S No. | Sector | Agency | Date Of Approval | Cost Original | Cost Overrun |
1. | RAILWAYS | WESTERN RAILWAY | 04/2008 | 3503.69 | 2699.82 |
2. | RAILWAYS | WEST CENTRAL RAILWAY | 06/2016 | 2478.23 | 459.77 |
3. | RAILWAYS | WEST CENTRAL RAILWAY | 12/2015 | 1763.93 | 681.37 |
4. | RAILWAYS | WESTERN RAILWAY | 10/2021 | 910 | 185.88 |
5. | RAILWAYS | WEST CENTRAL RAILWAY | 08/2016 | 582.13 | 665.51 |
6. | RAILWAYS | SOUTH EAST CENTRAL RAILWAY | 04/2015 | 1370 | 941.02 |
7. | RAILWAYS | RAIL VIKAS NIGAM LTD. | 09/2018 | 4340 | 3053.75 |
8. | RAILWAYS | WEST CENTRAL RAILWAY | 04/2001 | 424.6 | 2607.86 |
9. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 12/2017 | 217.96 | 666.04 |
10. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 09/2021 | 774.16 | 118.92 |
11. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 11/2017 | 392.33 | 78.39 |
12. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 10/2019 | 743.88 | .01 |
13. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 09/2021 | 814.04 | 133.25 |
14. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 12/2017 | 656.98 | 183.02 |
| Total | 14 | |