S No. | Agency Name | Sector Name | Project Name | Date Of Approval | Cost Original | Cost Anticipated | Expenditure |
1. | HSCL FOR DONER | DONER | CONSTRUCTION OF INTERNATIONAL CENTRE FOR PERFORMING ARTS AND CULTURE,SHILONG IN MEGALAYA UNDER NLCPR | 4/2014 | 151.33 | 151.33 | 148.33 |
2. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | REHABILITATION AND UPGRADATION OF NONGSTOIN TO WAHKAJI SECTION OF PROJECT ROAD KM 0.000 TO KM 43.06 | 8/2020 | 302.88 | 302.88 | 140.2 |
3. | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT/WIDENING TO 2-L WITH PAVED SHOULDER FROM (DESIGN KM 0.00 TO KM 10.670) / 4-LANING FROM ( | 11/2020 | 351.12 | 351.12 | 191.26 |
4. | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT/WIDENING TO 2-LANE WITH PAVED SHOULDER FROM (DESIGN KM 45.760 TO KM 63.530) BETWEEN SHIL | 11/2020 | 445.51 | 445.51 | 191.35 |
5. | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | REHABITITATION AND UP GRADATION OF NONGSTOIN-RAMBRAI-KYRSHAI ROAD UP TO MEGHALAYA-ASSAM BORDER FROM | 9/2021 | 359.86 | 359.86 | 204.47 |
6. | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT/WIDENING TO 2-LANE WITH PAVED SHOULDER FROM (DESIGN KM 10.670 TO KM 37.550) BETWEEN SHIL | 11/2020 | 525.68 | 525.68 | 358.61 |
7. | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | RANIKOR-MAHESHKHOLA- BAGHMARA (RMB) PKG-3 | 3/2021 | 260.21 | 260.21 | 163.71 |
8. | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO 2-LANE WITH GEOMETRIC IMPROVEMENTS OF TURA DALU ROAD UNDER JICA FUNDING FROM KM 85.000 T | 4/2017 | 553.51 | 553.51 | 314.01 |
9. | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | RANIKOR-MAHESHKHOLA- BAGHMARA (RMB) PKG-4 (KANAI-RONGARA) | 10/2020 | 157.86 | 157.86 | 129.42 |
10. | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | RANIKOR- MAHESHKHOLA- BAGHMARA PKG-2 | 11/2021 | 283.5 | 283.5 | 129.57 |
11. | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT/WIDENING TO 2-LANE WITH PAVED SHOULDER / 4-LANING FROM (DESIGN KM 63.530 TO KM 71.520) B | 11/2020 | 284.21 | 284.21 | 45.46 |
12. | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT/WIDENING TO 2-LANE WITH EARTHEN SHOULDERS FROM RANIKOR TO NONGJRI EXISTING CHAINAGE FROM | 3/2019 | 306.28 | 306.28 | 204.58 |
13. | NORTH EAST FRONTIER RAILWAY | RAILWAYS | NEW BG LINE FROM BYRNIHAT TO SHILLONG | 4/2010 | 906.46 | 8324.28 | 269.8 |
14. | RITES OF HIGHER EDUCATION | DEPARTMENT OF HIGHER EDUCATION | CONSTRUCTION AND DEVELOPMENT OF NATINAL INSTITUTE OF TECHNOLOGY MEGHALAYA PERMANENT CAMPUS AT SOHRA | 9/2013 | 484.32 | 429.7 | 266.05 |
| Total | 14 | |