S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | GHONSA EXPANSION DEEP OC | WESTERN COAL FIELDS LIMITED | COAL | 184.71 | 03/2021 | 03/2028 | 03/2029 | 12 |
2. | LIFE EXTENSION OF WALL PLATFORMS OF MUMBAI HIGH AND HEERA FIELDS | OIL & NATURAL GAS CORPORATION LIMITED | PETROLEUM | 3190.69 | 12/2015 | 04/2018 | 06/2025 | 86 |
3. | SETTING UP 500KTPA PROPANE DEHYDROGENATION INTEGRATED WITH POLYPROPYLENE UNIT ALONG WITH OFFSITE AND | GAS AUTHORITY OF INDIA LIMITED | PETROLEUM | 8797 | 05/2019 | 04/2025 | 10/2025 | 6 |
4. | EXPANSION OF CRYOGENICS GROUP BY SETTING UP NEW MANUFACTURING FACILITY | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 378 | 09/2021 | 10/2023 | 06/2025 | 20 |
5. | ATF PIPELINE FROM JAWAHARLAL NEHRU PORT TRUST (JNPT) TO NAVI MUMBAI INTERNATIONAL AIRPORT (NMIA) | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 165 | 09/2022 | 08/2025 | 03/2026 | 7 |
6. | DAMAN UPSIDE DEVELOPMENT PROJECT (DUDP) IN TAPTI DAMAN BLOCK | OIL & NATURAL GAS CORPORATION LIMITED | PETROLEUM | 4144.41 | 06/2022 | 10/2025 | 02/2026 | 4 |
7. | CGD PROJECT AT BEED, JALGAON AND JALNA DISTRICTS | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 865 | 03/2022 | 03/2030 | 09/2031 | 18 |
8. | ANDHERI RESIDENTIAL TOWERS MUMBAI | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 281.35 | 06/2017 | 05/2025 | 06/2026 | 13 |
9. | CONSTRUCTION OF ADDITIONAL TANKAGES AND ALLIED FACILITIES AT JNPT TERMINAL | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 341.43 | 04/2022 | 10/2024 | 08/2026 | 22 |
10. | PART REPLACEMENT PIPELINE PROJECT (PRPP) | OIL & NATURAL GAS CORPORATION LIMITED | PETROLEUM | 1219.48 | 11/2022 | 05/2024 | 11/2025 | 18 |
11. | BIKANER SOLAR POWER PROJECT | SATLUJ JAL VIDYUT NIGAM LIMITED | POWER | 5491.89 | 04/2022 | 05/2024 | 09/2025 | 16 |
12. | TS FOR EVACUATION OF 7GW RE INJECTION AT KHAVDA PS UNDER PHASE-IV PART E4 | POWER GRID CORPORATION OF INDIA LIMITED | POWER | 224 | 11/2023 | 07/2025 | 09/2025 | 2 |
13. | KALYAN-KASARA 3RD LINE | CENTRAL RAILWAYS | RAILWAYS | 792.89 | 04/2011 | 12/2025 | 12/2026 | 12 |
14. | WARDHA-SEWAGRAM NGP 3RD LINE | CENTRAL RAILWAYS | RAILWAYS | 540.02 | 04/2012 | 12/2025 | 02/2026 | 2 |
15. | WARDHA-BALHARSHAH - 3RD LINE (132 KM) | CENTRAL RAILWAYS | RAILWAYS | 1384.72 | 02/2015 | 12/2025 | 03/2026 | 3 |
16. | PUNE-MIRAJ-LONDA (467 KM) | CENTRAL RAILWAYS | RAILWAYS | 3627.47 | 02/2015 | 02/2025 | 05/2025 | 3 |
17. | DAUND - MANMAD (236 KM) | CENTRAL RAILWAYS | RAILWAYS | 2081.27 | 02/2016 | 12/2025 | 01/2026 | 1 |
18. | MANMAD - JALGAON - 3RD LINE (160 KM) | CENTRAL RAILWAYS | RAILWAYS | 1035.16 | 02/2016 | 12/2024 | 03/2026 | 15 |
19. | WARDHA - NAGPUR - 4TH LINE (76 KM) | CENTRAL RAILWAYS | RAILWAYS | 638 | 02/2016 | 12/2025 | 02/2026 | 2 |
20. | RAJNANDGAON - NAGPUR - 3RD LINE (SECR) | SOUTH EAST CENTRAL RAILWAY | RAILWAYS | 3544.92 | 09/2016 | 12/2024 | 12/2026 | 24 |
21. | PACHORA-JAMNER WITH EXTENSION UPTO MALKAPUR NG TO BG | CENTRAL RAILWAYS | RAILWAYS | 955 | 08/2022 | 08/2027 | 03/2029 | 19 |
22. | DHULE (BORVIHIR)-NARDANA (UMBRELLA WORK) | CENTRAL RAILWAYS | RAILWAYS | 492.76 | 01/2019 | 12/2026 | 03/2028 | 15 |
23. | NAGPUR- NAGBHIR RAILWAY LINE GAUGE CONVERSION PROJECT | Maharashtra Rail Infrastructure Development Corporation Limited | RAILWAYS | 1400 | 10/2019 | 06/2024 | 10/2025 | 16 |
24. | CONSTRUCTION OF FLYOVER AT KM.544.650 INCLUDING ROB ,SERVICE ROADS ,FOOTPATH FOR RCC DRAINS ON URBAN | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 649.5 | 12/2015 | 03/2019 | 07/2025 | 76 |
25. | NAGPUR RING ROAD PACKAGE-2 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 591.66 | 03/2016 | 07/2019 | 05/2025 | 70 |
26. | 4-LANNING OF BODHRE-DHULE SECTION(KM 390.000 TO 452.800) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 744.64 | 03/2017 | 03/2020 | 12/2025 | 69 |
27. | 4-LANNING OF WARANGA-MAHAGAON SECTION(KM 253.7000 TO 320.580) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1059.73 | 03/2017 | 03/2017 | 05/2025 | 98 |
28. | CONSTRUCTION OF 8 LANING OF EXISTING 4 LANE VADAPE TO THANE FROM KM 539.202 TO KM 563.000 SECTION OF | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1162.92 | 03/2018 | 07/2021 | 12/2025 | 53 |
29. | TUNNEL AT KHAMBATAKI GHAT SECTION AND ITS APPROACHES FROM EXISTING KM. 771.730 TO EXISTING KM. 782.0 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 493 | 02/2019 | 02/2022 | 08/2025 | 42 |
30. | DHARAMPURI-LONAND FROM KM. 117.00 TO 166.40 (PKG-IV) ON MOHOL-ALANDI SECTION | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 618.45 | 09/2021 | 09/2023 | 05/2025 | 20 |
31. | 6L OF KAGAL-SATARA SECTION FROM KM 658.000 TO KM 725.000 OF NH-48 (PKG-II) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1749.86 | 12/2022 | 12/2024 | 11/2025 | 11 |
32. | 4L OF RATNAGIRI - KOLHAPUR SECTION OF NH-166 FROM KM 0.000 TO KM 19.769 AND KM 31.000 TO KM 67.140 ( | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 930 | 11/2022 | 11/2024 | 09/2025 | 10 |
33. | 4L OF BARAMATI TO INDAPUR (PKG-II) FROM KM. 41.400 TO KM. 84.550 OF NH-965G (SAINT TUKARAM MARG) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 624.45 | 09/2021 | 09/2023 | 06/2025 | 21 |
34. | VADODARA MUMBAI EXPRESSWAY (PHASE II - PKG XI) [KM. 77.000 TO KM. 103.400] (GANJAD - TALSARI) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1260 | 05/2022 | 05/2024 | 06/2025 | 13 |
35. | VADODARA MUMBAI EXPRESSWAY (PHASE II - PKG XII) [KM. 50.700 TO KM. 77.000] (MASVAN - GANJAD) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1549.02 | 03/2022 | 03/2024 | 06/2025 | 15 |
36. | VADODARA MUMBAI EXPRESSWAY (PHASE II - PKG XIII) [KM. 26.582 TO KM. 50.700] (SHIRSAD - MASVAN) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2747 | 02/2022 | 02/2024 | 06/2025 | 16 |
37. | VADODARA MUMBAI EXPRESSWAY (PHASE II - PKG XIV) [KM. 3.000 TO KM. 20.200 OF SPUR] (SHIRSAD - AKLOLI) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1124 | 11/2022 | 05/2024 | 06/2025 | 13 |
38. | VADODARA MUMBAI EXPRESSWAY (PHASE II - PKG XVI) [KM. 43.000 TO KM. 69.800 OF SPUR] (AMNE - BHOJ) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1450 | 11/2022 | 10/2024 | 06/2025 | 8 |
39. | VADODARA MUMBAI EXPRESSWAY (PHASE II - PKG XV) [KM. 20.200 TO KM. 43.000 OF SPUR] (AKLOLI - AMNE) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 990 | 11/2022 | 10/2024 | 07/2025 | 9 |
40. | BALANCE WORKS OF 4L PANVEL-INDAPUR SECTION OF NH-66 (OLD NH-17) FROM KM 42.300 (KASU) TO KM 84.600 ( | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 332 | 10/2022 | 05/2024 | 12/2025 | 19 |
41. | BALANCE WORK OF 4 LANING OF PANVEL TO INDAPUR SECTION OF NH-66(OLD NH- 17) FROM KM 0.000 (PANVEL) TO | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 151.26 | 01/2023 | 12/2023 | 06/2025 | 18 |
42. | 4L OF EXISTING 2/4L STRETCH FROM LONAND TO DIVE GHAT (KM 166.400 TO KM 220.900 ) OF MOHOL – ALANDI S | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1833.73 | 01/2022 | 05/2024 | 05/2025 | 12 |
43. | 6L OF WAINGANGA BRIDGE - BHANDARA (INCLUDING BHANDARA BYPASS) SECTION FROM KM 485.000 TO KM 499.800 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 815.77 | 10/2021 | 01/2024 | 05/2025 | 16 |
44. | 4L MITIGATION MEASURE STRUCTURES ON CH/MH BORDER TO WAINGANGA BRIDGE SECTION OF NH-53 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 540.21 | 02/2021 | 11/2023 | 05/2025 | 18 |
45. | 4L OF NAGPUR-KATOL SECTION FROM KM. 13.00 TO KM. 62.900 OF NH-353J | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1166.96 | 02/2021 | 10/2023 | 10/2025 | 24 |
46. | BAL. WORKS OF FAGNE (KM. 510.000) TO MAHARASHTRA/GUJARAT BORDER (KM. 650.794) | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1654.07 | 12/2019 | 09/2022 | 12/2025 | 39 |
47. | MUMBAI METRO LINE 3 (COLABA-BANDRA-SEEPZ) | MUMBAI METRO RAIL CORPORATION LTD | URBAN DEVELOPMENT | 23136 | 07/2013 | 03/2020 | 07/2025 | 64 |
| Total | 47 | |