S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | CONSTRUCTION OF DOMESTIC PASSENGER TERMINAL BUILDING AT DEHRADUN AIRPORT, DEHRADUN | AIRPORT AUTHORITY OF INDIA LIMITED | CIVIL AVIATION | 456.86 | 07/2018 | 09/2020 | 04/2024 | 43 |
2. | TEHRI PUMPED STORAGE PLANT(1000MW) | THDC INDIA LIMITED | POWER | 1657 | 07/2006 | 02/2016 | 10/2024 | 104 |
3. | TAPOVAN-VISHNUGAD HEP (4X130MW) | NATIONAL THERMAL POWER CORPORATION | POWER | 2978.48 | 11/2006 | 03/2013 | 04/2029 | 193 |
4. | VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECT | THDC INDIA LIMITED | POWER | 2491.58 | 08/2008 | 06/2013 | 06/2026 | 156 |
5. | RISHIKESH - KARNAPRAYAG NEW LINE | RAIL VIKAS NIGAM LTD. | RAILWAYS | 16216 | 04/2011 | 12/2024 | 03/2025 | 3 |
6. | FOUR LANNING OF RAMPUR- KATHGODAM SECTION OF NH-87 FROM KM 42.791 (DESIGN CHAINAGE 43.446) TO KM 88 | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 720 | 03/2016 | 10/2019 | 04/2024 | 54 |
7. | CONSTRUCTION AND UPGRADATION OF EXISTING ROAD TO 2 LANE WITH PAVED SHOULDER FROM KM 368.00 TO KM 399 | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 274.31 | 03/2018 | 11/2020 | 03/2024 | 40 |
8. | 2 LANE WITH PAVED SHOULDER FROM KM 399.00 TO KM 430.00 OF KARANPARYAG TO CHAMOLI UNDER CHARDHAM PARI | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 403.36 | 03/2018 | 11/2020 | 04/2024 | 41 |
9. | 2 LANE WITH PAVED SHOULDER FROM KM 430.00 TO KM 468.00 OF CHAMOLI TO PAINI UNDER CHARDHAM PARIYOJNA | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 417.24 | 03/2018 | 11/2020 | 03/2024 | 40 |
10. | CONSTRUCTION OF 4.5 KM LONG SILKYARA TUNNEL BETWEEN KM 25.40 TO 50.25 KM (TUNNEL WORK) | NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION Ltd. | ROAD TRANSPORT AND HIGHWAYS | 1383.78 | 03/2018 | 07/2022 | 03/2025 | 32 |
11. | 6L ACCESS-CONTROLLED HIGHWAY OF DAAT KALI TUNNEL - DEHRADUN OF GANESHPUR – DEHRADUN SECTION FROM KM. | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 169.08 | 03/2021 | 03/2024 | 04/2024 | 1 |
| Total | 11 | |