Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
R8-28 | Achieve first criticality of RAPP-8 | 0 | 9/2016 | 9/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | |
R7-35 | Fuel Loading | 0 | 5/2016 | 6/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | |
R7-36 | Achieve first criticality of RAPP-7 | 0 | 7/2016 | 7/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | |
R7-37 | 1st synchronisation of RAPP-7 | 0 | 9/2016 | 9/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | |
R7-38 | Commencement of commercial operation of RAPP-7 | 0 | 1/2017 | 1/2017 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | |
R8-25 | Completion of hydro test of PHT system | 0 | 4/2016 | 4/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | |
R8-26 | Completion of Hot conditioning | 0 | 7/2016 | 7/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | |
R8-27 | Fuel loading | 0 | 7/2016 | 8/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | |
R8-29 | 1st synchronisation of RAPP-8 | 0 | 11/2016 | 11/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | |
R8-30 | Commencement of commercial operation of RAPP-8 | 0 | 3/2017 | 3/2017 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | |