Milestone Summary For Project
Sector Name : ATOMIC ENERGY.
Agency Name : NUCLEAR POWER CORPORATION OF INDIA LIMITED.
Project Name : RAJASTHAN ATOMIC POWER PROJECT -7 AND 8 (2X700 MW).

Milestone

CodeMilestoneCost Associated with Milestones in (INR)Original Start (mm/yyyy)Original End (mm/yyyy)Revised Start (mm/yyyy)Revised End (mm/yyyy)Actual Completion (mm/yyyy)MOU StatusMOU Traget (mm/yyyy)% AchievedStatusCriticalRemarks
R7-01First Pour of Concrete (zero date)0/7/20110/00/00/0No/0CompletedYes
R7-02Placement of PO for Common Service Piping Package0/7/20110/00/00/0No/0CompletedNo
R7-03Placement of PO for Electrical System Main Plant Package0/8/20110/00/00/0No/0CompletedNo
R7-04Placement of Work Order for Plant water Package0/3/20120/00/00/0No/0CompletedNo
R7-05Completion of NB-7 Raft0/4/20120/00/00/0No/0CompletedYes
R7-06Placement of Work Order for NDCT Package0/6/20120/00/00/0No/0CompletedNo
R7-07Placement of Work Order for IDCT Package0/8/20120/00/00/0No/100CompletedNo
R7-08Completion of RB-7 100m slab06/201210/20120/00/00/0No/0CompletedNo
R7-09Delivery of End Calandria0/6/20130/00/00/0No/0CompletedYes
R7-10Delivery of End shields03/20106/20130/00/00/0No/0CompletedYes
R7-11Release Calandria Vault for End Shield erection0/6/20130/00/00/0No/0CompletedYes
R7-12Delivery of PCP pumps0/12/20130/00/00/0No/100CompletedYes
R7-13Delivery of Calandria Tubes of site0/1/20140/00/00/0No/0CompletedYes
R7-14Delivery of Coolant Tubes to site010/20112/20120/00/00/0No/0CompletedNo
R7-15Completion of erection and wedding of End shields and calandria01/20143/20140/00/00/0Yes7/2015100CompletedYes
R7-16Completion of Calandria tube installation0/5/20140/00/00/0Yes11/20150CompletedNo
R7-17Delivery of PCP motors01/20146/20140/00/00/0No/0CompletedNo
R7-18Release of CB 111M for Control and Instrumentation works0/7/20140/00/00/0No/0CompletedYes
R7-19Delivery of Steam Generators01/20147/20140/00/00/0No/100CompletedYes
R7-20Release SG vaults for steam Generator erection08/20137/20140/00/00/0No/100CompletedYes
R7-21Delivery of FM bridge and columns09/20109/20140/00/00/0No/0CompletedNo
R7-22Completion of coolant channel installation05/20149/20140/00/00/0No/100CompletedYes
R7-23Erection of all steam generators07/201410/20140/00/00/0No/100CompletedYes
R7-24Erection of FM bridge and columns09/201411/20140/00/00/0No/100CompletedYes
R7-25Charge Start up transformer010/201411/20140/00/00/0No/100CompletedYes
R7-26Delivery of diesel generators08/201411/20140/00/00/0No/0CompletedNo
R7-27Delivery of Turbine Generator08/201412/20140/00/00/0No/100CompletedYes
R7-28-DCommissioning of plant water pump house011/201412/20140/00/00/0No/0CompletedYes
R7-29IC Dome completion RB-709/20141/20150/00/00/0No/100CompletedYes
R7-30Commision DM Plant03/20154/20150/00/00/0No/100CompletedYes
R7-31Complete erection of feeders012/20145/20150/00/00/0No/100CompletedYes
R7-32Commission Compressors07/20158/20150/00/00/0No/0CompletedYes
R7-33Completion of Hydro test of PHT system02/20162/20160/00/00/0No/100CompletedYes
R7-34Completion of Hot Conditioning05/20165/20160/00/00/0No/100CompletedYes
R8-01First pour of concrete 0/9/20110/00/00/0No/0CompletedYes
R8-02Completion of NB-8 Raft0/6/20120/00/00/0No/0CompletedYes
R8-03Completion of RB-8 100M slab0/12/20120/00/00/0No/100CompletedNo
R8-04Delivery of Calandria0/8/20130/00/00/0No/100CompletedYes
R8-05Delivery of end shields0/8/20130/00/00/0No/0CompletedNo
R8-06Release Calandria vault for end shield erection02/20139/20130/00/00/0No/0CompletedYes
R8-07Delivery of PCP pumps06/20102/20140/00/00/0No/0CompletedNo
R8-08Delivery of Calandria tubes to site0/3/20140/00/00/0No/0CompletedYes
R8-09Delivery of Coolant tubes to site010/20134/20140/00/00/0No/100CompletedYes
R8-10Completion of erection and welding of end shields and calandria02/20145/20140/00/00/0No/0CompletedYes
R8-11Completion of calandria tube installation05/20147/20140/00/00/0No/100CompletedYes
R8-12Delivery of PCP motors03/20148/20140/00/00/0No/100CompletedYes
R8-13Delivery of Steam generators03/20149/20140/00/00/0No/100CompletedYes
R8-14Release SG vaults for steam generator erection010/20139/20140/00/00/0No/100CompletedYes
R8-15Delivery of FM bridge and Columns0/11/20140/00/00/0No/0CompletedYes
R8-16Completion of coolant channel installation07/201411/20140/00/00/0No/100CompletedYes
R8-17Erection of all steam generators09/201412/20140/00/00/0No/100CompletedYes
R8-18Erection of FM bridge and columns011/20141/20150/00/00/0No/0CompletedYes
R8-19Charge start up transformer012/20141/20150/00/00/0No/100CompletedYes
R8-20Delivery of diesel generators09/20111/20150/00/00/0No/0CompletedNo
R8-21Delivery of boiler feed pumps to site 010/20142/20150/00/00/0No/100CompletedYes
R8-22IC Dome completion RB-8011/20143/20150/00/00/0No/100CompletedYes
R8-23Completion of erection of feeders02/20157/20150/00/00/0No/100CompletedYes
R8-24Delivery of shut down cooling pumps to site0/12/20150/00/00/0No/100CompletedNo

  Back