Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
P10 | Achievement of rated production. | 0 | 4/2022 | 3/2023 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
P11 | Conducting Gram Sabha under FRA 2006. | 0 | 4/2017 | 3/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | |
P12 | Issuance of notice for conducting Gram Sabha for one no. of village under FRA 2006. | 0 | 4/2018 | 3/2021 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | |
P2 | Environmental Clearance. | 0 | 12/2014 | 8/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
P3 | Forest Clearance. | 0 | 12/2014 | 8/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
P4 | Physical possession of land | 0 | 12/2014 | 3/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | |
P5 | Construction of CHP including Silo | 0 | 4/2017 | 3/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
P6 | Construction of Residential building. | 0 | 4/2017 | 3/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
P7 | Construction of Workshop | 0 | 4/2017 | 3/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
P8 | Construction of Wharf wall siding | 0 | 4/2017 | 3/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
P9 | Commissioning of In-pit conveyor transport system | 0 | 4/2021 | 3/2023 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |