S No. | Project Title | Agency Name | Sector Name | Cost Original | Date Of Approval | DOC Original | DOC Anticipated | Time Overrun(in months) |
1. | RANIGANJ MASTER PLAN | EASTERN COAL FIELDS LIMITED | COAL | 2661.73 | 08/2009 | 08/2019 | 08/2024 | 60 |
2. | 2.0 MTPA BHOJUDIH NLW WASHERY | BHARAT COKING COAL LIMITED | COAL | 304.13 | 12/2015 | 03/2017 | 06/2024 | 87 |
3. | CONSTRUCTION OF TWO NOS GIRLS HOSTELS AND ONE NO BOYS HOSTEL OF 500 CAPACITY EACH G PLUS 8 STOREYED | CPWD OF HIGHER EDUCATION | DEPARTMENT OF HIGHER EDUCATION | 193.83 | 03/2020 | 06/2020 | 03/2024 | 45 |
4. | NSG AT KOLKATA | CPWD FOR MHA | HOME AFFAIRS | 162.88 | 10/2014 | 04/2018 | 12/2024 | 80 |
5. | CONSTRUCTION OF BASEMENTG FLOOR10 STORIES BUILDING FOR THE STATE OF THE ART, DG, GSI AT SECTOR-V, SA | CENTRAL PUBLIC WORKS DEPARTMENT | MINES | 255.37 | 04/2019 | 04/2022 | 03/2026 | 47 |
6. | DURGAPUR-HALDIA PIPELINE PROJECT | GAS AUTHORITY OF INDIA LIMITED | PETROLEUM | 1740 | 03/2017 | 12/2020 | 06/2024 | 42 |
7. | 30 INCH CRUDE OIL PIPELINE IN HALDIA-BARAUNI SECTION OF PHBPL AND CONVERSION OF EXISTING 18 INCH HAL | INDIAN OIL CORPORATION LIMITED | PETROLEUM | 3712 | 03/2018 | 09/2022 | 03/2024 | 18 |
8. | RAMMAM-III HEPP (3X40 MW) | NATIONAL THERMAL POWER CORPORATION | POWER | 1381.84 | 09/2014 | 09/2019 | 03/2029 | 114 |
9. | DURGAPUR PP-III (2X20 MW) - NSPCL | NATIONAL THERMAL POWER CORPORATION | POWER | 529.68 | 12/2016 | 11/2018 | 03/2024 | 64 |
10. | TARAKESWAR - BISHNUPUR NEW BG LINE (NL), ER | EASTERN RAILWAYS | RAILWAYS | 1188.91 | 04/2000 | 03/2019 | 03/2025 | 72 |
11. | NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM BARANAGAR TO BARRACKPORE AND DAKSHINESHWAR (MTP) | RAIL VIKAS NIGAM LTD. | RAILWAYS | 2298.42 | 04/2010 | 03/2014 | 12/2025 | 141 |
12. | NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NSCB AIRPORT TO NEW GARIA VIA RAJARHAT (MTP) | RAIL VIKAS NIGAM LTD. | RAILWAYS | 3951.98 | 04/2010 | 03/2016 | 03/2026 | 120 |
13. | NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM JOKA TO BINOY BADAL DINESH BAGH. | RAIL VIKAS NIGAM LTD. | RAILWAYS | 2913.51 | 04/2010 | 03/2016 | 12/2026 | 129 |
14. | PURULIA TO KOTSHILA DOUBLING (39.1 KM) | SOUTH EASTERN RAILWAY | RAILWAYS | 338 | 04/2018 | 06/2022 | 12/2024 | 30 |
15. | NAHATI - RANAGHAT 3RD LINE (MM OF KALINARAYANPUR - KRISHNANAGAR) | EASTERN RAILWAYS | RAILWAYS | 283.54 | 07/2015 | 03/2025 | 03/2026 | 12 |
16. | EAST WEST METRO CORRIDOR KOLKATA | KOLKATA METRO RAIL CORPORATION LIMITED | RAILWAYS | 4874.58 | 02/2009 | 09/2016 | 06/2024 | 93 |
17. | SIX-LANING OF BARWA ADDA-PANAGARH | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 1665 | 04/2014 | 09/2016 | 05/2024 | 92 |
18. | REHABILITATION AND UP GRADATION OF EXISTING ROAD TO 2-LANE WITH PAVED SHOULDER CONFIGURATION IN PURU | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 841.57 | 03/2018 | 09/2022 | 09/2024 | 24 |
19. | CONSTRUCTION OF NEW ROAD AT THE MISSING LINK PORTION OF NH-81 ALONG THE APPROVED ALIGNMENT BETWEEN H | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 271.17 | 03/2016 | 11/2018 | 05/2024 | 66 |
20. | UPGRADATION OF NH-81 WITH A MINIMUM OF 2-LANE WITH PAVED SHOULDER CONFIGURATION STARTING FROM KM 19. | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 426.18 | 02/2018 | 09/2020 | 03/2024 | 42 |
21. | DEVELOPMENT OF 4-LANING SECTION OF NH-31 FROM KM 551.36 (GHOSHPUKUR) TO KM 563.26 (BIHAR MORE, BAGDO | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 254.3 | 03/2018 | 10/2020 | 03/2024 | 41 |
22. | CONSTRUCTION OF ROB AND ITS APPROACHES IN LIEU OF UNMANNED LEVEL CROSSING AT KM 303.9 ON NH-60 (PAND | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 160.27 | 03/2016 | 09/2023 | 03/2024 | 6 |
23. | CONSTRUCTION OF TWINS 2-LANE ROB AND ITS APPROACHES IN REPLACEMENT OF EXISTING LEVEL CROSSING GATE N | MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (STATE PWDs) | ROAD TRANSPORT AND HIGHWAYS | 236.78 | 06/2016 | 09/2021 | 03/2024 | 30 |
24. | FOUR LANING OF PURULIYA BYPASS SECTION OF NH 32 IN THE STATE OF WEST BENGAL ON EPC MODE | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 557.55 | 08/2021 | 08/2023 | 05/2024 | 9 |
25. | CONSTRUCTION OF NEW 4 LANE BRIDGE OVER RIVER GANGA AT DOWNSTREAM OF FARAKKA BARRAGE INCLUDING APPROA | NATIONAL HIGHWAYS AUTHORITY OF INDIA | ROAD TRANSPORT AND HIGHWAYS | 622.04 | 08/2018 | 12/2021 | 12/2024 | 36 |
26. | DETAILED PROJECT REPORT FOR I AND D SEWERAGE SYSTEM AND STP FOR ASANSOL AND KULTI TOWNS | Kolkata Metropolitan Development Authority | WATER RESOURCES | 384.96 | 01/2019 | 04/2022 | 12/2024 | 32 |
27. | INTERCEPTION AND DIVERSION WORKS WITH STP FOR DRAINS FALLING IN RIVER DAMODAR AT DURGAPURL | Kolkata Metropolitan Development Authority | WATER RESOURCES | 287.53 | 03/2019 | 04/2022 | 12/2024 | 32 |
28. | I AND D AND STP WORKS AT BURDWAN WEST BENGAL | Kolkata Metropolitan Development Authority | WATER RESOURCES | 234.31 | 12/2018 | 04/2022 | 12/2024 | 32 |
29. | INTERCEPTION AND DIVERSION WITH STP AT MAHESHTALA | Kolkata Metropolitan Development Authority | WATER RESOURCES | 198.43 | 05/2018 | 02/2022 | 03/2024 | 25 |
30. | INTEGRATION OF STPS WITH REHABILITATION AND O AND M OF EXISTING ASSETS | Kolkata Metropolitan Development Authority | WATER RESOURCES | 165.16 | 03/2018 | 06/2022 | 03/2024 | 21 |
31. | INTERCEPTION DIVERSION TREATMENT WORKS AT TOLLYS NULLAH ADI GANGA | Kolkata Metropolitan Development Authority | WATER RESOURCES | 307.12 | 08/2017 | 09/2022 | 12/2026 | 51 |
32. | INTERCEPTION AND DIVERSION WITH STP AT HUGHLY-CHINSURAH | Kolkata Metropolitan Development Authority | WATER RESOURCES | 160 | 05/2018 | 02/2022 | 06/2024 | 28 |
| Total | 32 | |