S No. | Sector Name | Agency Name | Project Name | Date Of Approval | Cost Original | Cost Anticipated | Expenditure |
1. | ATOMIC ENERGY | NUCLEAR POWER CORPORATION OF INDIA LIMITED | KUDANKULAM NUCLEAR POWER PROJECT 5 AND 6 | 6/2017 | 49621 | 49621 | 14354 |
2. | ATOMIC ENERGY | BHAVINI LIMITED | PROTOTYPE FAST BREEDER REACTOR (BHAVINI, 500 MWE) | 9/2003 | 3492 | 7670 | 6649.17 |
3. | ATOMIC ENERGY | NUCLEAR POWER CORPORATION OF INDIA LIMITED | KUDANKULAM NUCLEAR POWER PROJECT UNIT-3 and 4 | 3/2013 | 39849 | 39849 | 41541 |
4. | CIVIL AVIATION | AIRPORT AUTHORITY OF INDIA LIMITED | DEVELOPMENT OF TUTICORIN AIRPORT | 6/2019 | 380.87 | 442.21 | 230.85 |
5. | CIVIL AVIATION | AIRPORT AUTHORITY OF INDIA LIMITED | MODERNIZATION OF CHENNAI AIRPORT PHASE II, CHENNAI | 6/2018 | 2467 | 2467 | 1432.08 |
6. | CIVIL AVIATION | AIRPORT AUTHORITY OF INDIA LIMITED | UPGRADATION OF PASSENGER TERMINAL BUILDING AND AIRSIDE FACILITIES AT TIRUCHIRAPALLI INTERNATIONAL AI | 8/2018 | 951.28 | 951.28 | 1059.94 |
7. | COAL | SINGARENI COLLIERS COMPANY LIMITTED | JAWAHAR KHANI OPENCAST (JK OC) MINE | 12/2021 | 297.88 | 297.88 | 40.83 |
8. | FINANCE | CPWD FOR FINANCE | CONSTRUCTION OF 726 Nos RESIDENTIAL QUARTERS CHENNAI | 11/2017 | 348.77 | 348.77 | 304.11 |
9. | FINANCE | CPWD FOR FINANCE | C/O OF 152 NOS TYPE-II,304 NOS,TYPE-III,76 NOS, TYPE-IV QTRS. FOR INCOME TAX DEPARTMENT AT CHENNAI | 12/2015 | 209 | 262 | 252.2 |
10. | MINES | NATIONAL ALUMINUM COMPANY LIMITED (NALCO) | 25.5 MW WIND POWER PROJECT AT KAYATHAR IN TAMILNADU | 9/2017 | 166.62 | 163.17 | 135.63 |
11. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | GRASS ROOT POL TERMINAL AT VALLUR, CHENNAI | 1/2022 | 827 | 827 | 365.99 |
12. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | ENNORE THIRUVALLUR BENGALURU PUDUCHERRY NAGAPATTINAM MADURAITUTICORIN GAS PIPELINE | 5/2016 | 4497 | 6025 | 5425.61 |
13. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | SETTING UP LUBE COMPLEX AT VILLAGES AMULLAVOYAL AND VAIKKADU, CHENNAI AS RESITEMENT OF EXISTING FACI | 10/2020 | 1398 | 1587 | 982.42 |
14. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | CGD PROJECT AT SALEM DISTRICT | 10/2018 | 1304 | 1304 | 106.9 |
15. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | EXTENSION OF ASANUR-SANKARI SECTION OF CHENNAI-TRICHY-MADURAI PIPELINE UPTO COIMBATORE (IRUGUR) | 1/2023 | 346.7 | 346.7 | 1.51 |
16. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | CGD PROJECT AT KANYAKUMARI, TUTICORIN, TIRUNVELI KATTABO AND TENKASI DISTRICTS | 3/2022 | 1295 | 1295 | 76.37 |
17. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | CBR ASANUR PIPELINE AND ITS HOOK UP WITH EXISTING CHENNAI TRICHY MADURAI PRODUCT PIPELINE | 3/2022 | 564 | 564 | 132.08 |
18. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | CGD PROJECT AT COIMBATORE DISTRICT | 10/2018 | 2998 | 2998 | 315.18 |
19. | PETROLEUM | CHENNAI PETROLEUM CORPORATION LIMITED | CBR 9 MMTPA PROJECT | 1/2021 | 31580 | 31580 | 1078.7 |
20. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | CGD PROJECT AT DHARMAPURI AND KRISHNAGIRI DISTRICTS | 3/2022 | 501 | 501 | 54.43 |
21. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | CONSTRUCTION OF CAPTIVE POL LPG JETTY AT KAMARAJAR PORT, CHENNAI | 10/2020 | 921 | 921 | 543.5 |
22. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | LAYING OF POL PIPELINES IN COMMON CORRIDOR FOR PROPOSED GRASS ROOT TERMINAL AT VALLUR (CHENNAI) | 1/2022 | 829 | 829 | 135.8 |
23. | PETROLEUM | BHARAT PETROLEUM CORPORATION LIMITED | IRUGUR-DEVANGONTHI POL PIPELINE | 11/2012 | 678 | 1732 | 208.91 |
24. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | CGD PROJECT AT MADURAI, THENI AND VIRUDHNAGAR DISTRICTS | 3/2022 | 1328 | 1328 | 72.76 |
25. | POWER | POWER GRID CORPORATION OF INDIA LIMITED | TRANSMISSION SYSTEM FOR EVACUTION OF POWER FROM NEYVELI LIGNITE CORP LTD TS - I (REPLACEMENT) IN NEY | 5/2017 | 186.17 | 219.66 | 179.47 |
26. | RAILWAYS | METROPOLITAN RAPID TRANSPORT PROJECTS | EXTENSION OF MRTS FROM VELACHERY TO STN. THOMAS, MTP | 4/2006 | 495.74 | 734.01 | 618.47 |
27. | RAILWAYS | SOUTHERN RAILWAY | TIDIVANAM-NAGARI (NL) | 9/2006 | 582.83 | 3631.34 | 764.61 |
28. | RAILWAYS | RAIL VIKAS NIGAM LTD. | MANIYACHI - NAGERCOIL (102 KM) DOUBLING | 2/2015 | 1700 | 1752.25 | 1634.41 |
29. | RAILWAYS | SOUTHERN RAILWAY | MORAPPUR-DHARMAPURI | 2/2019 | 358.95 | 358.95 | 2.79 |
30. | RAILWAYS | SOUTHERN RAILWAY | CHENNAI BEACH-CHENNAI EGMORE (4.3 KM) (UMBRELLA WORK PB#57/2019-20/NR) | 3/2022 | 359.6 | 274.2 | 130.36 |
31. | RAILWAYS | SOUTHERN RAILWAY | KARAIKAL - PERALAM NEW LINE (MM OF TIRUCHCHIRAPPALLI-NAGORE-KARAIKAL) | 1/2019 | 304.22 | 373.42 | 192.41 |
32. | RAILWAYS | SOUTHERN RAILWAY | NAGAPATTINAM- THIRUTURAIPUNDI VIA THIRUKUVALAI NEW LINE (MM OF TIRUCHCHIRAPPALLI-NAGORE-KARAIKAL) | 7/2008 | 677.12 | 788.05 | 103.18 |
33. | RAILWAYS | SOUTHERN RAILWAY | MAYLADUTHURAI-THIRUVARUR-KARAIKUDI-THIRU 'PONDI'-AGASTIYAMPALLI | 9/2007 | 724.69 | 3118.34 | 1911.17 |
34. | RAILWAYS | SOUTHERN RAILWAY | Chinnasalem-Kallakurichi New Line (MM of cuddalore- Salem 191 KM)
| 1/2006 | 417.5 | 417.5 | 26.02 |
35. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANING OF NERALURU TO THORAPALLI AGRAHARAM SECTION OF NH-844 (PKG-I) FROM KM.0+000 TO KM.23+350 | 9/2021 | 1751.18 | 1757.27 | 49.69 |
36. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4-LANING OF VADIPPATTI - THAMARAIPATTI SECTION OF NH-744A (MADURAI RING ROAD) | 12/2018 | 854.94 | 854.94 | 284.57 |
37. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4L OF VADUGAPATTI TO THERKUVENGANALLUR (RAJAPALYAM) SECTION FROM KM 36.000 TO KM 71.600 OF NH744 UND | 2/2022 | 1097.59 | 1097.59 | 376.13 |
38. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4-LANING OF KAMALAPURAM - ODDANCHATRAM SECTION OF NH-209 | 1/2019 | 1051.69 | 1051.69 | 451.15 |
39. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4L OF LEFT-OVER WORKS INCLUDING ADDITIONAL STRUCTURES FROM KERALA/TAMIL NADU BORDER TO KANYAKUMARI S | 3/2023 | 1141.78 | 1141.78 | 55.29 |
40. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | REMAINING WORK OF 2L+PS OF TRICHY - KARAIKUDI SECTION OF NH-210, INCLUDING TRICHY BYPASS | 2/2019 | 166.9 | 166.9 | 121.94 |
41. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | BANGALORE CHENNAI EXPRESSWAY PHASE-III PACKAGE II (WALAJAHPET TO ARAKKONAM) FROM KM 180.000 TO KM 2 | 12/2020 | 843.48 | 984.61 | 290.74 |
42. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4L BANGALORE-CHENNAI EXPRESSWAY FROM KM. 230.000 TO KM. 261.705 OF KANCHEPURAM TO SRIPERUMBUDUR SECT | 2/2021 | 2948.31 | 3516.83 | 589.57 |
43. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANING OF MUGAIYUR TO MARAKKANAM SECTION OF NH-332A FROM KM 31.000 TO KM 62.000 | 2/2019 | 825.94 | 1116.13 | 26.61 |
44. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | THOPPUR METTUR BHAVANI ERODE SECTION OF NH 544H FOR A LENGTH OF 85 KM | 7/2022 | 186.5 | 210.81 | 12.92 |
45. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANING OF MAMALLAPURAM TO MUGAIYUR SECTION OF NH332A FROM KM 0.000 TO KM 31.000 | 2/2019 | 1008.99 | 1360.53 | 142.73 |
46. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF BYPASS TO GUDIYATHAM TOWN IN KM 23/100 – 29/250 INCLUDING LA AND SHIFTING OF NH-234 | 1/2022 | 221.03 | 243.95 | 88.57 |
47. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF NEW DOUBLE TIER 4L ELEVATED CORRIDOR FROM CHENNAI PORT TO MADURAVOYAL IN CHENNAI DIS | 3/2023 | 1618.96 | 1618.96 | 0 |
48. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | BALANCE WORK OF 2L PS OF TINDIVANAM KRISHNAGIRI FROM KM 37.600 TO 219.782 | 5/2019 | 602.57 | 548.89 | 371.99 |
49. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 6L OF SRIPERUMBUDUR TO KARAIPETTAI FROM KM 37.000 TO KM 71.015 OF NH 48 | 1/2019 | 819.89 | 821 | 356.63 |
50. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANINIG OF CHETTIKULAM TO NATHAM SECTION OF NH-785 FROM CHETTIKULUM (KM 7.300) TO NATHAM (KM. 3 | 3/2018 | 505.35 | 837.69 | 376.61 |
51. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | BANGALORE CHENNAI EXPRESSWAY PHASE-III – PACKAGE I (GUDIPALA TO WALAJAJHPET) FROM KM 156.000 TO KM 1 | 10/2020 | 1023.91 | 1284.62 | 438.11 |
52. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANNING OF VIKRAVANDI-SETHIYAHOPU FROM KM 0.000 TO KM 60.250(DESIGN CHAINAGE KM 0.000 TO KM 65. | 3/2017 | 848.45 | 848.45 | 303.04 |
53. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4L OF THIRUMANGALAM TO VADUGAPATTI SECTION FROM KM 0.000 TO KM 36.000 OF NH-744 | 3/2022 | 1076.97 | 1076.97 | 261.62 |
54. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4-LANING OF ODDANCHATRAM - MADATHUKULAM SECTION OF NH-209 (NEW NH-83) | 1/2019 | 1518.53 | 1607.54 | 915.4 |
55. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF STRR (WEST SIDE)-NH948A-BALAGONDAPALLI (TAMIL NADU) TO KARNATAKA/TAMIL NADU BORDER F | 4/2022 | 1260.74 | 1260.74 | 248.22 |
56. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANING OF THORAPALLI AGRAHARAM TO JITTANDAHALLI SECTION OF NH-844 (PKG-II) FROM KM.23+350 TO KM | 2/2019 | 1243.57 | 1243.57 | 171.63 |
57. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4-LANING OF MELUR - PILLAYARPATTI - KARAIKUDI SECTION OF NH-338, NH-36, NH-383 | 6/2018 | 1103.86 | 1103.86 | 402.09 |
58. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANÌNG OF PUDUCHERRY (KM.29/000) TO POONDIYANKUPPAM (KM.67/000) SECTION OF NH-45A ON HAM UNDER | 3/2018 | 1294.47 | 1588.4 | 734.52 |
59. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | BALANCE WORK 2-LANE WITH PAVED SHOULDERS OF NAGAPATTINAM - THANJAVUR SECTION OF NH-67 (NEW NH-83) | 10/2020 | 434.12 | 434.12 | 258.89 |
60. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF 4 LANE WITH PAVED SHOULDERS THIRUVAYARU BYPASS IN BETWEEN EXISTING KM.55/926 TO 62/6 | 2/2022 | 191.33 | 191.33 | 71.8 |
61. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | BANGALORE CHENNAI EXPRESSWAY PHASE-III PACKAGE III (ARAKKONAM TO KANCHEEPURAM) FROM KM 204.500 TO K | 11/2020 | 1155.49 | 1458.45 | 402.84 |
62. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANING OF POONDIYANKUPPAM (KM.67/000) TO SATTANATHAPOURAM (KM.123/800) SECTION OF NH-45A ON HAM | 3/2018 | 2120.4 | 2565.63 | 1388.24 |
63. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4-LANING OF MADATHUKULAM - POLLACHI SECTION OF NH-209 (NEW NH-83) | 1/2019 | 1409.38 | 1409.38 | 597.59 |
64. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANNING OF CHOLOPURAM-THANJAVUR | 8/2017 | 1176.37 | 1176.37 | 1132.97 |
65. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | KARAIPETTAI TO WALAJAPET FROM KM 71.015 TO 107.091 | 10/2018 | 707.9 | 766.51 | 363.86 |
66. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANING OF MADURAI- CHETTIKULAM SECTION OF NH-785 FROM MADURAI (KM 0/000) TO CHETTICULAM (7/300) | 3/2018 | 628.71 | 756.13 | 583.02 |
67. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANING OF VILUPPURAM TO PUDHUCHERRY (DESIGN CH. KM. 00/000 TO KM. 29/000) SECTION OF NH-45A ON | 3/2018 | 998.7 | 1358.32 | 856.09 |
68. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 6L OF MADURAVOYAL TO SRIPERUMBUDUR SECTION FROM KM. 13.800 TO KM. 37.000 OF NH-4 THROUGH STATE HIGH | 11/2021 | 463.44 | 463.44 | 311.84 |
69. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 8L OF GUDUVANCHERY (KM 38.00) - MARAIMALAI NAGAR (KM 42.00) - SINGAPERUMAL KOIL (47.00) - CHETTIPU | 12/2020 | 230.69 | 230.69 | 197.46 |
70. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | TWO LANING WITH PAVED SHOULDER OF MEENSURUTTI (KM. 98.433) TO CHIDAMBARM (KM. 129.965.) SECTION OF N | 3/2018 | 633.55 | 883.21 | 265.12 |
71. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | BALANCE WORKS OF FOUR LANE FROM KM 43+950 (THIRUVALLUR BYPASS) TO KM 61+470 (VEPPAMPATTU BYPASS) PAS | 1/2022 | 467.99 | 468 | 18.83 |
72. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4-LANNING OF STHIYATHOPU-CHOLOPURAM | 9/2017 | 1227.87 | 1227.87 | 1203.43 |
73. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANING OF JITTANDAHALLI TO DHARMAPURI SECTION OF NH-844 (PKG-III) FROM KM.60+100 TO KM.94+460 | 2/2019 | 1291.37 | 1291.37 | 215.02 |
74. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | WIDENING FROM TWO LANE TO TWO LANE WITH PAVED SHOULDER FROM KM 34/000 TO 49/000 AND TWO LANE TO FOUR | 2/2022 | 184.15 | 184.15 | 150.82 |
75. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANING OF SATTANATHAPURAM (KM.123/800) TO NAGAPATTINAM (KM.179/555) SECTION OF NH-45A ON HAM UN | 3/2018 | 1872.68 | 2756.09 | 1031.85 |
76. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | SIX LANING OF TUTICORIN PORT ROAD SECTION OF NH-7A (NEW NH-138) FROM KM 0.000 TO KM 6.140 [EFFECTIVE | 3/2023 | 200.3 | 200.3 | 11.93 |
77. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF NEW DOUBLE TIER 4L ELEVATED CORRIDOR FROM CHENNAI PORT TO MADURAVOYAL IN CHENNAI DIS | 3/2023 | 1301.37 | 1301.37 | 0 |
78. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF NEW DOUBLE TIER 4L ELEVATED CORRIDOR FROM CHENNAI PORT TO MADURAVOYAL IN CHENNAI DIS | 3/2023 | 1207.4 | 1207.4 | 0 |
79. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF NEW DOUBLE TIER 4 LANE ELEVATED CORRIDOR FROM CHENNAI PORT TO MADURAVOYAL IN CHENNAI | 3/2023 | 1382 | 1382 | 0 |
80. | URBAN DEVELOPMENT | CHENNAI METRO RAIL LTD | CHENNAI METRO RAIL LTD (PHASE 1) | 2/2009 | 14600 | 18380 | 17619.68 |
81. | URBAN DEVELOPMENT | CHENNAI METRO RAIL LTD | CHENNAI METRO RAIL LTD (PHASE 1 EXT) | 6/2016 | 3770 | 3770 | 2527.73 |
| Total | 81 | |