Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
R7-01 | First Pour of Concrete (zero date) | 0 | / | 7/2011 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R7-02 | Placement of PO for Common Service Piping Package | 0 | / | 7/2011 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
R7-03 | Placement of PO for Electrical System Main Plant Package | 0 | / | 8/2011 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
R7-04 | Placement of Work Order for Plant water Package | 0 | / | 3/2012 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
R7-05 | Completion of NB-7 Raft | 0 | / | 4/2012 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R7-06 | Placement of Work Order for NDCT Package | 0 | / | 6/2012 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
R7-07 | Placement of Work Order for IDCT Package | 0 | / | 8/2012 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
R7-08 | Completion of RB-7 100m slab | 0 | 6/2012 | 10/2012 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
R7-09 | Delivery of End Calandria | 0 | / | 6/2013 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R7-10 | Delivery of End shields | 0 | 3/2010 | 6/2013 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R7-11 | Release Calandria Vault for End Shield erection | 0 | / | 6/2013 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R7-12 | Delivery of PCP pumps | 0 | / | 12/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R7-13 | Delivery of Calandria Tubes of site | 0 | / | 1/2014 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R7-14 | Delivery of Coolant Tubes to site | 0 | 10/2011 | 2/2012 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
R7-15 | Completion of erection and wedding of End shields and calandria | 0 | 1/2014 | 3/2014 | 0/0 | 0/0 | 0/0 | Yes | 7/2015 | 100 | Completed | Yes | |
R7-16 | Completion of Calandria tube installation | 0 | / | 5/2014 | 0/0 | 0/0 | 0/0 | Yes | 11/2015 | 0 | Completed | No | |
R7-17 | Delivery of PCP motors | 0 | 1/2014 | 6/2014 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
R7-18 | Release of CB 111M for Control and Instrumentation works | 0 | / | 7/2014 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R7-19 | Delivery of Steam Generators | 0 | 1/2014 | 7/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R7-20 | Release SG vaults for steam Generator erection | 0 | 8/2013 | 7/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R7-21 | Delivery of FM bridge and columns | 0 | 9/2010 | 9/2014 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
R7-22 | Completion of coolant channel installation | 0 | 5/2014 | 9/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R7-23 | Erection of all steam generators | 0 | 7/2014 | 10/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R7-24 | Erection of FM bridge and columns | 0 | 9/2014 | 11/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R7-25 | Charge Start up transformer | 0 | 10/2014 | 11/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R7-26 | Delivery of diesel generators | 0 | 8/2014 | 11/2014 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
R7-27 | Delivery of Turbine Generator | 0 | 8/2014 | 12/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R7-28-D | Commissioning of plant water pump house | 0 | 11/2014 | 12/2014 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R7-29 | IC Dome completion RB-7 | 0 | 9/2014 | 1/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R7-30 | Commision DM Plant | 0 | 3/2015 | 4/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R7-31 | Complete erection of feeders | 0 | 12/2014 | 5/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R7-32 | Commission Compressors | 0 | 7/2015 | 8/2015 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R7-33 | Completion of Hydro test of PHT system | 0 | 2/2016 | 2/2016 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R7-34 | Completion of Hot Conditioning | 0 | 5/2016 | 5/2016 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R8-01 | First pour of concrete | 0 | / | 9/2011 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R8-02 | Completion of NB-8 Raft | 0 | / | 6/2012 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R8-03 | Completion of RB-8 100M slab | 0 | / | 12/2012 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |
R8-04 | Delivery of Calandria | 0 | / | 8/2013 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R8-05 | Delivery of end shields | 0 | / | 8/2013 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
R8-06 | Release Calandria vault for end shield erection | 0 | 2/2013 | 9/2013 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R8-07 | Delivery of PCP pumps | 0 | 6/2010 | 2/2014 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
R8-08 | Delivery of Calandria tubes to site | 0 | / | 3/2014 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R8-09 | Delivery of Coolant tubes to site | 0 | 10/2013 | 4/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R8-10 | Completion of erection and welding of end shields and calandria | 0 | 2/2014 | 5/2014 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R8-11 | Completion of calandria tube installation | 0 | 5/2014 | 7/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R8-12 | Delivery of PCP motors | 0 | 3/2014 | 8/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R8-13 | Delivery of Steam generators | 0 | 3/2014 | 9/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R8-14 | Release SG vaults for steam generator erection | 0 | 10/2013 | 9/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R8-15 | Delivery of FM bridge and Columns | 0 | / | 11/2014 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R8-16 | Completion of coolant channel installation | 0 | 7/2014 | 11/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R8-17 | Erection of all steam generators | 0 | 9/2014 | 12/2014 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R8-18 | Erection of FM bridge and columns | 0 | 11/2014 | 1/2015 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
R8-19 | Charge start up transformer | 0 | 12/2014 | 1/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R8-20 | Delivery of diesel generators | 0 | 9/2011 | 1/2015 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
R8-21 | Delivery of boiler feed pumps to site | 0 | 10/2014 | 2/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R8-22 | IC Dome completion RB-8 | 0 | 11/2014 | 3/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R8-23 | Completion of erection of feeders | 0 | 2/2015 | 7/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | |
R8-24 | Delivery of shut down cooling pumps to site | 0 | / | 12/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | |