S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | CONSTRUCTION AND DEVELOPMENT OF NATINAL INSTITUTE OF TECHNOLOGY MEGHALAYA PERMANENT CAMPUS AT SOHRA | RITES OF HIGHER EDUCATION | DEPARTMENT OF HIGHER EDUCATION | 484.32 | 09/2013 | 09/2014 | 07/2024 | 118 |
2. | WIDENING TO 2-LANE WITH GEOMETRIC IMPROVEMENTS OF TURA DALU ROAD UNDER JICA FUNDING FROM KM 85.000 T | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 553.51 | 04/2017 | 09/2021 | 12/2024 | 39 |
3. | IMPROVEMENT/WIDENING TO 2-L WITH PAVED SHOULDER FROM (DESIGN KM 0.00 TO KM 10.670) / 4-LANING FROM ( | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 351.12 | 11/2020 | 12/2023 | 10/2025 | 22 |
4. | IMPROVEMENT/WIDENING TO 2-LANE WITH PAVED SHOULDER FROM (DESIGN KM 10.670 TO KM 37.550) BETWEEN SHIL | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 525.68 | 11/2020 | 12/2023 | 08/2026 | 32 |
5. | RANIKOR-MAHESHKHOLA- BAGHMARA (RMB) PKG-4 (KANAI-RONGARA) | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 157.86 | 10/2020 | 04/2022 | 06/2024 | 26 |
6. | RANIKOR-MAHESHKHOLA- BAGHMARA (RMB) PKG-3 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 260.21 | 03/2021 | 12/2022 | 06/2024 | 18 |
7. | REHABILITATION AND UPGRADATION OF NONGSTOIN TO WAHKAJI SECTION OF PROJECT ROAD KM 0.000 TO KM 43.06 | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 302.88 | 08/2020 | 02/2022 | 07/2024 | 29 |
| Total | 7 | |