Milestone Summary For Project | |||||||||||||
Sector Name : | RAILWAYS. | ||||||||||||
Agency Name : | WEST CENTRAL RAILWAY. | ||||||||||||
Project Name : | LALITPUR-SATNA-REWA-SINGRULI NL, (NCR). |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
MK | MAWAI-KHAJURAHO (100 KM) | 0 | 4/2004 | 1/2017 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | WCR Construction Organisation |