S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | TEESTA VI HE PROJECT | NATIONAL HYDRO-ELECTRIC POWER CORPORATION | POWER | 5748.04 | 03/2019 | 03/2024 | 12/2027 | 45 |
2. | RANGIT IV HE PROJECT | NATIONAL HYDRO-ELECTRIC POWER CORPORATION | POWER | 938.29 | 03/2021 | 05/2024 | 05/2025 | 12 |
3. | CONSTRUCTION OF 2-LANE WITH PAVED SHOULDER INCLUDING GEOMETRIC IMPROVEMENT FROM KM 16.000 TO KM 32.5 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 290.05 | 11/2017 | 10/2020 | 03/2024 | 41 |
4. | CONSTUCTION/UPGRADATION OF EXISTING HIGHWAY TO 2 LANE WITH PAVED SHOULDER FROM KM 13.00 TO KM 25.600 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 295.97 | 08/2020 | 04/2023 | 06/2024 | 14 |
5. | CONSTRUCTION AND UPGRADATION OFEXISTINGROAD TO 2-LANE WITH PAVED SHOULDER INCLUDING GEOMETRIC IMPROV | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 311 | 08/2020 | 04/2023 | 05/2024 | 13 |
6. | CONSTRUCTION AND UPGRADATION OFEXISTINGROAD TO 2-LANE WITH PAVED SHOULDER INCLUDING GEOMETRIC IMPROV | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 345.38 | 07/2020 | 04/2023 | 03/2024 | 11 |
7. | CONSTRUCTION OF 2-LANE ROAD WITH PAVED SHOULDER (GREENFIELD ALIGNMENT) OF EXISTING STRETCH BETWEEN L | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 183.31 | 09/2020 | 05/2022 | 06/2024 | 25 |
8. | CONSTRUCTION OF 2-LANE SPECIFICATION ROAD WITH PAVED SHOULDER AS REALIGNMENT (GREENFIELD ALIGNMENT) | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 262.84 | 09/2020 | 05/2023 | 01/2025 | 20 |
9. | REHABILITATION AND UPGRADATION OF EXISTING ROAD TO 2-LANE WITH PAVED SHOULDER INCLUDING GEOMETRIC IM | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 292.8 | 08/2020 | 05/2022 | 06/2024 | 25 |
10. | CONSTRUCTION AND UPGRADATION OF EXISTING ROAD TO 2-LANE WITH PAVED SHOULDER FROM KM27.200 (END OF RO | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 230.45 | 08/2020 | 04/2023 | 06/2024 | 14 |
11. | CONSTRUCTION AND UPGRADATION OF EXISTING ROAD TO 2-LANE WITH PAVED SHOULDER FROM NEW ROLEP BRIDGE AT | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 493.42 | 10/2020 | 11/2023 | 01/2025 | 14 |
12. | CONSTRUCTION OF 2-LANE WITH PAVED SHOULDER OF NEW GREEN FIELD ALIGNMENT FROM CHOCHENPHERI AT KM 52.0 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 816.79 | 10/2020 | 12/2023 | 09/2024 | 9 |
13. | RISHI BORDER- ROLEP- MENLA PKG- 2A | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 332.2 | 01/2021 | 09/2023 | 01/2025 | 16 |
14. | RISHI BORDER- ROLEP- MENLA PKG- 3B | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 410.6 | 12/2020 | 02/2024 | 04/2025 | 14 |
| Total | 14 | |