Milestone Summary For Project
Sector Name : ATOMIC ENERGY.
Agency Name : NUCLEAR POWER CORPORATION OF INDIA LIMITED.
Project Name : KAKRAPAR ATOMIC POWER PROJECT - 3 AND 4.

Milestone

CodeMilestoneCost Associated with Milestones in (INR)Original Start (mm/yyyy)Original End (mm/yyyy)Revised Start (mm/yyyy)Revised End (mm/yyyy)Actual Completion (mm/yyyy)MOU StatusMOU Traget (mm/yyyy)% AchievedStatusCriticalRemarks
K3-01Receipt of administrative and Financial Sanction from Government of India0/10/20090/00/00/0No/100CompletedYesNPCIL
K3-02Award of Main Plant Civil Contract0/12/20090/00/00/0No/100CompletedYes
K3-03Start Excavation (Ground Break)0/1/20100/00/00/0No/100CompletedYes
K3-04First Pour of Concrete (Zero Date)0/11/20100/00/00/0No/100CompletedYes
K3-05Placement of Purchase Order for Nuclear Piping Package04/20115/20110/00/00/0No/100CompletedYes
K3-06Completion of NB-3 Raft0/10/20110/00/00/0No/100CompletedYes
K3-07Placement of PO for Common Service Piping Package0/7/20110/00/00/0No/100CompletedNo
K3-08Placement of PO for electrical system main plant package0/9/20110/00/00/0No/100CompletedNo
K3-09Placement of PO for C and I field Instrumentation Package0/12/20110/00/00/0No/100CompletedNo
K3-10Completion of RB-3 100m slab0/3/20120/00/00/0No/100CompletedYes
K3-11Delivery of Calandria0/7/20120/00/00/0No/100CompletedYes
K3-12Delivery of End shields0/9/20120/00/00/0No/100CompletedNo
K3-13Release Calandria Vault for End Shield erection0/9/20120/00/00/0No/100CompletedYes
K3-14Delivery of Calandria Tubes to Site0/4/20130/00/00/0No/100CompletedYes
K3-15Completion of erection and welding of End Shields and Calandria012/20125/20130/00/00/0No/100CompletedYes
K3-16Delivery of Coolant Tubes to site0/6/20130/00/00/0No/100CompletedYes
K3-17Delivery of FM bridge and Columns06/20106/20130/00/00/0No/100CompletedNo
K3-18Completion of Calandria tube Installation05/20137/20130/00/00/0No/100CompletedYes
K3-19Release of CB 111M for Control and Instrumentation works0/8/20130/00/00/0No/100CompletedNo
K3-20Delivery of PCP pumps0/9/20130/00/00/0No/100CompletedYes
K3-21Delivery of Steam Generators04/201310/20130/00/00/0No/CompletedYesNPCIL
K3-22Completion of Coolant Channel Installation0/11/20130/00/00/0Yes3/20160CompletedNo
K3-23Release SG Vaults for steam generator erection012/201211/20130/00/00/0No/100CompletedNo
K3-24Erection of FM bridge and Columns0/1/20140/00/00/0No/100CompletedYes
K3-25Erection of all Steam Generators01/20144/20140/00/00/0No12/2015CompletedYesNPCIL
K3-26Delivery of Turbine Generator01/20145/20140/00/00/0No/100CompletedNo
K3-27Charge Start Up Transformer04/20145/20140/00/00/0Yes3/2016100CompletedNo
K3-28IC Dome Completion01/20145/20140/00/00/0No/100CompletedYes
K3-29Delivery of Diesel Generators0/6/20140/00/00/0No/100CompletedNo
K3-30Commissioning of Plant water pump house05/20146/20140/00/00/0No/0CompletedYes
K3-31Completed erection of feeders02/20147/20140/00/00/0No/100CompletedYes
K3-32Commission DM Plant09/201410/20140/00/00/0No/100CompletedYesNPCIL
K3-33Commission Compressors010/201411/20140/00/00/0No/100CompletedYes
K3-34Delivery of PCP motors0/6/20150/00/00/0No/0CompletedNo
K3-35Completion of Hydro test of PHT System06/20156/20150/00/00/0No/0CompletedYes
K3-36Completion of Hot Conditioning09/20159/20150/00/00/0No/100CompletedYes
K3-37Fuel Loading09/201510/20150/00/00/0No/0CompletedYes
K3-38Achieve first criticality of KAPP-3011/201511/20150/00/00/0No/0CompletedYes
K3-391st Synchronisation of KAPP-301/20161/20160/00/00/0No/100CompletedYes
K3-40Commencement of commercial Operation of KAPP-305/20165/20160/00/00/0No/100CompletedYes
K4-01First pour of Concrete0/5/20110/00/00/0No/100CompletedYes
K4-02Completion of NB-4 Raft0/2/20120/00/00/0No/100CompletedYes
K4-03Completion of RB-4 100m slab0/9/20120/00/00/0No/100CompletedYes
K4-04Delivery of Calandria0/1/20130/00/00/0No/100CompletedYes
K4-05Delivery of End shields03/20102/20130/00/00/0No/100CompletedNo
K4-06Release Calandria Vault for end shield erection0/3/20130/00/00/0No/100CompletedYes
K4-07Delivery of calandria Tubes to site0/10/20130/00/00/0No/100CompletedYes
K4-08Completion of erection and welding of End shields and calandria0/11/20130/00/00/0No/0CompletedNo
K4-09Delivery of FM bridge and Columns0/12/20130/00/00/0No/100CompletedNo
K4-10Delivery of coolant Tubes to site0/12/20130/00/00/0No/100CompletedNo
K4-11Completion of Calandria tube installation012/20131/20140/00/00/0No/100CompletedYes
K4-11Completion of Calandria tube installation0/1/20140/00/00/0No/0CompletedYes
K4-12Delivery of PCP pumps0/3/20140/00/00/0No/100CompletedNo
K4-13Delivery of Steam Generators010/20134/20140/00/00/0No/100CompletedYes
K4-14Completion of Coolant Channel Installation01/20145/20140/00/00/0No/100CompletedYes
K4-15Release SG vaults for steam generator erection06/20135/20140/00/00/0No/100CompletedYes
K4-16Erection of FM bridge and columns05/20147/20140/00/00/0No/100CompletedYes
K4-17Delivery of boiler feed pumps to site04/20148/20140/00/00/0No/100CompletedYesNPCIL
K4-18Erection of all steam generators07/201410/20140/00/00/0No/100CompletedYes
K4-19Charge Start Up transformer010/201411/20140/00/00/0No/100CompletedYes
K4-20IC Dome Completion 07/201411/20140/00/00/0No/100CompletedYes
K4-21Delivery of Diesel Generators08/201412/20140/00/00/0No/100CompletedNo
K4-22Completion of erection of feeders08/20141/20150/00/00/0No/100CompletedYes
K4-23Delivery of shut down cooling pumps to site0/6/20150/00/00/0No/100CompletedNo
K4-24Delivery of PCP motors011/201512/20150/00/00/0No/100CompletedYesNPCIL
K4-25Completion of Hydro test of PHT system012/201512/20150/00/00/0No/100CompletedYes
K4-26Completion of Hot Conditioning03/20163/20160/00/00/0No/100CompletedYes
K4-27Fuel Loading04/20164/20160/00/00/0No/100CompletedYes
K4-27Fuel Loading0/4/20160/00/00/0No/0CompletedYes
K4-28Achieve first Criticality of KAPP-405/20165/20160/00/00/0No/100CompletedYes
K4-291st Synchronisation of KAPP-407/20167/20160/00/00/0No/100CompletedYes
K4-30Commencement of Commercial Operation of KAPP-4011/201611/20160/00/00/0No/100CompletedYes

  Back