Milestone Summary For Project | |||||||||||||
Sector Name : | RAILWAYS. | ||||||||||||
Agency Name : | WEST CENTRAL RAILWAY. | ||||||||||||
Project Name : | RAMGANJMUNDI-BHOPAL (NL),WCR. |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
RB3b | Junakheda Aklera | 0 | 12/2015 | 3/2022 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB4a | Aklera - Ghatoli | 0 | 12/2015 | 3/2023 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB4b | Ghatoli- Nayagaon | 0 | 12/2015 | 3/2024 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB4c | Nayagaon - Rajgarh | 0 | 12/2019 | 3/2024 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB5a | Nishatpura - Sant Hirdaram Nagar | 0 | 12/2019 | 3/2023 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB5b | Rajgarh - Biyavara | 0 | 4/2020 | 2/2024 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB5c | Biyarajgarh - Sonkacch | 0 | 10/2020 | 3/2024 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB5d | Sonkach - Narsinghgarh | 0 | 10/2020 | 3/2023 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB6a | Narsingh garh - Kurawar | 0 | 1/2021 | 3/2024 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB6b | Kurawar - Shampur | 0 | 2/2021 | 3/2024 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB6c | Jharkhera - Sant Hirdaram Nagar | 0 | 3/2021 | 3/2023 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No |