S No. | Sector | Agency | Date Of Approval | Cost Original | Cost Overrun |
1. | COAL | EASTERN COAL FIELDS LIMITED | 08/2009 | 2661.73 | 2484.75 |
2. | COAL | BHARAT COKING COAL LIMITED | 12/2015 | 304.13 | 37.09 |
3. | HOME AFFAIRS | CPWD FOR MHA | 10/2014 | 162.88 | 47.95 |
4. | PETROLEUM | GAS AUTHORITY OF INDIA LIMITED | 03/2017 | 1740 | 693.15 |
5. | POWER | NATIONAL THERMAL POWER CORPORATION | 09/2014 | 1381.84 | 421.16 |
6. | POWER | NATIONAL THERMAL POWER CORPORATION | 12/2016 | 529.68 | 149.32 |
7. | RAILWAYS | EASTERN RAILWAYS | 04/2000 | 1188.91 | 430.6 |
8. | RAILWAYS | SOUTH EASTERN RAILWAY | 04/2018 | 338 | 55.83 |
9. | RAILWAYS | RAIL VIKAS NIGAM LTD. | 04/2010 | 2913.51 | 1921.03 |
10. | RAILWAYS | METROPOLITAN RAPID TRANSPORT PROJECTS | 03/2013 | 4874.58 | 5567.83 |
11. | RAILWAYS | KOLKATA METRO RAIL CORPORATION LIMITED | 02/2009 | 4874.58 | 5567.83 |
12. | RAILWAYS | RAIL VIKAS NIGAM LTD. | 04/2010 | 2298.42 | 435.44 |
13. | RAILWAYS | RAIL VIKAS NIGAM LTD. | 04/2010 | 3951.98 | 5012.37 |
14. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 03/2018 | 841.57 | 777.91 |
15. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 06/2016 | 236.78 | 26.48 |
16. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 03/2016 | 160.27 | 53.7 |
17. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 03/2020 | 2193.23 | 120.77 |
18. | ROAD TRANSPORT AND HIGHWAYS | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | 03/2016 | 271.17 | 20.03 |
19. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 12/2015 | 1083 | 331.01 |
20. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 12/2018 | 2375.87 | 190.93 |
21. | ROAD TRANSPORT AND HIGHWAYS | NATIONAL HIGHWAYS AUTHORITY OF INDIA | 04/2014 | 1665 | 695.65 |
22. | WATER RESOURCES | Kolkata Metropolitan Development Authority | 08/2017 | 307.12 | 346.55 |
23. | WATER RESOURCES | Kolkata Metropolitan Development Authority | 05/2018 | 198.43 | 26.26 |
| Total | 23 | |