Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
K3-01 | Receipt of administrative and Financial Sanction from Government of India | 0 | / | 10/2009 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | NPCIL |
K3-02 | Award of Main Plant Civil Contract | 0 | / | 12/2009 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-03 | Start Excavation (Ground Break) | 0 | / | 1/2010 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-04 | First Pour of Concrete (Zero Date) | 0 | / | 11/2010 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-05 | Placement of Purchase Order for Nuclear Piping Package | 0 | 4/2011 | 5/2011 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-06 | Completion of NB-3 Raft | 0 | / | 10/2011 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-07 | Placement of PO for Common Service Piping Package | 0 | / | 7/2011 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K3-08 | Placement of PO for electrical system main plant package | 0 | / | 9/2011 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K3-09 | Placement of PO for C and I field Instrumentation Package | 0 | / | 12/2011 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K3-10 | Completion of RB-3 100m slab | 0 | / | 3/2012 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-11 | Delivery of Calandria | 0 | / | 7/2012 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-12 | Delivery of End shields | 0 | / | 9/2012 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K3-13 | Release Calandria Vault for End Shield erection | 0 | / | 9/2012 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-14 | Delivery of Calandria Tubes to Site | 0 | / | 4/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-15 | Completion of erection and welding of End Shields and Calandria | 0 | 12/2012 | 5/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-16 | Delivery of Coolant Tubes to site | 0 | / | 6/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-17 | Delivery of FM bridge and Columns | 0 | 6/2010 | 6/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K3-18 | Completion of Calandria tube Installation | 0 | 5/2013 | 7/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-19 | Release of CB 111M for Control and Instrumentation works | 0 | / | 8/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K3-20 | Delivery of PCP pumps | 0 | / | 9/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-21 | Delivery of Steam Generators | 0 | 4/2013 | 10/2013 | 0/0 | 0/0 | 0/0 | No | / | | Completed | Yes | NPCIL |
K3-22 | Completion of Coolant Channel Installation | 0 | / | 11/2013 | 0/0 | 0/0 | 0/0 | Yes | 3/2016 | 0 | Completed | No | |
K3-23 | Release SG Vaults for steam generator erection | 0 | 12/2012 | 11/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K3-24 | Erection of FM bridge and Columns | 0 | / | 1/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-25 | Erection of all Steam Generators | 0 | 1/2014 | 4/2014 | 0/0 | 0/0 | 0/0 | No | 12/2015 | | Completed | Yes | NPCIL |
K3-26 | Delivery of Turbine Generator | 0 | 1/2014 | 5/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K3-27 | Charge Start Up Transformer | 0 | 4/2014 | 5/2014 | 0/0 | 0/0 | 0/0 | Yes | 3/2016 | 100 | Completed | No | |
K3-28 | IC Dome Completion | 0 | 1/2014 | 5/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-29 | Delivery of Diesel Generators | 0 | / | 6/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K3-30 | Commissioning of Plant water pump house | 0 | 5/2014 | 6/2014 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
K3-31 | Completed erection of feeders | 0 | 2/2014 | 7/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-32 | Commission DM Plant | 0 | 9/2014 | 10/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | NPCIL |
K3-33 | Commission Compressors | 0 | 10/2014 | 11/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-34 | Delivery of PCP motors | 0 | / | 6/2015 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
K3-35 | Completion of Hydro test of PHT System | 0 | 6/2015 | 6/2015 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
K3-36 | Completion of Hot Conditioning | 0 | 9/2015 | 9/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-37 | Fuel Loading | 0 | 9/2015 | 10/2015 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
K3-38 | Achieve first criticality of KAPP-3 | 0 | 11/2015 | 11/2015 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
K3-39 | 1st Synchronisation of KAPP-3 | 0 | 1/2016 | 1/2016 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K3-40 | Commencement of commercial Operation of KAPP-3 | 0 | 5/2016 | 5/2016 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-01 | First pour of Concrete | 0 | / | 5/2011 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-02 | Completion of NB-4 Raft | 0 | / | 2/2012 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-03 | Completion of RB-4 100m slab | 0 | / | 9/2012 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-04 | Delivery of Calandria | 0 | / | 1/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-05 | Delivery of End shields | 0 | 3/2010 | 2/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K4-06 | Release Calandria Vault for end shield erection | 0 | / | 3/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-07 | Delivery of calandria Tubes to site | 0 | / | 10/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-08 | Completion of erection and welding of End shields and calandria | 0 | / | 11/2013 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
K4-09 | Delivery of FM bridge and Columns | 0 | / | 12/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K4-10 | Delivery of coolant Tubes to site | 0 | / | 12/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K4-11 | Completion of Calandria tube installation | 0 | 12/2013 | 1/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-11 | Completion of Calandria tube installation | 0 | / | 1/2014 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
K4-12 | Delivery of PCP pumps | 0 | / | 3/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K4-13 | Delivery of Steam Generators | 0 | 10/2013 | 4/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-14 | Completion of Coolant Channel Installation | 0 | 1/2014 | 5/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-15 | Release SG vaults for steam generator erection | 0 | 6/2013 | 5/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-16 | Erection of FM bridge and columns | 0 | 5/2014 | 7/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-17 | Delivery of boiler feed pumps to site | 0 | 4/2014 | 8/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | NPCIL |
K4-18 | Erection of all steam generators | 0 | 7/2014 | 10/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-19 | Charge Start Up transformer | 0 | 10/2014 | 11/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-20 | IC Dome Completion | 0 | 7/2014 | 11/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-21 | Delivery of Diesel Generators | 0 | 8/2014 | 12/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K4-22 | Completion of erection of feeders | 0 | 8/2014 | 1/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-23 | Delivery of shut down cooling pumps to site | 0 | / | 6/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
K4-24 | Delivery of PCP motors | 0 | 11/2015 | 12/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | NPCIL |
K4-25 | Completion of Hydro test of PHT system | 0 | 12/2015 | 12/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-26 | Completion of Hot Conditioning | 0 | 3/2016 | 3/2016 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-27 | Fuel Loading | 0 | 4/2016 | 4/2016 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-27 | Fuel Loading | 0 | / | 4/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
K4-28 | Achieve first Criticality of KAPP-4 | 0 | 5/2016 | 5/2016 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-29 | 1st Synchronisation of KAPP-4 | 0 | 7/2016 | 7/2016 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
K4-30 | Commencement of Commercial Operation of KAPP-4 | 0 | 11/2016 | 11/2016 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |