S No. | Agency Name | Sector Name | Project Name | Date Of Approval | Cost Original | Cost Anticipated | Expenditure |
1. | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | PRAYAGRAJ AIRPORT - CONSTRUCTION OF NEW TERMINAL BUILDING, SECOND LINK TAXI TRACK, APRON EXPANSION, | 5/2023 | 185.75 | 274.38 | 206.39 |
2. | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | CCS INTERNATIONAL AIRPORT , LUCKNOW | 6/2018 | 1383 | 3291.81 | 2652.63 |
3. | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | VARANASI: DEVELOPMENT OF LAL BAHADUR SHASTRI INTERNATIONAL AIRPORT, VARANASI. | 7/2024 | 2869.65 | 2869.65 | 283 |
4. | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | AGRA: DEVELOPMENT OF NEW CIVIL ENCLAVE AT AGRA AIRPORT. | 6/2024 | 579 | 579 | 72.23 |
5. | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | DEVELOPMENT OF AYODHYA AIRPORT PHASE-01 | 3/2021 | 242.14 | 358 | 344.58 |
6. | BHARAT PETROLEUM CORPORATION LIMITED | PETROLEUM | CITY GAS DISTRIBUTION PROJECTS AT LAKHIMPUR KHERI , SITAPUR, BAHRAICH, SHRAVASTI,BALRAMPUR, | 12/2022 | 16654 | 16654 | 550.36 |
7. | EAST CENTRAL RAILWAYS | RAILWAYS | SURFACE TRIANGLE LINE BETWEEN BHADURA STATION AND NEW CROSSING STN KARMA DOUBLING | 10/2022 | 199.96 | 199.96 | 55.09 |
8. | GAS AUTHORITY OF INDIA LIMITED | PETROLEUM | 60 KTA POLYPROPYLENE PROJECT | 3/2019 | 910.56 | 1299.02 | 974 |
9. | INDIAN OIL CORPORATION LIMITED | PETROLEUM | AUGMENTATION OF FACILITIES AT MATHURA BITUMEN PLANT | 4/2022 | 260.12 | 260.12 | 1.07 |
10. | INDIAN OIL CORPORATION LIMITED | PETROLEUM | GRASS-ROOT TERMINAL AT MIRZAPUR UTTAR PRADESH | 9/2022 | 980.45 | 980.45 | 206.85 |
11. | LUCKNOW METRO RAIL CORPORATION LIMITED | URBAN DEVELOPMENT | KANPUR METRO RAIL PROJECT | 5/2019 | 11076.48 | 11076.48 | 8839.21 |
12. | LUCKNOW METRO RAIL CORPORATION LIMITED | URBAN DEVELOPMENT | AGRA METRO RAIL PROJECT | 5/2019 | 8379.62 | 8379.62 | 5116 |
13. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | REHABILITATION AND UPGRADATION TO 2 LANE WITH PS OF MIRANPUR KATRA TO RADHAITA SECTION OF NH-730C F | 4/2020 | 172.5 | 172.5 | 106.06 |
14. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 2-LANE WITH PS OF NEAR KARRI VILLAGE TO ETAWAH SECTION OF NH-92 FROM KM.30.000 TO 57.346 UNDER GNHCP | 4/2020 | 211.09 | 211.09 | 147.58 |
15. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF 4-LANE HIGHWAY WITH PAVED SHOULDERS FROM KM 49.155 TO KM 74.700 OF NH-731A ON HYBRID | 1/2022 | 1156.72 | 1156.72 | 407.2 |
16. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | REHABILITATION AND UPGRADATION TO FOUR LANE ROAD FROM KM 70.500 TO KM 78.600 OF NH-92 UNDER EPC MODE | 1/2022 | 296.02 | 296.02 | 27.96 |
17. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT AND UPGRADATION TO TWO LANE WITH PAVED SHOULDER CONFIGURATION FROM EXISTING KM 90.00 TO | 11/2021 | 403.36 | 403.36 | 150.57 |
18. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF AMETHI BYPASS (PART-II) AT KM.30.050 OF NH-931 UNDER EPC MODE IN THE STATE OF UTTAR | 12/2022 | 283.86 | 283.86 | 58.92 |
19. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF RAEBARELI RING ROAD (PHASE-2) WITH FOUR LANE CONFIGURATION FOR RAEBARELI CITY IN THE | 3/2022 | 1273.72 | 1273.72 | 330.15 |
20. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF FOUR LANE HIGHWAY WITH PAVED SHOULDER FROM KM.74.700 TO KM.112.950 OF NH-731A (I/C Y | 3/2022 | 1141.67 | 1141.67 | 423.37 |
21. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING AND STRENGTHENING FROM KM 0.00 TO KM 15.089 OF NH-334A (PURKAJI-LAKSAR-HARIDWAR ROAD) TO TW | 10/2021 | 227.06 | 227.06 | 141.89 |
22. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO 4L RIGID PAVEMENT CONFIGURATION FROM KM 90.00 TO KM 100.800 OF NH-96 (KM 42.O TO KM 53.3 | 12/2022 | 309.63 | 309.63 | 13.52 |
23. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT AND UP-GRADATION TO TWO LANE WITH PAVED SHOULDER CONFIGURATION FROM EXISTING KM. 420.00 | 1/2022 | 509.65 | 509.65 | 188.84 |
24. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF TWO LANE WITH PAVED SHOULDER FROM EXISTING KM.0.000 TO KM.55.610 (DESIGN KM. 0.000 T | 12/2021 | 840.93 | 840.93 | 524.04 |
25. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT AND UP-GRADATION OF NH-227B (84 KOSI PARIKRAMA MARG) PACKAGE –I, FROM KM 228.920 (JAGARN | 3/2022 | 912.5 | 912.5 | 388.5 |
26. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | PROJECTS- REHABILITATION AND UPGRADATION OF NH-731A FROM KM 0.00 TO KM.35.00 | 3/2021 | 264.86 | 264.86 | 129.12 |
27. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO 4L FROM KM.108.50 TO 139.00 OF NH-135A PKG-II (JAUNPUR TO AKBARPUR SECTION) ON HAM IN TH | 3/2023 | 1511.57 | 1511.57 | 154.69 |
28. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | REHABILITATION AND UPGRADATION FROM KM 51.600 TO KM 75.700 OF NH-321G (NUHKHAS TO ETAH SECTION) TO T | 1/2022 | 343.54 | 343.54 | 75.96 |
29. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF JASRA BYPASS WITH FOUR LANE PAVED SHOULDER CONFIGURATION FROM KM. 379.670 ON NH-76 ( | 2/2023 | 274.06 | 274.06 | 135.53 |
30. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF PRATAPGARH BYPASS (EXTENSION) CONNECTING NH-31 TO NH-330 | 10/2022 | 225.17 | 225.17 | 96.56 |
31. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF SHOHRATGARH BYPASS ON NH-730 UNDER EPC MODE IN THE STATE OF UTTAR PRADESH | 10/2022 | 189.31 | 189.31 | 59.91 |
32. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING AND STRENGTHENING FROM DESIGN KM. 67.280 TO KM. 88.622 OF NH-727A (SALEMPUR-MAIRWA ROAD) TO | 3/2023 | 371.89 | 371.89 | 151.99 |
33. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | R/U TO 2-LANE WITH PS OF BEWAR TO ALLAHGANJ SECTION OF NH-730C FROM KM.0.00 TO 52.770 UNDER GNHCP | 4/2020 | 325.24 | 325.24 | 284.35 |
34. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF BALRAMPUR BYPASS WITH 2L FLEXIBLE PAVEMENT CONFIGURATION FROM KM.223.000 OF NH-330 T | 12/2022 | 515.69 | 515.69 | 187.8 |
35. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 2-LANE WITH PS OF BEWAR TO NEAR KARRI VILLAGE SECTION OF NH-92 FROM KM.0.00 TO 30.00 UNDER GNHCP | 4/2020 | 236.47 | 236.47 | 145.95 |
36. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF 6 LANE BRIDGE ON GANGA ON NH-96 AND ITS APPROACHES IN PHAPHAMAU ALLAHABAD ON EPC MOD | 7/2018 | 1948.25 | 1948.25 | 1146.61 |
37. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING AND UPGRADATION TO FOUR LANE CONFIGURATION FROM KM.34.900 (BHADOHI) TO KM.73.134 (JAUNPUR) | 3/2021 | 395.62 | 395.62 | 281.93 |
38. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | REHABILITATION AND UPGRADATION TO 2 LANE WITH PS OF RADHAITA TO PILIBHIT SECTION OF 46.130 KM | 4/2020 | 199.39 | 199.39 | 200.01 |
39. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | REHABILITATION and UP-GRADATION TO 2L+PS FROM KM. 0.0 TO KM. 7.80 AND KM. 35.400 TO KM. 52.345 (DESI | 3/2023 | 701.02 | 701.02 | 270.54 |
40. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF MARIAHU BYPASS WITH FOUR LANE PAVED SHOULDER CONFIGURATION (KM.53.540 TO KM.59.200) | 3/2023 | 438.24 | 438.24 | 211.72 |
41. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF RING ROAD FOR RAEBARELI CITY (PHASE -I) ON EASTERN SIDE OF NH 24B | 12/2019 | 282.41 | 319.96 | 276.35 |
42. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING AND STRENGTHENING OF SECTION FROM BHARTHANA CHOWK TO KODARKOOT (KM. 0.00 TO KM. 40.00) OF | 3/2020 | 262.37 | 343.77 | 278.92 |
43. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | WIDENING TO FOUR LANE WITH PAVED SHOULDER FROM DESIGN KM.49.200 TO KM.89.285 OF NH-731B ON EPC MODE | 3/2022 | 917.91 | 917.91 | 615.53 |
44. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT AND UP-GRADATION TO TWO LANE WITH PAVED SHOULDER/FOUR LANE CONFIGURATION FROM EXISTING K | 1/2022 | 974.19 | 974.19 | 616.12 |
45. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF TWO LANE WITH PAVED SHOULDER HIGHWAY FROM DESIGN CH.0.000 TO CH.49.2OO OF NH-731B ON | 3/2022 | 640.18 | 602.76 | 487.39 |
46. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT AND UP-GRADATION OF NH-227B (84 KOSI PARIKRAMA MARG) PACKAGE –III, FROM KM.47.800 (GOSAI | 3/2022 | 587.97 | 587.97 | 107.68 |
47. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF FOUR-LANE ELEVATED VIADUCT FROM KM.4+634 TO KM.6+345 ON NH-24A INCLUDING RETAINING W | 3/2021 | 185.09 | 269.81 | 266.35 |
48. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF 4-LANE GREEN FIELD HIGHWAY FROM KM. 35.000 TO KM. 49.155 OF NH-731A WITH PAVED SHOUL | 1/2022 | 697.66 | 697.66 | 318.82 |
49. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | REHABILITATION AND UP-GRADATION FROM KM. 0.000 TO KM. 40.390 OF NH-730S (MAHARAJGANJ – NICHLOUL – TH | 3/2023 | 809.25 | 809.25 | 279.77 |
50. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF BASTI RING ROAD (PHASE-I) WITH 4L CONFIGURATION FOR BASTI CITY IN THE STATE OF UTTAR | 12/2022 | 1138.72 | 1138.72 | 263.7 |
51. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT AND UPGRADATION TO TWO LANE WITH PAVED SHOULDER CONFIGURATION FROM EXISTING KM 55.00 TO | 11/2021 | 307.11 | 307.11 | 199.38 |
52. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF NEW 4 LANE PRAYAGRAJ SOUTHERN BYPASS (PHASE-I) FROM DESIGN KM 43+200 (AT MAHUWARI VI | 8/2023 | 1378.36 | 739 | 213.86 |
53. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2LPS OF BIJNOR TO KOTAWALI SECTION OF NH-709AD, PKG-IV | 9/2021 | 300.79 | 300.79 | 122.56 |
54. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4-LANING OF MEERUT NAJIBABAD SECTION FROM KM. 11.500 TO KM 39.250 AND KM 86.590 TO KM. 112.545.IN TH | 10/2019 | 1936.68 | 2458.03 | 1380.9 |
55. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | TWO / FOUR LANING OF RAEBARELI - JAGDISHPUR SECTION OF NH-330A FROM KM. 0.000 TO KM. 47.800 (DESIGN | 10/2020 | 724.6 | 724.6 | 569.96 |
56. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | REHABILITATION and UPGRADATION FROM 2 LANE TO 4 LANE OF NH STRETCH UNDER BHARATMALA PARIYOJANA FOR U | 10/2019 | 1779.83 | 2200 | 1066 |
57. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT AND UP-GRADATION OF EXISTING ROAD TO 2/4L PS FROM KM 40.000 TO 88.750, START OF KHUTAR B | 3/2022 | 762.62 | 838.68 | 571.23 |
58. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF 4 LANE GREEN FIELD NORTHERN EAST SIDE GORAKHPUR BYPASS (26.616 KMS) STARTING FROM NH | 2/2023 | 1973.98 | 1973.98 | 736.14 |
59. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4L FROM GAJU VILLAGE AT KM 32.982 TO DEVINAGAR BYPASS (END) AT KM 208.000 OF NH 530B (PKG 1C) | 12/2021 | 1384.79 | 1384.79 | 657.94 |
60. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L OF AGRA BYPASS (NORTHERN) CONNECTING KM. 174.500 OF NH-2 (NEW NH-19) TO KM. 141.000 OF YAMUNA EXP | 10/2021 | 957.62 | 957.62 | 832.8 |
61. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF FOUR LANE HIGHWAY FORM GHAZIPUR BALLIA UP BIHAR STATE BORDER (GREENFIELD) SECTION OF | 10/2022 | 1706.47 | 1706.47 | 719.13 |
62. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4-LANNING OF HARIDWAR-NAGINA SECTION OF NH 74 FROM (KM 204.300 OF NH 58) TO KM 73.00 | 3/2016 | 1408 | 1659.12 | 1336.33 |
63. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT AND UP-GRADATION OF EXISTING ROAD TO 4L PS FROM KM 123.650 TO 175.080, FROM START OF SHA | 9/2022 | 1212.26 | 1212.26 | 361.81 |
64. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L ACCESS CONTROL GREENFIELD HIGHWAY OF VILL-LOHADDA TO VILL-KARAUNDA MAHAJAN FROM KM. 27.000 TO KM. | 3/2022 | 1335.45 | 1335.45 | 480.89 |
65. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4L SPUR OF SHAMLI-MUZZAFARNAGAR CONNECTING NH-709AD (PANIPAT-SHAMLI-MUZAFFARNAGAR) AND NH-58 (MEERUT | 1/2023 | 391.26 | 391.26 | 14.12 |
66. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | DEVELOPMENT OF SIX-LANE ACCESS CONTROLLED HIGHWAY FROM GOGWAN JALALPUR (SHAMLI DISTRICT) TO RANIPUR | 4/2022 | 1843.59 | 1843.59 | 843.87 |
67. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF LEFT OUT PORTION OF AGRA INNER RING ROAD CONNECTING VILLAGE DEORI TO NH-44 VILLAGE B | 10/2021 | 772.05 | 772.05 | 593.39 |
68. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SPUR OF MEERUT-GARH-MUKTESHWAR SECTION(NH-709A) CONNECTING NH-119 AND NH-58 BYPASSING MEERUT TOWN | 1/2022 | 953.79 | 953.79 | 384.66 |
69. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT AND UP-GRADATION OF EXISTING ROAD TO 4L PS FROM KM 229.070 TO 260.800, END OF HARDOI DIS | 12/2021 | 540.97 | 540.97 | 314.76 |
70. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4L SPUR OF PANIPAT - SHAMLI CONNECTING NH-709AD (PANIPAT – SHAMLI – MUZAFFARNAGAR) AND NH-709A (KARN | 8/2022 | 326.79 | 329.79 | 113.42 |
71. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | KANPUR LUCKNOW EXPRESSWAY PKG-1 CONSTRUCTION OF 6-LANE TO EIGHT LANE OF KANPUR LUCKNOW EXPRESSWAY (N | 12/2021 | 1972.1 | 1936 | 504.87 |
72. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4L FROM MATHURA BYPASS (START) AT EXISTING KM. 154.20 OF NH-44 TO GAJU VILLAGE AT KM 32.982 OF NH-53 | 1/2022 | 1738.2 | 1738.2 | 742.13 |
73. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L ACCESS CONTROL GREENFIELD HIGHWAY OF VILL-KARAUNDA MAHAJAN TO VILL-KHYAWARI FROM KM. 56.500 TO K | 1/2022 | 1159.96 | 1159.96 | 515.8 |
74. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 2-LANE EXISTING RAMPUR BYPASS OF RAMPUR TO BE DEVELOPED TO 4-LANE ON EPC MODE IN THE STATE OF UTTAR | 3/2021 | 364.47 | 364.47 | 209.19 |
75. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | BALANCE WORKS OF 4-LANNING OF RAMPUR-KATHGODAM SECTION OF NH-87 (NEW NH NO. 09) FROM KM. 0.000 (KM 1 | 8/2022 | 199.31 | 244.26 | 190.1 |
76. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4L OF SHAMLI BYAPSS- SAHARANPUR FROM KM 92.2 TO KM 155.025 SECTION OF NH-709B, PKG-II | 5/2019 | 779.17 | 779.17 | 71.39 |
77. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF FOUR LANE HIGHWAY FROM GHAZIPUR BALLIA UP BIHAR STATE BORDER (GREENFIELD) SECTION OF | 10/2022 | 1493.5 | 1493.5 | 492.86 |
78. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | VARANASI RING ROAD (PKG-II) CONNECTING SANDAHA VILLAGE (KM 11.70 / NH-29) WITH REVASA VILLAGE (KM 81 | 2/2019 | 927.77 | 1603 | 1202.77 |
79. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF RING ROAD AROUND KANPUR FROM KM.000 TO KM. 23.325 (CHACHENDI SACHENDI I TO MAHARAJPU | 1/2023 | 1754 | 1754 | 350.78 |
80. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF FOUR-LANE “WESTERN SIDE SPUR OF RAMPUR-RUDRAPUR SECTION CONNECTING NH-24 TO NH-87 BY | 3/2021 | 646.27 | 646.27 | 110.65 |
81. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L ACCESS CONTROLLED GREENFIELD HIGHWAY OF JUNCTION OF EPE (VILL.-MAVIKALAN) TO VILL.-LOHADDA FROM K | 3/2022 | 1602.48 | 1602.48 | 454.77 |
82. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L OF ACCESS-CONTROLLED HIGHWAY FROM MOHAND TO DAAT KALI TUNNEL OF GANESHPUR – DEHRADUN SECTION FROM | 3/2021 | 990.28 | 990.28 | 997.62 |
83. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF NEW 4 LANE PRAYAGRAJ SOUTHERN BYPASS FROM DESIGN KM 50.860 (NABABA URF NIBI KALA UPA | 8/2023 | 993.77 | 349.48 | 372.98 |
84. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4 LANE CONNECTOR FROM DELHI MEERUT EXPRESSWAY KM 50.000 TO KM 8.520 OF NH 235 IN THE STATE OF UTTAR | 8/2021 | 1147.26 | 1147.26 | 172.34 |
85. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | IMPROVEMENT , UP-GRADATION OF NH-734 SECTION OF MORADABAD - THAKURDWARA - KASHIPUR: “PACKAGE-I: MORA | 10/2022 | 1841.92 | 1841.92 | 449.98 |
86. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANING OF HAPUR BYPASS TO MORADABAD SECTION INCLUDING HAPUR BYPASS FROM KM 50.000 (DESIGN CHAINA | 3/2018 | 2140.93 | 2140.93 | 2081.52 |
87. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF FOUR LANE HIGHWAY FROM GHAZIPUR BALLIA UP BIHAR STATE BORDER (GREENFIELD) SECTION OF | 10/2022 | 1493.14 | 1493.14 | 93.3 |
88. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L ACCESS CONTROL GREENFIELD HIGHWAY OF VILL-KHYAWARI TO VILL-LATIFPUR AT SAHARANPUR BYPASS FROM KM | 3/2022 | 1428.19 | 1428.19 | 544.15 |
89. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4LPS OF MUZAFFARNAGAR TO MIRANPUR SECTION OF NH-709AD, PKG-III | 11/2021 | 923.15 | 923.15 | 455.61 |
90. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L GREENFIELD KANPUR - LUCKNOW (EXPRESSWAY) PKG II FROM KM. 28.500 TO KM. 73.744 | 12/2021 | 2470.64 | 2335 | 691.28 |
91. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | FOUR LANING OF SONAULI GORAKHPUR SECTION OF NH 29E (NEW NH 24) FROM DESIGN CH. 0.000 TO DESIGN CH. 7 | 12/2021 | 2555.5 | 2555.5 | 966.89 |
92. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | STRENGTHENING OF EXISTING 4L AYODHYA BYPASS SECTION FROM DESIGN KM.121.600 TO KM. 144.020 OF NH 28 ( | 2/2023 | 526.45 | 526.45 | 228.37 |
93. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | CONSTRUCTION OF FOUR LANE HIGHWAY FROM GHAZIPUR BALLIA UP BIHAR STATE BORDER GREENFIELD SECTION OF N | 10/2022 | 617.87 | 617.88 | 106.2 |
94. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | SIX LANE ACCESS CONTROLLED OF DELHI SAHARANPUR HIGHWAY FROM DELHI UP BORDER TO EPE JUNCTION CH.14.75 | 6/2020 | 2002.79 | 2002.79 | 1989.85 |
95. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | GARHMUKTESHWAR (KM. 83.200 OF NH-24) TO MEERUT (KM. 9.860 OF NH-235) INCLUDING CONNECTOR TO NH-119 | 10/2019 | 2068.99 | 2171 | 209.6 |
96. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 6L ACCESS-CONTROLLED HIGHWAY FROM (GANESHPUR) TO(NEAR MOHAND) OF GANESHPUR – DEHRADUN SECTION FROM K | 3/2021 | 836.24 | 836.24 | 792.55 |
97. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 4 LANING OF NAJIBABAD BYPASS OF NH-119 FROM KM. 105.423 TO KM. 118.373 (EXCLUDING 2.45 KM. OF NH-74 | 2/2022 | 570.98 | 570.98 | 424.98 |
98. | NATIONAL THERMAL POWER CORPORATION | POWER | SINGRAULI SUPER THERMAL POWER PROJECT, STAGE-III (2X800 MW) | 3/2024 | 17195.31 | 17195.31 | 1569.79 |
99. | NEYVELI LIGNITE CORPORATION | COAL | NEYVELI UTTAR PRADESH POWER PROJECT LIMITED 1980 MW | 7/2016 | 17237 | 21780.94 | 19949 |
100. | NORTH CENTRAL RAILWAY | RAILWAYS | JHANSI MANIKPUR AND KHAIRAR BHIMSEN DOUBLING | 3/2018 | 4329.53 | 4329.53 | 2125.66 |
101. | NORTH CENTRAL RAILWAY | RAILWAYS | MATHURA - VRINDAVAN (11 KM) | 8/2022 | 402.88 | 402.88 | 0 |
102. | NORTH CENTRAL RAILWAY | RAILWAYS | ALIGARH-DAUD KHAN - 3RD LINE 6.9 KM AND CONSTRUCTION OF FLYOVER AT DAUD KHAN | 4/2019 | 451.99 | 779.49 | 122.08 |
103. | NORTH CENTRAL RAILWAY | RAILWAYS | ALIGARH-HARDUAGANJ FLYOVER (22 KM) | 4/2020 | 1456.89 | 1456.89 | 10.14 |
104. | NORTH CENTRAL RAILWAY | RAILWAYS | MUGHALSARAI - ALLAHABAD - 3RD LINE | 8/2019 | 2649.44 | 2390 | 83.1 |
105. | NORTH CENTRAL RAILWAY | RAILWAYS | BHANDAI - FLYOVER FOR ETAWAH BOUND DOWN TRAINS | 4/2019 | 187.21 | 250.17 | 1.29 |
106. | NORTH CENTRAL RAILWAY | RAILWAYS | ALLAHABAD-BAMHRAULI - 4TH LINE (10 KM) WITH FLY-OVER AT SUBEDARGANJ | 4/2019 | 494.11 | 494.11 | 42.61 |
107. | NORTH CENTRAL RAILWAY | RAILWAYS | LALITPUR - BIRARI WITH FLYOVER AT LALITPUR | 3/2017 | 356.09 | 356 | 213.97 |
108. | NORTH CENTRAL RAILWAY | RAILWAYS | JHANSI BINA DOUBLING | 9/2016 | 2002 | 2001 | 1745.48 |
109. | NORTH EASTERN RAILWAY | RAILWAYS | BAHRAICH SRAVASTI BALRAMPUR (TULSIPUR) | 10/2018 | 4939.78 | 4939.78 | 1334.98 |
110. | NORTH EASTERN RAILWAY | RAILWAYS | BURHWAL - GONDA - 3RD RUNNING LINE. | 4/2016 | 1015.59 | 1450 | 1277.57 |
111. | NORTH EASTERN RAILWAY | RAILWAYS | SHAHGANJ-BHATNI-PHEPHNA-INDARA, MAU-SHAHGANJ (EXCL. MAU-INDARA) PATCH DOUBLING. | 4/2016 | 1177.96 | 2145 | 2050.16 |
112. | NORTH EASTERN RAILWAY | RAILWAYS | BAHRAICH - NANPARA -NEPALGANJ (56.15 KM) | 7/2020 | 950 | 500 | 424.74 |
113. | NORTH EASTERN RAILWAY | RAILWAYS | DOMINGARH - GORAKHPUR - GORAKHPUR CANTT - KUSUMHI - 3RD RUNNING LINE (21.15 KM) | 11/2016 | 351.03 | 500.37 | 494.01 |
114. | NORTH EASTERN RAILWAY | RAILWAYS | SAHJANWA - DOHRIGHAT | 8/2019 | 371.77 | 1319.75 | 577.85 |
115. | NORTHERN COAL FIELDS LIMITED | COAL | KHADIA EXPANSION OCP | 6/2021 | 491.67 | 491.67 | 202.24 |
116. | NORTHERN RAILWAY | RAILWAYS | JANGHAI PRATAPGARH AMETHI DOUBLING | 11/2017 | 721.72 | 1100 | 58.98 |
117. | NORTHERN RAILWAY | RAILWAYS | BARABANKI MALHAUR 3RD AND 4TH LINE (32.84 KM) | 1/2019 | 323.85 | 407 | 18.91 |
118. | NORTHERN RAILWAY | RAILWAYS | DOUBLING BETWEEN JAUNPUR JN-ZAFFARABAD (6.28 KM) | 3/2023 | 177.33 | 177.33 | .89 |
119. | POWER GRID CORPORATION OF INDIA LIMITED | POWER | TRANSMISSION SYSTEM FOR EVACUATION OF POWER FROM RAJASTHAN REZ PH-IV (PART-4: 3.5 GW): PART A | 12/2024 | 5846 | 5846 | 198.76 |
120. | POWER GRID CORPORATION OF INDIA LIMITED | POWER | TRANSMISSION SYSTEM FOR STRENGTHENING TO FACILITATE EVACUATION OF POWER FROM BHADLA/BIKANER COMPLEX | 12/2024 | 213 | 213 | 0 |
121. | RAIL VIKAS NIGAM LTD. | RAILWAYS | JANGHAI-PHAPHAMAU - DOUBLING WITH ELECTRIFICATION (46.79 KM) | 11/2018 | 357.48 | 409.38 | 362.09 |
122. | RAIL VIKAS NIGAM LTD. | RAILWAYS | BHATNI - AUNRIHAR WITH ELECTRIFICATION (125 KM) (EXCL INDARA - MAU (116.95 KM)) | 5/2018 | 2529.46 | 2529.46 | 1636.33 |
123. | RAIL VIKAS NIGAM LTD. | RAILWAYS | MATHURA-JHANSI-3RD LINE (273.80 KM) | 6/2016 | 5323.39 | 5190.26 | 5046.07 |
124. | THDC INDIA LIMITED | POWER | KHURJA SUPER THERMAL POWER PROJECT | 3/2019 | 11089.42 | 13276.16 | 12580.53 |
125. | Uttar Pradesh Jal Nigam | WATER RESOURCES | INTERCEPTION AND DIVERSION WORKS AND STP AT MUZAFFARNAGAR UTTAR PRADESH | 1/2019 | 231.79 | 234.03 | 141.79 |
126. | Uttar Pradesh Jal Nigam | WATER RESOURCES | SEWERAGE SCHEME INTERCEPTION AND DIVERSION WITH STP WORKS AT MEERUT UTTAR PRADESH | 2/2019 | 681.78 | 690.71 | 13.34 |
| Total | 126 | |