S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | RAJASTHAN ATOMIC POWER PROJECT -7 AND 8 (2X700 MW) | NUCLEAR POWER CORPORATION OF INDIA LIMITED | ATOMIC ENERGY | 12320 | 10/2009 | 12/2016 | 12/2026 | 120 |
2. | NEW MUNDRA-PANIPAT CRUDE OIL PIPELINE | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 9028 | 12/2021 | 10/2024 | 12/2024 | 2 |
3. | RAJASTHAN REFINERY PROJECT | HPCL Rajasthan Refinery Limited(JV) | PETROLEUM | 43129 | 10/2017 | 10/2022 | 03/2025 | 29 |
4. | SAMBHU KI BHURJ-II SOLAR 300MW | NATIONAL THERMAL POWER CORPORATION | POWER | 1782 | 03/2020 | 09/2021 | 09/2024 | 36 |
5. | ANTA SOLAR 90 MW | NATIONAL THERMAL POWER CORPORATION | POWER | 382.22 | 01/2021 | 03/2022 | 03/2024 | 24 |
6. | BHENSARA 320 MW | NATIONAL THERMAL POWER CORPORATION | POWER | 1221.73 | 01/2021 | 07/2022 | 03/2024 | 20 |
7. | CHHATTARGARH 150 MW | NATIONAL THERMAL POWER CORPORATION | POWER | 599.99 | 02/2021 | 07/2022 | 03/2024 | 20 |
8. | TRANSMISSION SYSTEM STRENGTHENING SCHEME FOR EVACUATION OF POWER FROM SOLAR ENERGY ZONES IN RAJASTHA | POWER GRID CORPORATION OF INDIA LIMITED | POWER | 1184.88 | 05/2021 | 09/2022 | 05/2024 | 20 |
9. | TRANSMISSION SYSTEM STRENGTHENING SCHEME FOR EVACUATION OF POWER FROM SOLAR ENERGY ZONES IN RAJASTHA | POWER GRID CORPORATION OF INDIA LIMITED | POWER | 713.82 | 06/2021 | 12/2022 | 05/2024 | 17 |
10. | TRANSMISSION SYSTEM STRENGTHENING SCHEME FOR EVACUATION OF POWER FROM SOLAR ENERGY ZONES IN RAJASTHA | POWER GRID CORPORATION OF INDIA LIMITED | POWER | 1562 | 06/2021 | 12/2022 | 09/2024 | 21 |
11. | TRANSMISSION SYSTEM STRENGTHENING SCHEME FOR EVACUATION OF POWER FROM SOLAR ENERGY ZONES IN RAJASTHA | POWER GRID CORPORATION OF INDIA LIMITED | POWER | 1006 | 06/2021 | 12/2022 | 09/2024 | 21 |
12. | NOKH PLOT-1 SOLAR PV PROJECT 245MW | NATIONAL THERMAL POWER CORPORATION | POWER | 1352.71 | 03/2022 | 08/2023 | 09/2024 | 13 |
13. | NOKH PLOT-2 SOLAR PV PROJECT 245MW | NATIONAL THERMAL POWER CORPORATION | POWER | 1409.52 | 03/2022 | 08/2023 | 09/2024 | 13 |
14. | NOKH PLOT-3 SOLAR PV PROJECT 245MW | NATIONAL THERMAL POWER CORPORATION | POWER | 1426.94 | 03/2022 | 08/2023 | 09/2024 | 13 |
15. | BHADLA-II 500MW SOLAR PV PROJECT | NATIONAL THERMAL POWER CORPORATION | POWER | 2598.92 | 06/2022 | 03/2024 | 12/2024 | 9 |
16. | 300 MW SOLAR POWER PROJECT UNDER CPSU SCHEME | NATIONAL HYDRO-ELECTRIC POWER CORPORATION | POWER | 1677.12 | 05/2022 | 11/2023 | 12/2024 | 13 |
17. | UP-GRADATION TO TWO LANING WITH PAVED SHOULDER OF AJMER-NAGAUR SECTION BY EXECUTING BALANCE WORK FRO | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 255.23 | 03/2020 | 10/2022 | 07/2024 | 21 |
18. | REHABILATION AND UPGRADATION TO 2 LANE WITH PAVED SHPULDERS CONFIGURATION OF BEAWAR-ASIND SECTION (K | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 196.23 | 08/2020 | 11/2022 | 03/2024 | 16 |
19. | 4L+PS OF RAS-BEAWAR SECTION (KM 0.00 TO KM 30.00) OF NH-158 (GNHCP) WORLD BANK. PKG-I. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 319.09 | 07/2020 | 03/2024 | 09/2024 | 6 |
20. | 4L+PS OF BEAWAR-ASIND SECTION (KM 30.00 TO KM 74.00) OF NH-158 (GNHCP) WORLD BANK. PKG-II | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 216.72 | 08/2020 | 12/2022 | 03/2024 | 15 |
21. | 4L+PS OF NH -58 FROM BEAWAR-GOMTI (OLD CH KM 58.245 TO KM. 108.600) PKG-I. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 379.23 | 12/2020 | 10/2023 | 06/2024 | 8 |
22. | 4L+PS OF NH -58 FROM BEAWAR-GOMTI (OLD CH KM 108.600 TO KM 144 KM 158.419 TO KM 173.300 PKG-II. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 339.65 | 12/2020 | 10/2023 | 06/2024 | 8 |
23. | 2L+PS FROM KM 148/170 TO 211 /100 (DEVAL- DUNGARPUR-HIRATA - VARDA-SAGWARA) SECTION OF NH-927A. PKG- | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 240.99 | 02/2021 | 01/2024 | 05/2024 | 4 |
| Total | 23 | |