![]() | Milestone Summary For Project | ![]() | |||||||||||
Sector Name : | COAL. | ||||||||||||
Agency Name : | SOUTH-EASTERN COAL FIELDS LIMITED. | ||||||||||||
Project Name : | PELMA OCP(15.00MTY). |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
N06000045 | Notification u/s 11(i) of CBA Act for land acquisition. | 0 | 4/2011 | 9/2011 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No |