TO 70.900 OF NH-150 UNDER EPC MODE IN THE STAT | 11/2016 | 314.9 | 314.9 | 241.94 |
29. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO TWO LANE WITH PAVED SHOULDER FROM KM 194.900 TO KM 243.200 OF NH-234 BANAVARA-HULIYAR | 9/2017 | 191.6 | 191.6 | 115.52 |
30. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | STRENGTHENING AND WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM.106.00 TO 153.00 OF NH-218 BIJAP | 3/2015 | 165.67 | 165.67 | 127.3 |
31. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | BALANCE WORK OF CONSTRUCTION OF TWO/FOUR LANE WITH PAVED SHOULDER FROM KM 422.000 TO 523.600 ( CHITR | 12/2021 | 516.96 | 516.96 | 119.17 |
32. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO TWO LANE WITH PAVED SHOULDER FROM KM 4.40 TO KM 56.00 OF NH-218 BIJAPURA-HUBLI SECTION U | 1/2017 | 291.49 | 291.49 | 249.75 |
33. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF MAJOR BRIDGE AT KM 180.865 ACROSS RIVER KRISHNA ON NH-167 HAGARI – JADERCELA SECTION | 2/2017 | 157.32 | 187.61 | 48.73 |
34. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | BALANCE WORK OF CONTSRUCTION OF TWO/FOUR LANE WITH PAVED SHOULDER FROM KM. 54.370 TO KM. 101.400 (BI | 3/2021 | 344.79 | 344.79 | 1.8 |
35. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO EXISTING 2 LANE WITH PAVED SHOULDER TO 4 LANE WITH PAVED SHOULDER FROM DESIGN KM 153.00 | 2/2023 | 177.94 | 177.94 | 17.15 |
36. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO 2 LANE WITH PAVED SHOULDERS FROM DESIGN KM 103.200 (EXISTING KM 103.200) TO DESIGN KM 11 | 1/2023 | 166.58 | 166.58 | .49 |
37. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM. 33.13 TO KM. 40.23 AND KM. 52.00 TO KM. 71.00 (EX | 9/2022 | 172.98 | 172.98 | 31.8 |
38. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO 2-LANE WIH PAVED SHOULDER FROM KM. 544.20 TO 594.00 (HOSAMANE CROSS TO PANDAVAPURA) SECT | 1/2017 | 264.34 | 264.34 | 201.07 |
39. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF TWO LANE WITH PAVED SHOULDER FROM KM.0 TO KM. 80 ON NH 548B (VIJAYAPURA-SANKESWAR SE | 3/2021 | 766.64 | 766.64 | 109.21 |
40. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO 2 LANES WITH PAVED SHOULDERS FROM KM 24.400 TO 27.270, 40.500 TO 41.900, 84.300 TO 88.20 | 11/2022 | 218.93 | 218.93 | 50.97 |
41. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | ESTIMATE FOR WIDENING TWO LANE TO FOUR LANE FROM FROM KM.129.00 TO 144.00 OF NH-63 ANKOLA-GOOTY SECT | 5/2018 | 171.6 | 171.6 | 169.49 |
42. | NATIONAL CAPITAL REGION TRANSPORT CORP | RAILWAYS | YESHVANTHPUR-CHANNASANDRA (21.7 KM) | 4/2019 | 169.65 | 169.65 | 115.82 |
43. | NATIONAL CAPITAL REGION TRANSPORT CORP | RAILWAYS | BAIYYAPPANAHALLI-HOSUR (48 KM) | 4/2019 | 375.67 | 375.67 | 0 |
44. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | TWO/FOUR LANNING OF BRT TIGER RESERVE BOUNDARY TO BANGALORE SECTION OF NH-209(EXISTING CHAINAGE FROM | 9/2016 | 950.69 | 1108 | 1881.19 |
45. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4-LANNING EXISTING KM 189.700 TO 237.00] HASSAN TO MARANAHALLY | 3/2016 | 701.4 | 701.4 | 381.83 |
46. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4/6L OF BANGALORE - PUNE SECTION OF BYPASS CONNECTING DHARWAD - HUBLI FROM KM. 403.80 TO KM. 433.20 | 5/2022 | 1135.39 | 1135.39 | 204.44 |
47. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4L OF SANNUR TO BIKARNAKATTE SECTION FROM KARKALA TO MANGALORE | 3/2021 | 1409.68 | 1409.68 | 675.29 |
48. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | FOUR LANING OF LEFT OVER WORKS OF HOSPET BELLARY KARNATAKA/ AP BORDER FROM KM.280.080 TO KM. 375.450 | 3/2023 | 830.28 | 830.28 | 268.42 |
49. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4-LANING OF GOA/KARNATAKA BORDER-KUNDAPUR SECTION | 5/2014 | 1655.01 | 2639 | 1793.67 |
50. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L OF MH/KN BORDER (NIMBAL VILLAGE) TO KN/TS BORDER (SINGNODI VILLAGE) FROM KM. 162.5 TO KM. 203.100 | 11/2022 | 1732.73 | 1732.73 | 508.9 |
51. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF 4 LANE BANGALORE-CHENNAI EXPRESSWAY FROM KM 0.000 TO KM 26.400 NE-7(ALONG WITH 0.700 | 10/2020 | 3184 | 2867.98 | 1105.12 |
52. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | BANGALORE/TN BORDER TO HOSKOTE | 2/2023 | 1240.6 | 1240.6 | 510.53 |
53. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4L OF CHANNARAYAPATNA BYPASS AND HASSAN BYPASS WITH STRUCTURES IN DEVIHALLI -HASSAN SECTION | 9/2020 | 688 | 688 | 462.11 |
54. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | FOUR LANING OF KARADI TO BANAVARA SECTION FROM KM. 66+540 (DESIGN KM. 65+195) TO KM. 119+790 (DESIGN | 10/2019 | 1225.24 | 1505.85 | 58.52 |
55. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | BALANCE WORK OF 2L PS FROM KM 30.800 TO 70.800 AND 2L WITH RIGID CARRIAGEWAY FROM 70.800 TO KM 84.12 | 11/2022 | 226.76 | 226.76 | 55.77 |
56. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | DEVELOPMENT OF 6 LANE ACCESS CONTROLLED GREENFIELD HIGHWAY FROM KM. 97.000 TO KM. 162.500 MARADGI S | 12/2022 | 1589 | 1589 | 305.29 |
57. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L FROM SANKESHWAR BYPASS TO MH KNT BORDER FROM KM. 555.017 TO KM. 592.853 OF NH-48 (PKG II) | 1/2022 | 1388.7 | 1388.7 | 231.08 |
58. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L OF MH/KN BORDER (NIMBAL VILLAGE) TO KN/TS BORDER (SINGNODI VILLAGE) FROM KM. 26.000 TO KM. 97.000 | 12/2022 | 2718.46 | 2718.46 | 159.7 |
59. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | UPGRADATION 2/4 LANE NH CONNECTIVITY UNDER SAGARMALA SCHEME SH 2 HAVERI YEKAMBI SH 69 YEKAMBI KUMTA | 3/2022 | 294.62 | 294.62 | 23.45 |
60. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | BELAKERI PORT TO KUMTA - SIRSI ROAD FROM KM 0.00 - KM 4.265 OF BELEKERI PORT ROAD LINK RD. AND KM 4. | 3/2018 | 440.16 | 440.16 | 278.02 |
61. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L FROM BELGAUM TO SANKESHWAR BYPASS FROM KM 515.000 TO KM 555.017 OF NH 48 | 10/2022 | 1479.3 | 1479.3 | 320.43 |
62. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4L OF ADDAHOLE TO BANTWAL CROSS SECTION | 3/2021 | 317.9 | 317.9 | 303.74 |
63. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | FOUR LANING OF BANAVARA TO BETTADAHALLI SECTION FROM KM. 119+790 (DESIGN KM. 121+900) TO KM. 166+100 | 3/2021 | 1065.06 | 1444.5 | 131.89 |
64. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF 4 LANE BANGALORE -CHENNAI EXPRESSWAY FROM KM 53.500 TO KM 71.000 SECTION OF NE-7 (BA | 1/2021 | 1069 | 1061.33 | 768.18 |
65. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | FOUR LANING OF BETTADAHALLI TO SRIRAMPURA SECTION FROM KM. 166+100 (DESIGN KM. 170+415) TO KM. 217+0 | 10/2021 | 1331.77 | 2082.98 | 239.65 |
66. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | HOSPET-BELLARY-KARNATAKA AP BORDER | 8/2016 | 1167.42 | 1224.01 | 662.05 |
67. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4L OF ADDAHOLE TO BANTWAL CROSS SECTION INCLUDING FLYOVER AT KALLADKA TOWN | 3/2021 | 1100.88 | 1100.88 | 857.14 |
68. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CHALLAKERE TO HARIYUR SECTION FROM KM 358.500 TO KM 414.205 OF NH150 A | 1/2021 | 1167.52 | 1167.52 | 931.32 |
69. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | TUMKUR - NELAMANGALA(6L) | 8/2022 | 2032.15 | 2032.15 | 137.53 |
70. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF 4 LANE BANGALORE - CHENNAI EXPRESSWAY FROM KM 26.400 TO KM 53.500 SECTION OF NE-7 (M | 12/2020 | 1745 | 1594.09 | 1216.76 |
71. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | AURAD - BIDAR KM 0.00 TO KM 45.878 | 9/2021 | 912.37 | 424.16 | 326.36 |
72. | RAIL VIKAS NIGAM LTD. | RAILWAYS | HOSPET-HUBLI-LONDA-VASCODAGAMA DL | 4/2010 | 2127 | 3692.6 | 3399.77 |
73. | SOUTH WESTERN RAILWAY | RAILWAYS | WHITEFIELD-KOLAR (52.9 KM) | 2/2011 | 162.13 | 348.85 | .36 |
74. | SOUTH WESTERN RAILWAY | RAILWAYS | SHIMOGA-SHIKARIPURA-RANEBENNUR (UMBRELLA WORK PB#23/2018-19/NR) | 9/2019 | 1453.73 | 994.47 | 43.34 |
75. | SOUTH WESTERN RAILWAY | RAILWAYS | TUMKUR-CHITRADURGA-DAVENGERE NL | 4/2011 | 1801.01 | 1801.01 | 211.46 |
76. | SOUTH WESTERN RAILWAY | RAILWAYS | HASSAN (ALUR) - BELUR (32 KM) (UMBRELLA WORK PB#23/2018-19/NR) | 6/2019 | 663.03 | 748.85 | .34 |
77. | SOUTH WESTERN RAILWAY | RAILWAYS | SHIMOGA-HARIHAR NL | 4/2011 | 832.47 | 832.47 | .94 |
78. | SOUTH WESTERN RAILWAY | RAILWAYS | GADAG-WADI NL | 4/2013 | 2841.84 | 2841.84 | 984.14 |
79. | SOUTH WESTERN RAILWAY | RAILWAYS | KADUR CHIKMAGALUR SAKLESHPUR NEW LINE (93 KM) | 3/1996 | 644.78 | 825.31 | 522.59 |
80. | SOUTH WESTERN RAILWAY | RAILWAYS | MARIKUPPAM - KUPPAM | 4/2012 | 279.54 | 279.54 | 75.43 |
81. | SOUTH WESTERN RAILWAY | RAILWAYS | BAGALKOT-KUDACHI NL | 4/2010 | 986.3 | 1649.31 | 458.12 |
82. | SOUTH WESTERN RAILWAY | RAILWAYS | BELGAUM-DHARWAD VIA KITTUR (73.10 KM) (UMBRELLA WORK PB#22/2019-20/NR) | 9/2020 | 1590.8 | 927.42 | .06 |
83. | SOUTH WESTERN RAILWAY | RAILWAYS | BANGALORE-WHITEFIELD-BANGALORE CITY-KRISHNARAJAPURAM QUADRUPLING | 3/2018 | 492.87 | 492.87 | 9.41 |
| Total | 83 | |