S No. | Sector Name | Agency Name | Project Name | Date Of Approval | Cost Original | Cost Anticipated | Expenditure |
1. | CIVIL AVIATION | AIRPORT AUTHORITY OF INDIA LIMITED | PRAYAGRAJ AIRPORT - CONSTRUCTION OF NEW TERMINAL BUILDING, SECOND LINK TAXI TRACK, APRON EXPANSION, | 5/2023 | 185.75 | 185.75 | 15.85 |
2. | CIVIL AVIATION | AIRPORT AUTHORITY OF INDIA LIMITED | CCS INTERNATIONAL AIRPORT , LUCKNOW | 6/2018 | 1383 | 3291.81 | 2112.84 |
3. | CIVIL AVIATION | AIRPORT AUTHORITY OF INDIA LIMITED | DEVELOPMENT OF AYODHYA AIRPORT PHASE-01 | 3/2021 | 242.14 | 328 | 328.98 |
4. | COAL | NEYVELI LIGNITE CORPORATION | NEYVELI UTTAR PRADESH POWER PROJECT LIMITED 1980 MW | 7/2016 | 17237 | 19406.12 | 17142.31 |
5. | COAL | NORTHERN COAL FIELDS LIMITED | KHADIA EXPANSION OCP | 6/2021 | 491.67 | 491.67 | 20.12 |
6. | HOME AFFAIRS | CPWD FOR MHA | CONSTRUCTION OF 683 VARIOUS TYPE FAMILY QUARTERS AT GROUP CENTRE CRPF CHANDAULI | 5/2019 | 199.31 | 199.31 | 86.49 |
7. | PETROLEUM | HINDUSTAN PETROLEUM CORPORATION LIMITED | CITY GAS DISTRIBUTION IN UP AND UK | 3/2019 | 3450.2 | 3450.2 | 1505.5 |
8. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | GRASS-ROOT TERMINAL AT MIRZAPUR UTTAR PRADESH | 9/2022 | 980.45 | 980.45 | 62.45 |
9. | PETROLEUM | GAS AUTHORITY OF INDIA LIMITED | 60 KTA POLYPROPYLENE PROJECT | 3/2019 | 910.56 | 1299.02 | 670.4 |
10. | PETROLEUM | INDIAN OIL CORPORATION LIMITED | AUGMENTATION OF FACILITIES AT MATHURA BITUMEN PLANT | 4/2022 | 260.12 | 260.12 | .25 |
11. | POWER | THDC INDIA LIMITED | KHURJA SUPER THERMAL POWER PROJECT | 3/2019 | 11089.42 | 11089.42 | 9784.81 |
12. | POWER | NATIONAL HYDRO-ELECTRIC POWER CORPORATION | KALPI SOLAR POWER PROJECT | 7/2020 | 314.64 | 350.46 | 295.32 |
13. | RAILWAYS | NORTH EASTERN RAILWAY | BAHRAICH SRAVASTI BALRAMPUR (TULSIPUR) | 10/2018 | 1600 | 4939.78 | 634.45 |
14. | RAILWAYS | RAIL VIKAS NIGAM LTD. | JANGHAI-PHAPHAMAU - DOUBLING WITH ELECTRIFICATION (46.79 KM) | 11/2018 | 357.48 | 409.38 | 246.85 |
15. | RAILWAYS | NORTH CENTRAL RAILWAY | JHANSI MANIKPUR AND KHAIRAR BHIMSEN DOUBLING | 3/2018 | 4329.53 | 4329.53 | 60.37 |
16. | RAILWAYS | NORTH EASTERN RAILWAY | ROSA-SITAPUR CANTT-BURHWAL DOUBLING | 3/2015 | 1295.42 | 2560 | 2262.57 |
17. | RAILWAYS | NORTH CENTRAL RAILWAY | BHANDAI - FLYOVER FOR ETAWAH BOUND DOWN TRAINS | 4/2019 | 187.21 | 250.17 | 1.29 |
18. | RAILWAYS | NORTH EASTERN RAILWAY | DOMINGARH - GORAKHPUR - GORAKHPUR CANTT - KUSUMHI - 3RD RUNNING LINE (21.15 KM) | 11/2016 | 186.85 | 457.68 | 396.85 |
19. | RAILWAYS | NORTH CENTRAL RAILWAY | MUGHALSARAI - ALLAHABAD - 3RD LINE | 8/2019 | 2390 | 2390 | 0 |
20. | RAILWAYS | NORTH EASTERN RAILWAY | BURHWAL - GONDA - 3RD RUNNING LINE. | 4/2016 | 602.5 | 714.96 | 647.12 |
21. | RAILWAYS | NORTHERN RAILWAY | JANGHAI PRATAPGARH AMETHI DOUBLING | 11/2017 | 701.98 | 1100 | 0 |
22. | RAILWAYS | NORTH CENTRAL RAILWAY | ALIGARH-HARDUAGANJ FLYOVER (22 KM) | 4/2020 | 1456.89 | 1456.89 | 0 |
23. | RAILWAYS | NORTH CENTRAL RAILWAY | ALIGARH-DAUD KHAN - 3RD LINE (6.9 KM) & CONSTRUCTION OF FLYOVER AT DAUD KHAN | 4/2019 | 451.99 | 451.99 | 0 |
24. | RAILWAYS | RAIL VIKAS NIGAM LTD. | LUCKNOW- PILIBHIT VIA SITAPUR, LAKHIMPUR GC | 4/2011 | 927.01 | 1457.79 | 1684 |
25. | RAILWAYS | RAIL VIKAS NIGAM LTD. | BHATNI - AUNRIHAR WITH ELECTRIFICATION (125 KM) (EXCL INDARA - MAU (116.95 KM)) | 5/2018 | 1177.96 | 2529.46 | 1537.14 |
26. | RAILWAYS | NORTH EASTERN RAILWAY | SHAHGANJ-BHATNI-PHEPHNA-INDARA, MAU-SHAHGANJ (EXCL. MAU-INDARA) PATCH DOUBLING. | 4/2016 | 1177.96 | 1777.39 | 1429.35 |
27. | RAILWAYS | NORTH CENTRAL RAILWAY | LALITPUR - BIRARI WITH FLYOVER AT LALITPUR | 3/2017 | 260 | 260 | 0 |
28. | RAILWAYS | NORTH CENTRAL RAILWAY | ALLAHABAD-BAMHRAULI - 4TH LINE (10 KM) WITH FLY-OVER AT SUBEDARGANJ | 4/2019 | 494.11 | 494.11 | 0 |
29. | RAILWAYS | NORTH CENTRAL RAILWAY | JHANSI BINA DOUBLING | 9/2016 | 2001 | 2001 | 1118.8 |
30. | RAILWAYS | RAIL VIKAS NIGAM LTD. | VARANASI-MODHOSINGH-ALLAHABAD DOUBLING | 4/2015 | 943.6 | 2018.23 | 1459.5 |
31. | RAILWAYS | EAST CENTRAL RAILWAYS | RAMNA - SINGRAULI DOUBLING | 8/2015 | 2436.21 | 2880.4 | 2729.14 |
32. | RAILWAYS | NORTH EASTERN RAILWAY | BAHRAICH - NANPARA -NEPALGANJ (56.15 KM) | 7/2020 | 950 | 341.66 | 7.84 |
33. | RAILWAYS | NORTHERN RAILWAY | DOUBLING BETWEEN JAUNPUR JN-ZAFFARABAD (6.28 KM) | 3/2023 | 177.33 | 177.33 | 0 |
34. | RAILWAYS | NORTHERN RAILWAY | BARABANKI-MALHAUR - 3RD & 4TH LINE (32.84 KM) | 1/2019 | 323.85 | 323.85 | 0 |
35. | RAILWAYS | RAIL VIKAS NIGAM LTD. | MATHURA-JHANSI-3RD LINE (273.80 KM) | 6/2016 | 3677.76 | 5190.26 | 4893.11 |
36. | RAILWAYS | NORTHERN RAILWAY | BARABANKI AKBARPUR DOUBLING | 9/2017 | 1200 | 1700 | 0 |
37. | RAILWAYS | NORTHERN RAILWAY | JAUNPUR AKBARPUR (TANDA) DOUBLING | 8/2017 | 515.5 | 676 | 0 |
38. | RAILWAYS | RAIL VIKAS NIGAM LTD. | MAU-GHAZIPUR-TARIGHAT NEW LINE | 4/2015 | 1765.92 | 1765.92 | 1687.89 |
39. | RAILWAYS | NORTH CENTRAL RAILWAY | MATHURA - VRINDAVAN (11 KM) | 8/2022 | 402.88 | 402.88 | 0 |
40. | RAILWAYS | NORTH EASTERN RAILWAY | SAHJANWA - DOHRIGHAT | 8/2019 | 371.77 | 1319.75 | 346.5 |
41. | RAILWAYS | EAST CENTRAL RAILWAYS | SURFACE TRIANGLE LINE BETWEEN BHADURA STATION AND NEW CROSSING STN KARMA DOUBLING | 10/2022 | 199.96 | 199.96 | 55 |
42. | RAILWAYS | EAST CENTRAL RAILWAYS | KARAILA ROAD - SHAKTINAGAR DOUBLING | 8/2015 | 528.57 | 762.97 | 679.98 |
43. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | REHABILITATION AND UPGRADATION TO 2 LANE WITH PS OF MIRANPUR KATRA TO RADHAITA SECTION OF NH-730C F | 4/2020 | 172.5 | 172.5 | 75.84 |
44. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF NEW 4 LANE PRAYAGRAJ SOUTHERN BYPASS (PHASE-I) FROM DESIGN KM 43+200 (AT MAHUWARI VI | 8/2023 | 1378.36 | 739 | 9.89 |
45. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF NH-24 EXTENSION 4-LANE BYPASS STARTING FROM BEHTA ROAD AND TERMINATING AT SITAPUR RO | 3/2018 | 1117.84 | 1117.84 | 1165.5 |
46. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | IMPROVEMENT AND UPGRADATION TO TWO LANE WITH PAVED SHOULDER CONFIGURATION FROM EXISTING KM 55.00 TO | 11/2021 | 307.11 | 307.11 | 130.04 |
47. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4L OF SHAMLI TO MUZAFFARNAGAR SECTION OF NH-709AD, PKG-II | 6/2020 | 1621.07 | 1621.07 | 1058.71 |
48. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | REHABILITATION and UPGRADATION FROM 2 LANE TO 4 LANE OF NH STRETCH UNDER BHARATMALA PARIYOJANA FOR U | 10/2019 | 1779.83 | 2200 | 931 |
49. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF TWO LANE WITH PAVED SHOULDER HIGHWAY FROM DESIGN CH.0.000 TO CH.49.2OO OF NH-731B ON | 3/2022 | 640.18 | 640.18 | 239.95 |
50. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | IMPROVEMENT AND UPGRADATION TO TWO LANE WITH PAVED SHOULDER CONFIGURATION FROM EXISTING KM 90.00 TO | 11/2021 | 403.36 | 403.36 | 30.44 |
51. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | IMPROVEMENT AND UP-GRADATION OF EXISTING ROAD TO 2/4L PS FROM KM 40.000 TO 88.750, START OF KHUTAR B | 3/2022 | 762.62 | 762.62 | 275.02 |
52. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | WIDENING AND STRENGTHENING FROM KM.15.000 TO KM, 58.600 (BHADEWARA -DRAMANDGANJ SECTION) OF NATIONAL | 12/2021 | 257.97 | 257.97 | 132.48 |
53. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF 4 LANE GREEN FIELD NORTHERN EAST SIDE GORAKHPUR BYPASS (26.616 KMS) STARTING FROM NH | 2/2023 | 1973.98 | 1973.98 | 381.93 |
54. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4L FROM GAJU VILLAGE AT KM 32.982 TO DEVINAGAR BYPASS (END) AT KM 208.000 OF NH 530B (PKG 1C) | 12/2021 | 1384.79 | 1384.79 | 603.35 |
55. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANING OF SONAULI GORAKHPUR SECTION OF NH 29E (NEW NH 24) FROM DESIGN CH. 0.000 TO DESIGN CH. 7 | 12/2021 | 2555.5 | 2555.5 | 632.79 |
56. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | REHABILITATION AND UPGRADATION TO 2 LANE WITH PS OF RADHAITA TO PILIBHIT SECTION OF 46.130 KM | 4/2020 | 199.39 | 199.39 | 130.92 |
57. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4 LANE CONNECTOR FROM DELHI MEERUT EXPRESSWAY KM 50.000 TO KM 8.520 OF NH 235 IN THE STATE OF UTTAR | 8/2021 | 1147.26 | 1147.26 | 51.88 |
58. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | IMPROVEMENT , UP-GRADATION OF NH-734 SECTION OF MORADABAD - THAKURDWARA - KASHIPUR: “PACKAGE-I: MORA | 10/2022 | 1841.92 | 1841.92 | 139.2 |
59. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | SIX LANING OF HAPUR BYPASS TO MORADABAD SECTION INCLUDING HAPUR BYPASS FROM KM 50.000 (DESIGN CHAINA | 3/2018 | 2140.93 | 2140.93 | 2044.81 |
60. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF FOUR LANE HIGHWAY FROM GHAZIPUR BALLIA UP BIHAR STATE BORDER (GREENFIELD) SECTION OF | 10/2022 | 1493.14 | 1493.14 | 30.9 |
61. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 6L ACCESS CONTROL GREENFIELD HIGHWAY OF VILL-KHYAWARI TO VILL-LATIFPUR AT SAHARANPUR BYPASS FROM KM | 3/2022 | 1428.19 | 1428.19 | 368.73 |
62. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 88.00 148.00 KM 4-LANNING OF VARANASI GORAKHPU | 3/2016 | 1396.74 | 1396.74 | 3797.76 |
63. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4LPS OF MUZAFFARNAGAR TO MIRANPUR SECTION OF NH-709AD, PKG-III | 11/2021 | 923.15 | 923.15 | 455.61 |
64. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 6L GREENFIELD KANPUR - LUCKNOW (EXPRESSWAY) PKG II FROM KM. 28.500 TO KM. 73.744 | 12/2021 | 2470.64 | 2335 | 401.95 |
65. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | DEVELOPMENT OF SIX-LANE ACCESS CONTROLLED HIGHWAY FROM GOGWAN JALALPUR (SHAMLI DISTRICT) TO RANIPUR | 4/2022 | 1843.59 | 1843.59 | 716.12 |
66. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | SIX LANING OF CHAKERI TO ALLAHABAD SECTION OF NH-2 FROM KM 483.687 TO KM 628.753 (DESIGN LENGTH – 14 | 11/2017 | 2159 | 2262 | 2240.43 |
67. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF LEFT OUT PORTION OF AGRA INNER RING ROAD CONNECTING VILLAGE DEORI TO NH-44 VILLAGE B | 10/2021 | 772.05 | 772.05 | 530.47 |
68. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | IMPROVEMENT AND UP-GRADATION OF EXISTING ROAD TO 4L PS FROM KM 175.080 TO 229.070, FROM END OF HARDO | 12/2021 | 1138.81 | 1138.81 | 194.8 |
69. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | SPUR OF MEERUT-GARH-MUKTESHWAR SECTION(NH-709A) CONNECTING NH-119 AND NH-58 BYPASSING MEERUT TOWN | 1/2022 | 953.79 | 953.79 | 384.66 |
70. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF MARIAHU BYPASS WITH FOUR LANE PAVED SHOULDER CONFIGURATION (KM.53.540 TO KM.59.200) | 3/2023 | 438.24 | 438.24 | 151.35 |
71. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | IMPROVEMENT AND UP-GRADATION OF EXISTING ROAD TO 4L PS FROM KM 229.070 TO 260.800, END OF HARDOI DIS | 12/2021 | 540.97 | 540.97 | 75.66 |
72. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF RING ROAD FOR RAEBARELI CITY (PHASE -I) ON EASTERN SIDE OF NH 24B | 12/2019 | 282.41 | 319.96 | 269.08 |
73. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 6L ACCESS CONTROL GREENFIELD HIGHWAY OF VILL-KARAUNDA MAHAJAN TO VILL-KHYAWARI FROM KM. 56.500 TO K | 1/2022 | 1159.96 | 1159.96 | 485.74 |
74. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | REHABILITATION AND UPGRADATION FROM KM 51.600 TO KM 75.700 OF NH-321G (NUHKHAS TO ETAH SECTION) TO T | 1/2022 | 343.54 | 343.54 | 22.2 |
75. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4-LANNING OF HARIDWAR-NAGINA SECTION OF NH 74 FROM (KM 204.300 OF NH 58) TO KM 73.00 | 3/2016 | 1408 | 1659.12 | 1157.69 |
76. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF JASRA BYPASS WITH FOUR LANE PAVED SHOULDER CONFIGURATION FROM KM. 379.670 ON NH-76 ( | 2/2023 | 274.06 | 274.06 | 0 |
77. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ALLAHGANJ TO MIRANPUR KATRA SECTION OF NH-730C FROM KM.52.770 TO 114.00 | 4/2020 | 294.84 | 294.84 | 242.16 |
78. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | IMPROVEMENT AND UP-GRADATION OF EXISTING ROAD TO 4L PS FROM KM 123.650 TO 175.080, FROM START OF SHA | 9/2022 | 1212.26 | 1212.26 | 182.1 |
79. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 6L ACCESS CONTROL GREENFIELD HIGHWAY OF VILL-LOHADDA TO VILL-KARAUNDA MAHAJAN FROM KM. 27.000 TO KM. | 3/2022 | 1335.45 | 1335.45 | 306 |
80. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | WIDENING OF RAEBARELI TO PRAYAGRAJ SECTION FROM KM. 82.650 TO KM. 161.450 OF NH-30 AND LINK ROAD FRO | 11/2023 | 1470.93 | 1470.93 | 69.56 |
81. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4L SPUR OF SHAMLI-MUZZAFARNAGAR CONNECTING NH-709AD (PANIPAT-SHAMLI-MUZAFFARNAGAR) AND NH-58 (MEERUT | 1/2023 | 391.26 | 391.26 | 14.12 |
82. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 2-LANE EXISTING RAMPUR BYPASS OF RAMPUR TO BE DEVELOPED TO 4-LANE ON EPC MODE IN THE STATE OF UTTAR | 3/2021 | 364.47 | 364.47 | 106.87 |
83. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF PRATAPGARH BYPASS (EXTENSION) CONNECTING NH-31 TO NH-330 | 10/2022 | 225.17 | 225.17 | 64.43 |
84. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF SHOHRATGARH BYPASS ON NH-730 UNDER EPC MODE IN THE STATE OF UTTAR PRADESH | 10/2022 | 189.31 | 189.31 | 46.36 |
85. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | R/U TO 2-LANE WITH PS OF BEWAR TO ALLAHGANJ SECTION OF NH-730C FROM KM.0.00 TO 52.770 UNDER GNHCP | 4/2020 | 325.24 | 325.24 | 146.25 |
86. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF 4 LANE ELEVATED VIADUCT AT KM. 7.500 MUNSHI PULIA OF NH-24A | 12/2021 | 170.6 | 170.6 | 152.84 |
87. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 2-LANE WITH PS OF BEWAR TO NEAR KARRI VILLAGE SECTION OF NH-92 FROM KM.0.00 TO 30.00 UNDER GNHCP | 4/2020 | 236.47 | 236.47 | 113.64 |
88. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF 6 LANE BRIDGE ON GANGA ON NH-96 AND ITS APPROACHES IN PHAPHAMAU ALLAHABAD ON EPC MOD | 7/2018 | 1948.25 | 1948.25 | 861.29 |
89. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | WIDENING AND UPGRADATION TO FOUR LANE CONFIGURATION FROM KM.34.900 (BHADOHI) TO KM.73.134 (JAUNPUR) | 3/2021 | 395.62 | 395.62 | 165.81 |
90. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | WIDENING AND STRENGTHENING OF SECTION FROM BHARTHANA CHOWK TO KODARKOOT (KM. 0.00 TO KM. 40.00) OF | 3/2020 | 262.37 | 343.77 | 186.58 |
91. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4L SPUR OF PANIPAT - SHAMLI CONNECTING NH-709AD (PANIPAT – SHAMLI – MUZAFFARNAGAR) AND NH-709A (KARN | 8/2022 | 326.79 | 329.79 | 83.46 |
92. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | KANPUR LUCKNOW EXPRESSWAY PKG-1 CONSTRUCTION OF 6-LANE TO EIGHT LANE OF KANPUR LUCKNOW EXPRESSWAY (N | 12/2021 | 1972.1 | 1936 | 402.14 |
93. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | WIDENING TO FOUR LANE WITH PAVED SHOULDER FROM DESIGN KM.49.200 TO KM.89.285 OF NH-731B ON EPC MODE | 3/2022 | 917.91 | 917.91 | 409.12 |
94. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4L FROM MATHURA BYPASS (START) AT EXISTING KM. 154.20 OF NH-44 TO GAJU VILLAGE AT KM 32.982 OF NH-53 | 1/2022 | 1738.2 | 1738.2 | 702.65 |
95. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | BALANCE WORKS OF 4-LANNING OF RAMPUR-KATHGODAM SECTION OF NH-87 (NEW NH NO. 09) FROM KM. 0.000 (KM 1 | 8/2022 | 199.31 | 199.38 | 104.35 |
96. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4L OF SHAMLI BYAPSS- SAHARANPUR FROM KM 92.2 TO KM 155.025 SECTION OF NH-709B, PKG-II | 5/2019 | 779.17 | 779.17 | 13.27 |
97. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | WIDENING AND STRENGTHENING FROM KM 0.00 TO KM 15.089 OF NH-334A (PURKAJI-LAKSAR-HARIDWAR ROAD) TO TW | 10/2021 | 227.06 | 227.06 | 82.59 |
98. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF FOUR LANE HIGHWAY FROM GHAZIPUR BALLIA UP BIHAR STATE BORDER (GREENFIELD) SECTION OF | 10/2022 | 1493.5 | 1493.5 | 468.41 |
99. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | IMPROVEMENT AND UP-GRADATION TO TWO LANE WITH PAVED SHOULDER CONFIGURATION FROM EXISTING KM. 420.00 | 1/2022 | 509.65 | 509.65 | 109.01 |
100. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF TWO LANE WITH PAVED SHOULDER FROM EXISTING KM.0.000 TO KM.55.610 (DESIGN KM. 0.000 T | 12/2021 | 840.93 | 840.93 | 337.18 |
101. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | VARANASI RING ROAD (PKG-II) CONNECTING SANDAHA VILLAGE (KM 11.70 / NH-29) WITH REVASA VILLAGE (KM 81 | 2/2019 | 927.77 | 1603 | 1202.77 |
102. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF RING ROAD AROUND KANPUR FROM KM.000 TO KM. 23.325 (CHACHENDI SACHENDI I TO MAHARAJPU | 1/2023 | 1754 | 1754 | 172.25 |
103. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF FOUR-LANE “WESTERN SIDE SPUR OF RAMPUR-RUDRAPUR SECTION CONNECTING NH-24 TO NH-87 BY | 3/2021 | 646.27 | 646.27 | 38.83 |
104. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 6L ACCESS CONTROLLED GREENFIELD HIGHWAY OF JUNCTION OF EPE (VILL.-MAVIKALAN) TO VILL.-LOHADDA FROM K | 3/2022 | 1602.48 | 1602.48 | 274.09 |
105. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | PROJECTS- REHABILITATION AND UPGRADATION OF NH-731A FROM KM 0.00 TO KM.35.00 | 3/2021 | 264.86 | 264.86 | 97.23 |
106. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 6L OF ACCESS-CONTROLLED HIGHWAY FROM MOHAND TO DAAT KALI TUNNEL OF GANESHPUR – DEHRADUN SECTION FROM | 3/2021 | 990.28 | 990.28 | 997.24 |
107. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF NEW 4 LANE PRAYAGRAJ SOUTHERN BYPASS FROM DESIGN KM 50.860 (NABABA URF NIBI KALA UPA | 8/2023 | 993.77 | 349.48 | 44.78 |
108. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 2LPS OF BIJNOR TO KOTAWALI SECTION OF NH-709AD, PKG-IV | 9/2021 | 300.79 | 300.79 | 122.56 |
109. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4-LANING OF MEERUT NAJIBABAD SECTION FROM KM. 11.500 TO KM 39.250 AND KM 86.590 TO KM. 112.545.IN TH | 10/2019 | 1936.68 | 2458.03 | 1380.9 |
110. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | TWO / FOUR LANING OF RAEBARELI - JAGDISHPUR SECTION OF NH-330A FROM KM. 0.000 TO KM. 47.800 (DESIGN | 10/2020 | 724.6 | 724.6 | 569.96 |
111. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | STRENGTHENING OF EXISTING 4L AYODHYA BYPASS SECTION FROM DESIGN KM.121.600 TO KM. 144.020 OF NH 28 ( | 2/2023 | 526.45 | 526.45 | 73.16 |
112. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF FOUR LANE HIGHWAY FROM GHAZIPUR BALLIA UP BIHAR STATE BORDER GREENFIELD SECTION OF N | 10/2022 | 617.87 | 617.87 | 64.75 |
113. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | SIX LANE ACCESS CONTROLLED OF DELHI SAHARANPUR HIGHWAY FROM DELHI UP BORDER TO EPE JUNCTION CH.14.75 | 6/2020 | 2002.79 | 2002.79 | 1211.94 |
114. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF FOUR-LANE ELEVATED VIADUCT FROM KM.4+634 TO KM.6+345 ON NH-24A INCLUDING RETAINING W | 3/2021 | 185.09 | 185.09 | 238.59 |
115. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | GARHMUKTESHWAR (KM. 83.200 OF NH-24) TO MEERUT (KM. 9.860 OF NH-235) INCLUDING CONNECTOR TO NH-119 | 10/2019 | 2068.99 | 2171 | 199.6 |
116. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF 4-LANE GREEN FIELD HIGHWAY FROM KM. 35.000 TO KM. 49.155 OF NH-731A WITH PAVED SHOUL | 1/2022 | 697.66 | 697.66 | 192.84 |
117. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF 4-LANE HIGHWAY WITH PAVED SHOULDERS FROM KM 49.155 TO KM 74.700 OF NH-731A ON HYBRID | 1/2022 | 1156.72 | 1156.72 | 116.34 |
118. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANNING OF JAGDISHPUR-FAIZABAD SECTION FROM KM 47.930 TO KM 107.680 OF NH-330A | 3/2021 | 1980 | 1980 | 1185.97 |
119. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 6L OF AGRA BYPASS (NORTHERN) CONNECTING KM. 174.500 OF NH-2 (NEW NH-19) TO KM. 141.000 OF YAMUNA EXP | 10/2021 | 957.62 | 957.62 | 571.8 |
120. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | CONSTRUCTION OF FOUR LANE HIGHWAY FORM GHAZIPUR BALLIA UP BIHAR STATE BORDER (GREENFIELD) SECTION OF | 10/2022 | 1706.47 | 1706.47 | 666.71 |
121. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | CONSTRUCTION OF BYPASS FOR PROVIDING INTER CONNECTIVITY AMONG (NHS) AROUND THE PRATAPGARH CITY (PRAT | 4/2021 | 309.48 | 309.48 | 112.76 |
122. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4L BYPASSES FOR JAGATPUR, B4ABUGANJ, UNCHAHAR, ALAPUR BYPASS, AND SAI RIVER BRIDGE OF RAEBARELI- PRA | 12/2022 | 1699 | 1699 | 64.39 |
123. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | FOUR LANNING OF RAMPUR- KATHGODAM SECTION OF NH-87 FROM KM 0.000 (KM. 190.000 OF NH-24) TO KM 42.791 | 3/2016 | 899 | 1619.32 | 1058.06 |
124. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 2-LANE WITH PS OF NEAR KARRI VILLAGE TO ETAWAH SECTION OF NH-92 FROM KM.30.000 TO 57.346 UNDER GNHCP | 4/2020 | 211.09 | 211.09 | 72.69 |
125. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4 LANING OF NAJIBABAD BYPASS OF NH-119 FROM KM. 105.423 TO KM. 118.373 (EXCLUDING 2.45 KM. OF NH-74 | 2/2022 | 570.98 | 578.02 | 217.74 |
126. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 4-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 148.00 208.300 KM [PACKAGE-IV] | 3/2016 | 1587.49 | 3063.99 | 2969.21 |
127. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 6L ACCESS-CONTROLLED HIGHWAY FROM (GANESHPUR) TO(NEAR MOHAND) OF GANESHPUR – DEHRADUN SECTION FROM K | 3/2021 | 836.24 | 836.24 | 772.63 |
128. | URBAN DEVELOPMENT | LUCKNOW METRO RAIL CORPORATION LIMITED | KANPUR METRO RAIL PROJECT | 5/2019 | 11076.48 | 11076.48 | 6762.53 |
129. | URBAN DEVELOPMENT | LUCKNOW METRO RAIL CORPORATION LIMITED | AGRA METRO RAIL PROJECT | 5/2019 | 8379.62 | 8379.62 | 3522.35 |
130. | WATER RESOURCES | Uttar Pradesh Jal Nigam | INTERCEPTION AND DIVERSION WORKS AND STP AT MUZAFFARNAGAR UTTAR PRADESH | 1/2019 | 231.79 | 234.03 | 141.79 |
131. | WATER RESOURCES | Uttar Pradesh Jal Nigam | MATHURA SEWERAGE SCHEME | 12/2017 | 460.45 | 460.45 | 315.3 |
132. | WATER RESOURCES | Uttar Pradesh Jal Nigam | STP AT PANKHA KANPUR AND INTEGRATION WITH EXISTING STPS | 3/2018 | 967.23 | 967.23 | 254.98 |
133. | WATER RESOURCES | Uttar Pradesh Jal Nigam | INTERCEPTION AND DIVERSION WORKS WITH STP AT LUCKNOW UTTAR PRADESH | 3/2019 | 298.12 | 213.91 | 67.74 |
134. | WATER RESOURCES | Uttar Pradesh Jal Nigam | INTERCEPTION AND DIVERSION WORKS WITH STP AT BAREILLY, UTTAR PRADESH | 3/2019 | 271.39 | 271.39 | 181.03 |
135. | WATER RESOURCES | Uttar Pradesh Jal Nigam | INTERCEPTION, DIVERSION AND TREATMENT WORKS FOR NAINI DISTRICT G PHAPHAMAU DISTRICT F AND JHUSI AREA | 5/2017 | 767.59 | 767.59 | 276.97 |
136. | WATER RESOURCES | Uttar Pradesh Jal Nigam | INTERCEPTION AND DIVERSION WORKS AND SEWAGE TREATMENT PLANT AT JAUNPUR UTTAR PRADESH | 1/2019 | 206.05 | 206.05 | 137.58 |
137. | WATER RESOURCES | Uttar Pradesh Jal Nigam | SEWERAGE SCHEME INTERCEPTION AND DIVERSION WITH STP WORKS AT MEERUT UTTAR PRADESH | 2/2019 | 681.78 | 690.71 | 13.34 |
138. | WATER RESOURCES | Uttar Pradesh Jal Nigam | FARRUKHABAD I AND D AND STP WORKS HAM | 10/2017 | 213.62 | 261.12 | 177.62 |
| Total | 138 | |