Milestone Summary For Project | |||||||||||||
Sector Name : | COAL. | ||||||||||||
Agency Name : | WESTERN COAL FIELDS LIMITED. | ||||||||||||
Project Name : | UKNI DEEP OC. |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
1 | Acquisition and physical possession of non-forest land | 0 | 4/2019 | 3/2021 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No |